Scope of Services - Halfmoon Bridge Tectonic R1
resolution
22 pages
Meeting: portal event 927 (no meeting page on file)
Agenda item: Proposed Resolutions — Consider authorizing the Village Manager to accept Sections 1 through 8 of the proposal from Tectonic Engineering of Rocky Hill, Connecticut, to provide consulting and engineering design services related to the reconstruction of the Half Moon Bay Bridge.
Resolution, 22 pages. Attached to agenda item: “Proposed Resolutions — Consider authorizing the Village Manager to accept Sections 1 through 8 of the proposal from Tectonic Engineering of Rocky Hill, Connecticut, to provide consulting and engineering design services r”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
Resolution 29-2024 Half Moon Bay Bridge Consulting Services
Extracted text
Scope of Services (SOS)
Section 1 - General
1.01
Project Description and Location
Project Name: Half Moon Bay Bridge (BIN 2270050) Reconstruction Project
PIN:8763.05
Project Description: In order to address past safety flags and inspections, the Village is moving
ahead with the rehabilitation/reconstruction of the Half Moon Bay Bridge. The consultant is
expected to perform inspections, prepare a report and present options for this renovation.
Project Limits: The project limit to be considered is the entire area around the bridge structure as
well as both approaches. The total distance is approximately 240 linear feet from the intersection
of Elliot Way to the approach past the eastern abutment.
Sponsor: Village of Croton-on-Hudson
Town of Cortlandt
Westchester County
The anticipated start date of preliminary design: February, 2024
The anticipated letting date: November 2024 (dependent on coordination with railroad)
The construction completed date. April 2026
The anticipated design costs. $ 200,000
The anticipated construction costs $ 1,500,000 (preliminary estimate only, subject to change)
1.02
Project Manager
The Sponsor’s Project Manager for this project is Frank Balbi, P.E., Superintendent of Public
Works, who can be reached at (914) 271-3775, or fbalbi@crotononhudson-ny.gov.
All correspondence to the Sponsor should be addressed to 1 Van Wyck Street, Croton-on-Hudson,
NY 10520. The use of email shall be appropriate unless original documents are required.
The Project Manager should receive copies of all project correspondence directed other than to the
Sponsor.
1.03
Project Classification
This project is assumed to be a Class II action under USDOT Regulations, 23 CFR 7711.
Classification under the New York State Environmental Quality Review Act (SEQRA) Part 617,
Title 6 of the Official Compilation of Codes, Rules, and Regulations of New York State (6 NYCRR
Part 617) is assumed to be Type II.
1.04
Categorization of Work
Project work is generally divided into the following sections:
Section 1
General
Section 2
Data Collection & Analysis
Section 3
Preliminary Design
Section 4
Environmental
1 http://www.ecfr.gov/cgi-
bin/textidx?c=ecfr&SID=d21c8e6f33a02787d9b788103bac7b9d&rgn=div5&view=text&node=23:1.0.1.8.43&idno=23
Section 5
Right-of-Way
Section 6
Detailed Design
Section 7
Advertising, Bid Opening, and Award
Section 8
Construction Support
Section 9
Construction Inspection
Section 10
Estimating & Technical Assumptions
When specifically authorized in writing to begin work, the Consultant will render all services and
furnish all materials and equipment necessary to provide the Sponsor with reports, plans, estimates,
and other data specifically described in Sections 1, 2, 3, 4, 5, 6, 7, 8, 9 and 10. [Note: Retain the
list of all sections above and on the last line only select the sections which will be retained in
the SOS Document]
1.05
Project Familiarization
The Sponsor will provide the Consultant with the following information:
•
Approved project initiation document (Initial Project Proposal or similar documentation) indicating
project type, project location, cost estimate, schedule, and fund source(s).
•
Transportation needs.
•
Accident records and history.
•
Most recent bridge inspection and condition report, NYSDOT weighted-average bridge condition
rating, FHWA sufficiency rating, and NYSDOT Bridge Management System rating.
•
Record plans.
•
Anticipated permits and approvals (initial determination).
•
Available project studies and reports.
•
Other relevant documents pertaining to the project.
The Consultant will become familiar with the project before starting any work. This includes a
thorough review of all supplied project information and a site visit to become familiar with field
conditions.
1.06
Meetings
The Consultant will prepare for and attend all meetings as directed by the Sponsor’s Project
Manager. Meetings may be held to:
•
Present, discuss and receive direction on the progress and scheduling of work in this contract.
•
Present, discuss, and receive direction on project specifics.
•
Discuss and resolve comments resulting from the review of project documents, advisory agency
review, and coordination with other agencies.
•
Preview visual aids for public meetings.
•
Manage subconsultants and subcontractors.
The Consultant will be responsible for the preparation of all meeting minutes; the minutes will be
submitted to meeting attendees within one (1) week of the meeting date.
1.07
Cost and Progress Reporting
For the duration of this contract, the Consultant will prepare and submit to the Sponsor on a
monthly basis a Progress Report in a format approved by the Sponsor. The Progress Report must
contain the Cost Control Report.2 The beginning and ending dates defining the reporting period
2 https://www.dot.ny.gov/plafap/view-document?id=1598
must correspond to the beginning and ending dates for billing periods so that this reporting process
can also serve to explain billing charges. (In cases where all work under this contract is officially
suspended by the Sponsor, this task will not be performed during the suspension period.) Generally
the Cost Control Report will be submitted as part of the monthly invoicing.
1.08
Policy and Procedures
•
The design of this project will be progressed in accordance with the current version of the
NYSDOT Local Projects Manual (LPM)3 including the latest updates.
•
If there are conflicts between local policies and procedures and those listed in the LPM those
listed in the LPM take precedence.]
1.09
Standards & Specifications
The project will be designed and constructed in accordance with the current edition of the NYSDOT
Standard Specifications for Construction and Materials, including all applicable revisions.
1.10
Subconsultants
The Consultant will be responsible for:
•
Coordinating and scheduling work, including work to be performed by subconsultants.
•
Technical compatibility of a sub-consultant's work with the prime consultant’s and other
subconsultants’ work.
1.11
Subcontractors
The procurement of subcontractors must be in accordance with the requirements set forth in the
NYSDOT LPM.
Section 2 - Data Collection and Analysis
2.01
Design Survey
A.
Ground Survey
The Consultant will provide terrain data required for design by means of a topographic field
survey. Boundary Survey is explicitly excluded from the scope of services. Approximately
property lines, boundary and right of way lines will be identified from available mapping
and shall be considered approximate.
B.
Photogrammetric Survey
Intentionally Left Blank
C. Stream Survey
Intentionally Left Blank
D.
Survey of Wetland Boundaries
Intentionally Left Blank
E.
Supplemental Survey
3 https://www.dot.ny.gov/plafap
9 https://www.dot.ny.gov/portal/pls/portal/MEXIS_APP.EI_EB_DOC_DETAILS.show?p_arg_names=doc_id&p_arg_values=10618
The Consultant will provide supplemental surveys when needed for design purposes and to
keep the survey and mapping current.
F.
Standards
The survey will be done in accordance with the standards set forth in the NYSDOT Land
Surveying Standards and Procedures Manual4 and in accordance with local standards
described in Section 10 of the SOS.
2.02
Design Mapping
The Consultant will provide the following design mapping:
•
1:2500 scale mapping (large-scale projects only).
•
1:250 scale mapping with 0.5 meters or 2-foot contour intervals.
The Consultant will provide supplemental mapping when needed for design purposes and keep
the mapping current for the duration of the project.
2.03
Determination of Existing Conditions
The Consultant will determine, obtain or provide all information needed to accurately describe in
pertinent project documents the existing conditions within and adjacent to the project limits.
2.04
Accident Data and Analysis
The Sponsor will provide accident records for the last three years for roads within the project limits
plus one-tenth of a mile immediately outside of the project limits. The Consultant will prepare
collision diagrams and associated summary sheets and note any clusters of accidents or patterns
implying inadequate geometrics, or other safety problems, within the project limits. A formal
accident analysis is not required.
2.05
Traffic Counts
Intentionally Left Blank
2.06
Capacity Analysis
Intentionally Left Blank
2.07
Future Plans for Roadway and Coordination with Other Projects
Intentionally Left Blank.
2.08
Soil Investigations
Intentionally Left Blank
2.09
Hydraulic Analysis
Intentionally Left Blank
2.10
Bridges to be rehabilitated
A. Inspection
The Consultant will perform an in depth field inspection of each bridge to determine its
condition, to establish the rehabilitation work necessary, and to prepare a Level I
load rating. The intent is to supplement the inspection done as part of NYSDOT’s
4 https://www.dot.ny.gov/divisions/engineering/design/design-services/land-survey/repository/LSSPM09.pdf
on-going bridge inspection program, not to duplicate it.
The Consultant will perform and document the findings of in-depth inspection of each
bridge in accordance with the current AASHTO “Manual for Condition Evaluation of
Bridges.”
B. Bridge Deck Evaluation
For Bridges in which the deck will be rehabilitated, the Consultant will perform a bridge deck
evaluation in accordance with NYSDOT Bridge Deck Evaluation Manual5 and NYSDOT
Bridge Inspection Manual.6
The existing deck has an asphalt overlay which limits information that can be gathered.
Sounding and potential evaluation techniques will not be used on the top of the deck. The
evaluation of the top will be visual only.
C. Load Rating of Existing Bridge
The Consultant will perform a Level 1 load rating of each existing bridge in accordance with
NYSDOT’s Uniform Code of Bridge Inspection. Immediately upon completion, the
Consultant will transmit two copies of the load rating calculations and summary sheets to
the Sponsor and the Regional Local Projects Liaison for filing.
D. Fatigue Evaluation
The Consultant will analyze, in accordance with the current AASHTO Guide Specification
for Fatigue Evaluation of Existing Bridges, those metal structural elements which will or
may be retained in the rehabilitated bridge. Where this guide specification does not apply
(e.g., severe corrosion, mechanical damage, repaired fatigue damage, wrought iron instead
of steel, etc.), the Consultant will develop an appropriate approach for comprehensive
fatigue evaluation while maintaining close coordination with the Sponsor for guidance and
input. The Consultant will then conduct the evaluation accordingly.
For situations where the calculated remaining safe life is less than the planned remaining
service life, the Consultant will develop various conceptual strategies to improve fatigue
performance and/or safely manage the risk. The Consultant will prepare and submit to the
Sponsor a technical memorandum documenting the relative advantages, disadvantages, and
approximate costs of each strategy along with specific recommendations.
The Sponsor will determine the strategy to be adopted.
For situations where the calculated remaining safe life is equal to or greater than the planned
remaining service life, the Consultant will prepare and submit to the Sponsor a technical
memorandum documenting the results of the fatigue evaluation.
2.11
Pavement Evaluation
•
Intentionally Left Blank
Section 3 - Preliminary Design
3.01
Design Criteria
5 https://www.dot.ny.gov/divisions/engineering/structures/repository/manuals/br_deck_manual/bridge_deck_eval_manual_1992.pdf
6 https://www.dot.ny.gov/divisions/engineering/structures/manuals/bridge-inspection
The Consultant will identify the applicable design standards to be used for this project and will
establish project-specific design criteria in accordance with the NYSDOT Project Development
Manual7
The Sponsor will approve the selected project design criteria and will obtain NYSDOT
concurrence (either by written submission or at a meeting).
Based on the selected design criteria, the Consultant will identify all existing non-standard features
that are within and immediately adjacent to the project limits. Non-standard features that correlate
with a high accident rate will be noted.
3.02
Development of Alternatives
A. Selection of Design Alternative(s)
The Consultant will identify and make rudimentary evaluations of potential design
alternative concepts that would meet the Sponsor’s defined project objectives. These
evaluations are not to be carried beyond the point of establishing the feasibility of each
concept as a design alternative; only those significant environmental and geometric design
constraints that bear on the feasibility should be identified.
For each concept the Consultant will prepare rudimentary sketches of plan, profile, and
typical section views which show:
•
On plan: proposed centerlines; pavement edges; curve radii and termini; and
existing approximate ROW limits.
•
On profile: theoretical grade lines; critical clearances; vertical curve data; grades;
and touchdown points.
•
On typical section: lane, median, and shoulder widths; ditches; gutters; curbs; and
side slopes.
•
Where necessary: important existing features.
•
Where pertaining to feasibility: significant environmental and geometric design
constraints, labeled as such.
These sketches will include only the minimum information needed to select design
alternatives to be studied in further detail.
The Consultant will meet with the Sponsor to discuss the concepts, using the sketches as
discussion aids to describe the relative order-of-magnitude costs, advantages, disadvantages,
and problem areas of each. From these concepts, the Sponsor will select one or in some cases
more, design alternative(s) for further development.
B. Detailed Evaluations of Alternative(s)
The Consultant will further evaluate the selected design alternative and the null alternative
with specific engineering analyses and considerations. Analyses will be conceptual and
limited to determining the relative suitability of each design alternative, and will include:
•
Design geometry, including the identification and comparison of alignment constraints
and (where applicable) justification for retaining nonstandard design features, per the
NYSDOT Highway Design Manual.8
•
Environmental constraints and potential environmental impact mitigation measures
(identified under Section 4 tasks).
7 https://www.dot.ny.gov/divisions/engineering/design/dqab/pdm
8 https://www.dot.ny.gov/divisions/engineering/design/dqab/hdm
•
Traffic flow and safety considerations, including signs, signals, and level of service
analysis for intersections.
•
Pavement.
•
Structures, including bridges, retaining walls, major culverts, and building alterations
(limited to establishing basic concepts, accommodating clearances and streamflow, and
estimating costs). Bridge investigative work (inspection, deck coring, etc.) is covered
under Section 2.
•
Drainage.
•
Maintenance responsibility.
•
Maintenance and protection of traffic during construction.
•
Soil and foundation considerations.
•
Utilities.
•
Railroads.
•
Right-of-way acquisition requirements.
•
Conceptual landscaping (performed by a Registered Landscape Architect).
•
Accessibility for pedestrians, bicyclists and the disabled.
•
Lighting.
•
Construction cost factors.
The Consultant will prepare the following drawings for each design alternative analyzed:
•
1:250 plans showing (as a minimum) stationed centerlines; roadway geometrics; major
drainage features; construction limits; cut and fill limits; and proposed right-of-way
acquisition lines.
•
Profiles, at a scale of 1:250 horizontal and 1:50 (maximum) vertical, showing (as a
minimum) the vertical datum reference; significant elevations; existing ground line;
theoretical grade line; grades; vertical curve data including sight distances; critical
clearances at structures; centerline stations and equalities; construction limits; and
superelevation data.
•
Typical sections showing (as a minimum) lane, median, and shoulder widths; ditches;
gutters; curbs; and side slopes.
3.03
Cost Estimates
The Consultant will develop, provide and maintain a cost estimate for each design alternative.
The Consultant will update the estimate periodically and as necessary to incorporate significant
design changes.
3.04
Preparation of Draft Design Approval Document
For this project, the Design Approval Document (DAD) will be a Design Report.
The Sponsor will make all determinations not specifically assigned to the Consultant which are
needed to prepare the Draft DAD.
The Consultant will prepare a Draft DAD, which will include the results of analyses and/or studies
performed in other Sections of this document. The DAD will be formatted as specified in the
NYSDOT Project Development Manual (PDM).9
9 https://www.dot.ny.gov/divisions/engineering/design/dqab/pdm
The Consultant will submit three copies of the Draft DAD to the Sponsor for review. The
Sponsor will review the Draft DAD and provide the Consultant with review comments. The
Consultant will revise the Draft DAD to incorporate the comments.
The Consultant will revise the DAD to reflect NYSDOT and/or FHWA comments. The Sponsor
will sign the cover sheet and submit 3 copies of the revised report to the NYSDOT for signature by
the FHWA.
3.05
Advisory Agency Review
Intentionally Left Blank.
3.06
Public Information Meeting(s) and/or Public Hearing(s)
A
Public Information Meeting(s)
The Consultant will assist the Sponsor at three public information meeting(s) with advisory
agencies, local officials, and citizens, at which the Consultant will provide visual aids and
present a technical discussion of the alternatives.
The Sponsor will arrange for the location of public information meeting(s). The Consultant
will assist the Sponsor with appropriate notification.
B.
Public Hearing(s)
Intentionally Left Blank.
3.07
Preparation of Final Design Approval Document (DAD)
The Sponsor will obtain all necessary approvals and concurrences and will publish all applicable
legal notices.
The Consultant will prepare the Design Recommendation, and will modify the DAD to include
the Design Recommendation, re-title the DAD in accordance with the PDM Manual, and update
existing conditions and costs as necessary. The Consultant will incorporate changes resulting from
the advisory agency review and all public information meetings and public hearings.
The Consultant will submit three copies of the Final DAD to the Sponsor for review. The Sponsor
will review the Final DAD and provide the Consultant with review comments. The Consultant
will revise the Final DAD to incorporate the comments.
The Sponsor will submit three copies of the Final DAD to NYSDOT for a Final Environmental
Determination. NYSDOT will make the determination or obtain FHWA’s determination. If
necessary, NYSDOT will transmit the Final DAD to FHWA for final review and concurrence. The
Consultant will again revise the Final DAD to incorporate changes (assumed minor) resulting from
the NYSDOT and/or FHWA review.
The Sponsor will grant or obtain, from or through NYSDOT, Design Approval.
Section 4 – Environmental
Tectonic shall perform all work in accordance with the NYSDOT Project Development Manual
(PDM), and the NYSDOT The Environmental Manual (TEM)10 and Chapter 7 of the LPM. S
10 https://www.dot.ny.gov/divisions/engineering/environmental-analysis/manuals-and-guidance/epm
Specifically for Lead-based paint (LBP) and asbestos, Tectonic shall refer to the following: TEM
4.4.20: Contaminated Materials and Hazardous Substances and 4.4.19: Asbestos Management.
4.01
Asbestos Material Assessment & Report
Tectonic has reviewed the asbestos survey report prepared by QuES&T on October 26, 2016 for
the upper bridge deck, along the roadway of Half Moon Bay Dr., and has determined an additional
survey for the remaining areas of the bridge is required. All asbestos work, including reporting and
obtaining variances, shall be performed in accordance with the DOT Specifications 4.4.19:
ASBESTOS MANAGEMENT. Tectonic shall provide a track-trained, asbestos inspector certified
by the New York State Department of Labor (NYSDOL), to perform all bulk sampling and
inspection services in accordance with the following regulations:
•
USEPA Guidance for Controlling Asbestos-Containing Materials in Bridges (EPA
Purple Book);
•
USEPA Guidance effective June 4, 2013 titled, “Bulk Sampling for Asbestos”;
•
USEPA, 40 Code of Federal Regulations (CFR), Part 763, Asbestos; and
•
Part 56 of Title 12 of the Official Compilation of Codes, Rules, and Regulations
of the State of New York (CR 56).
To the extent feasible, prior to mobilizing to the site, Tectonic personnel shall review available
plans or drawings and any existing documentation to identify any materials specified as asbestos-
containing and/or any suspect materials that may be present.
The asbestos survey will be conducted in all areas of the existing structure, starting at the lowest
level and entering all accessible spaces. The Client will supply a means, in accordance with
Occupational Safety and Health Administration (OSHA), for accessing the sampling locations
(including ladders or aerial lifts to access the underside of the bridge span). Destructive sampling,
to determine if suspect materials are present will be performed as needed. The patching of sampling
locations will not be performed. As such, bulk samples will be collected from inconspicuous
locations when possible.
Suspect materials will be categorized into homogeneous materials based on color, texture and if
ascertainable date of installation. Representative samples from each homogenous group within the
impacted area(s) shall be collected according to recognized protocols. The inspection process will
focus on identifying the locations and quantities of the following types of materials: (1) surfacing
materials, (2) thermal system insulation (TSI) and (3) miscellaneous materials. The number of
samples collected for each type of material and the analytical procedure shall be in accordance with
EPA 40 CFR Part 763.86, Asbestos – Sampling, EPA Guidance document, and CR 56.
For all suspected materials sampled, a sketch of each homogeneous sampling area will be drawn.
A unique sample ID number will be assigned to each sample collected and recorded on the COC
form. Samples will be shipped via standard COC protocol to a NYSDOH ELAP accredited
laboratory for analysis.
If the inspector deems an area inaccessible, such as confined spaces, elevated locations, electrically
charged locations, or other areas that may be otherwise unsafe to enter, the areas and any potential
suspect ACM typically found in these areas will be recorded by the inspector and noted as presumed
ACM.
Analysis will be performed on each of the groups and when a positive result is found, analysis for
that group will stop. Bulk samples will be analyzed for asbestos fibers at a NYSDOH ELAP
accredited laboratory by polarized light microscopy (PLM) according to the "Interim Method for
the Determination of Asbestos in Bulk Insulation Samples" issued by the USEPA/EMSL, Research
Triangle Park, North Carolina.
In the event Non-Friable Organically Bound (NOB) materials are sampled, (i.e., mastics, caulks,
flashing, etc.) the organic material will be reduced by gravimetric reduction and read via PLM.
Should the PLM analysis show <1 % asbestos by weight, confirmation analysis via Transmission
Electron Microscopy (TEM) will be performed.
If the laboratory determines that vermiculite is present in any of the surfacing material samples (i.e.
sprayed-on fireproofing, plaster, etc.), the samples will be subjected to the NYSDOH approved
analysis method for Sprayed on Fireproofing / Surfacing Material containing Vermiculite (SOF-
V/SM-V).
Tectonic has assumed the sampling shall occur outside of normal business hours (weekends and/or
nights) by one (1) inspector and Staff Geologist, as needed, in (1) day. Additionally, Tectonic will
invoice the Client for the actual number of samples collected and analyzed by the laboratory.
Asbestos Survey Report
Based on the results of our asbestos survey, our certified personnel will prepare site specific
documents that detail the methods and procedures to be followed to complete the asbestos
abatement. This will include plans of ACM locations and will also include the preparation of Work
Practice Applications for submittal to the Client.
4.02
Lead Based Paint (LBP) – Assessment & Report
Tectonic has reviewed the Limited XRF Lead Testing survey report prepared by QuES&T on
September 22, 2016 for the upper bridge deck, along the roadway of Half Moon Bay Dr., and has
determined an additional survey for the remaining areas of the bridge is required. Tectonic will
provide a track-trained, United States Environmental Protection Agency (USEPA) certified risk
assessor to conduct a lead-based paint (LBP) survey and a surface-by-surface inspection utilizing
a X-ray fluorescence (XRF) spectrum analyzer. The LBP survey will be performed in accordance
with the USEPA regulation 40 CFR Part 745 and all state and local regulations.
Prior to analyzing bridge components with the XRF equipment, a three-point calibration will be
performed in accordance with the National Institute of Standards and Technology (NIST) standard
2573. The following painted surfaces will be tested for the presence of lead (if present):
•
Accessible bridge components (superstructure and substructure).
•
Utilities and supports to be impacted during construction.
•
Any other painted surfaces within the project limits as directed by the Client.
Locations of each XRF reading will be identified with cardinal direction. All sample locations will
be sketched on a sampling map and be identified with a unique sample ID number. Photographs of
sampling locations will be taken.
Tectonic’s inspection team will assess the current conditions of all tested surfaces to determine
paint condition in accordance with EPA guidelines. All inspection work will be based on either
Client direction, or regulatory protocol. Based on the data results, Tectonic will determine which
bridge components tested are to be considered actionable for lead based paint based on the criteria
below or other criteria specified by the Client, if communicated prior to the inspection services.
LEAD-BASED PAINT CRITERIA
Lead Content (mg/cm2)
Determination
< 1.0 mg/cm2
Negative
≥ 1.0 mg/cm2
Positive
Additionally, each XRF reading location will be marked on a Site Sketch and will be identified
using the unique sample ID number. A photograph of each sample location will be taken.
As stipulated by HUD guidelines, painted surfaces having an inconclusive XRF reading can be
assumed to be positive readings. However, the Client can elect to have paint chip samples collected
from inconclusive reading locations in lieu of identifying them as positive. If the Client elects to
have paint chip samples submitted for laboratory analysis, a paint-chip sample of approximately
four (4) square inches shall be collected. Paint-chip samples, when collected, will contain all layers
of paint. For all paint chips sampled, a unique sample ID number will be assigned to each sample
collected and recorded on the chain-of-custody (COC) form. Samples will be shipped via standard
COC protocol to a New York State Department of Health (NYSDOH) Environmental Laboratory
Approval Program (ELAP) accredited laboratory for analysis. Collection and laboratory analysis
of paint chip samples are included in this proposal as an optional service.
Tectonic has assumed the sampling shall occur outside of normal business hours (weekends and/or
nights) by one (1) inspector in one (1) day.
Additionally, Tectonic shall prepare site specific operation and maintenance plans and/or
abatement design documents that detail methods and procedures to be followed for the maintenance
and/or abatement of lead.
4.03
Limitations of Service
The limitations of service shall be as outlined in our contractual agreement upon procurement of
the project and the following:
4.03.1 Our scope of services is limited to those described above. All permit application fees,
Municipal fees, escrow payments, etc. shall be the responsibility of the Client. Making
revisions to the documents as requested by the Municipality, regulatory entities, the various
stakeholders, or the Client are not included. If documentation not within the scope described
above is required during this process, additional fees will be required. The scope of work
and estimated fee related to additional work (including TBD fees in the table below) will be
discussed and agreed upon with the Client before proceeding.
4.03.2 Tectonic assumes all work will be performed during normal business hours (Monday through
Friday 7:00 AM – 5:00 PM). A premium of 1.5 times the normal billing rate will be charged
for time in excess of 8 hours per day, after hours or on holidays or weekends. Tectonic
assumes all work can be performed in OSHA level D PPE. It is not anticipated that respiratory
protection will be necessary during routine sampling activities except in the event that
damaged asbestos is present. Tectonic ACM Inspectors will be equipped with half-mask
respirators equipped with HEPA P-100 filters to be worn whenever potential risk to exposure
to airborne asbestos fibers exists.
4.03.3 The Client is responsible for supplying a man lift and/or ladder and personnel to stabilize the
ladder such that Tectonic personnel can access material sampling points. The Client is
responsible for moving all obstructions associated with access to material sampling locations.
Client responsible for providing lockout/tagout in accordance with OSHA requirements for
the sampling of electrically charged suspect materials.
4.03.4 The Client is responsible for obtaining and providing Tectonic with all necessary clearances,
flagging, access and protections. Tectonic shall coordinate the scheduling.
4.03.5 Please note, per NYSDOL CR 56, the completed asbestos survey for controlled or pre-
demolition asbestos projects should be submitted to the appropriate Asbestos Control Bureau
district office by the bridge owner.
4.03.6 Regulatory liaison services are not included in our scope of services. Except as specified,
revisions to the documents prepared under the scope of work above as requested by the
various regulatory agencies or the Client are not included. If documentation not included in
Section 4 above is required during the review by these entities, this scope will also constitute
additional work. The actual scope of work and associated estimated fee related to the
additional work will be discussed and agreed upon with the Client before proceeding.
4.03.7 Changes to the project design or scope during the prosecution of the work contained in this
proposal after Tectonic receives initial direction from the Client will constitute additional
work. A revised scope of work and estimated fee related to additional effort will be discussed
and agreed upon with the Client before proceeding.
4.03.8 Tectonic will assume no liability for project delays, extra costs, or any and all claims
associated with the sample data if such data is obtained in general accordance with applicable
regulations or Client direction.
4.03.9 Deliverables will be in electronic format (PDF) unless otherwise arranged.
4.03.10 Tectonic has provided unit rates/fees for all ACM and Lead work that will be required, based
on information provided by the client. The amount invoiced will be based on the actual
number of days time the unit rates provided, adjusted for overtime if required. For sampling,
the actual amount invoice will be the actual number of samples collected and tested as
discussed and approved in advance with client. The total of all actual labor and testing
quantities assumed are shown in the attached Environmental Fee Schedule.
4.03.11 For the purpose of this proposal, Tectonic has assumed asbestos removal air monitoring will
be performed by others. Should removal work require containment within a negative pressure
environment such as a tent, air monitoring may be required. Asbestos monitoring services
may be provided at the request of the Client for an additional fee.
4.03.12 For the purpose of this proposal, Tectonic has assumed lead abatement air monitoring will
be performed by others. Lead monitoring services may be provided at the request of the
Client for an additional fee.
Section 4.02 – Fees
Tectonic will provide the above-described scope of work for a pre-abatement work fee of $22,110.00. A
breakdown of the charges is included below:
Item
No.
Descripton
Fee
Estimated
Quantity
Extended
4.01
Asbestos Survey:
NYSDOL Asbestos Inspector (per
weekend day/night rate)
$3,600.00 1
$3,600.00
Survey Report & Abatement Design
$2,500.00 1
$2,500.00
Asbestos Samples:
PLM Bulk - Non-friable (5-day TAT)
$25.00
$750.00
PLM Bulk - Friable (5-day TAT)
$20.00
$600.00
TEM (5-day TAT)
$40.00
$800.00
Sample
Prep.
(For
Non-Friable
Samples Not Analyzed by Laboratory)
$10.00
$300.00
MNR Track Training (per person).
Assumes max four hours to complete.
$500.00
$1,000.00
4.02
Lead-based Paint (LBP) Survey:
USEPA LBP Inspector (includes use of
XRF Spectrum Analyzer & Lead Paint
Chip Samples for inconclusive XRF
results) (per weekend day/night rate)
$4,800.00 1
$4,800.00
Lead-based Paint Letter Report
$1,500.00 1
$1,500.00
MNR Track Training (per person).
Assumes max four hours to complete.
$500.00
$1,000.00
4.01/
4.02
ACM
&
LBP
Permits/Variances
(additional services – if required)
$2,500.00 1
$2,500.00
Geologist / Environmental Scientist (1
personnel–hourly weekend day/night
rate)
$230.00
$1,840.00
Staff
Geologist
/
Environmental
Scientist (hourly office rate)
$115.00
$920.00
TOTAL ESTIMATED COST FOR ITEMS/QUANTITIES LISTED ABOVE: $22,110.00
Section 5 - Right-of-Way
5.01
Abstract Request Map and/or Title Search
Intentionally Left Blank
5.02
Right-of-Way Survey
Intentionally Left Blank
5.03
Right-of-Way Mapping
Intentionally Left Blank
5.04
Right-of-Way Plan
Intentionally Left Blank
5.05
Right-of-Way Cost Estimates
Intentionally Left Blank
5.06
Public Hearings/Meetings
Intentionally Left Blank
5.07
Property Appraisals
Intentionally Left Blank
5.08
Appraisal Review
Intentionally Left Blank
5.09
Negotiations and Acquisition of Property
Intentionally Left Blank
5.10
Relocation Assistance
Intentionally Left Blank
5.11
Property Management
Intentionally Left Blank
Section 6 - Detailed Design
6.01
Preliminary Bridge Plans
A.
New and Replacement Bridges
Intentionally Left Blank
B.
Bridge Rehabilitations
For each bridge to be rehabilitated, the Consultant will prepare and submit to the Sponsor for
review a Preliminary Bridge Rehabilitation Plan, which will be sufficiently developed to:
• Show basic concepts and major details (including all existing and proposed
utilities).
• Acquaint affected parties with the project and project components.
• Serve as an instrument for initial approval.
• Provide a basis for the development of final plans.
The plan should indicate maintenance and protection of traffic provisions and be
accompanied by a cost estimate.
C.
Selected Structural Treatment
The Consultant will modify the Structure Justification Report, Preliminary Bridge Plan
and/or Preliminary Bridge Rehabilitation Plan to incorporate Sponsor review comments.
The Sponsor will approve the selected structural treatment and will obtain NYSDOT
concurrence (either by a written submission or at a meeting).
6.02
Advance Detail Plans (ADP)
The Consultant will develop the approved design alternative to the ADP stage. At this stage, all
plans, specifications, estimates and other associated materials will be 90% complete.
As part of this task, the Consultant will prepare templated cross-sections at 50 foot intervals.
Advance Detail Plans will be in accordance with Chapter 21 of the NYSDOT Highway Design
Manual.11
The Consultant will prepare and submit three copies of the ADP's to the Sponsor for review. The
Consultant will modify the design to reflect the review of the ADP package.
6.03
Contract Documents
The Consultant will prepare a complete package of bid-ready contract documents. The package
will include:
•
Instructions to bidders.
•
Bid documents.
•
Contract language, including applicable federal provisions and prevailing wage rates.
•
Special notes.
•
Specifications.
•
Plans.
•
A list of supplemental information available to bidders (i.e., subsurface exploration logs,
record as-built plans, etc.).
•
Other pertinent information.
The Consultant will submit the contract documents to the Sponsor for approval. Upon approval,
the Sponsor will submit 3 copies of the contract bid documents to NYSDOT as described in the
LPM.
6.04
Cost Estimate
The Consultant will develop, provide, and maintain the construction cost estimate for the project.
The Consultant will update the estimate periodically and as necessary to incorporate significant
design changes and will develop and provide the final Engineer's Estimate, including all quantity
computations.
6.05
Utilities
The Consultant will coordinate with affected utility companies to ensure the timely relocation of
utility poles and appurtenances. The Consultant will assist the Sponsor in preparing any necessary
agreements with utility companies. Any agreements containing reimbursable relocations must be
approved and signed by the Design Support Section of the NYSDOT Design Quality Assurance
Bureau (see LPM Appendix 10-8).
6.06
Railroads
The Consultant will coordinate with affected railroads and will assist the Sponsor in preparing all
necessary Railroad Agreements.
6.07
Bridge Inventory and Load Rating Forms
The Consultant will complete and provide the Sponsor and NYSDOT with:
• Inventory Update forms, per the current NYSDOT Bridge Inventory Manual for Bridge Inventory
11 https://www.dot.ny.gov/divisions/engineering/design/dqab/hdm/hdm-repository/Chapt_21.pdf
and Inspection System, reflecting all proposed physical changes resulting from construction.
• Level 2 Load Rating Data Input forms, per NYSDOT User Manual for Structural Rating Program
for Bridges and current NYSDOT guidance on the "Procedure for Inventorying, Inspecting, and
Level 2 Load Rating, New, Replacement and Reconstructed or Rehabilitated Bridges".
6.08
Information Transmittal
Upon completion of the contract documents, the Consultant will transmit to the Sponsor all project
information, including electronic files. The electronic information will be in the format requested
by the Sponsor.
Section 7 - Advertisement, Bid Opening and Award
7.01
Advertisement
The Consultant will prepare the advertisement for bids to be placed in the NYS Contract Reporter
and any other newspaper or publication identified by the Sponsor. The Consultant will submit
the ad(s) to the Sponsor for review and will revise the ad(s) to reflect comments generated by that
review. Upon approval by the Sponsor, the Consultant will place the advertisements.
Advertisements must not be placed until authorization is granted to the Sponsor by the NYSDOT.
7.02
Bid Opening (Letting) and Award
The Consultant will analyze the bid results. The analysis will include:
• Verifying the low bidder mathematical calculations.
• Ensuring receipt of all required bid documents (non-collusive bid certification, debarment history
certification, etc.).
• Breaking the low bid into fiscal shares, if necessary.
• Determining whether the low bid is unbalanced.
• For pay items bid more than 25% over the Engineer’s Estimate:
Check accuracy of quantity calculations.
Review the appropriateness of price bid for work in the item.
Review the low bidder qualifications to perform the work.
Prepare a summary letter.
The Consultant will assist the Sponsor in preparing and compiling the package of information to
be transmitted to the NYSDOT.
The Sponsor will award the contract and will transmit the award package to the NYSDOT as
described in the Procedures for Locally Administered Federal Aid Projects (LPM).
Section 8 - Construction Support
The Consultant will provide design response to unanticipated or changed field conditions, analyze
and participate in proposed design changes, and interpret design plans.
Work under this section will always be in response to a specific assignment from the Sponsor
under one of the tasks below:
• In response to unanticipated and/or varying field conditions or changes in construction procedures,
the Consultant will conduct on-site field reconnaissance and, where required, prepare Field
Change Sheets modifying pertinent contract plan sheets.
• The Consultant will analyze and make recommendations on the implementation of changes
proposed by the Sponsor or the construction contractor. This includes the Traffic Control Plan.
• The Consultant will interpret and clarify design concepts, plans and specifications.
• The Consultant will review and approve shop drawings for construction.
Not reimbursable under this Section are:
•
Corrections of design errors and omissions
•
Straightforward interpretations of plans and designer intentions
Section 9 - Construction Inspection
9.01
Equipment
The Contractor will furnish office space and basic office furnishings for the Consultant, as part
of the contract.
The Consultant will furnish all other office, field and field laboratory supplies and equipment
required to properly perform the inspection services listed below.
9.02
Inspection
The Consultant must provide, to the satisfaction of the Sponsor, contract administration and
construction inspection services from such time as directed to proceed until the completion of the
final agreement and issuance of final payment for the contract. The Consultant must assume
responsibility, as appropriate, for the administration of the contract including maintaining complete
project records, processing payments, performing detailed inspection work and on-site field tests
of all materials and items of work incorporated into the contract consistent with federal policies
and the specifications and plans applicable to the project.
9.03
Municipal Project Manager
This Project Manager will be the Municipality’s official representative on the contract and the
Consultant must report to and be directly responsible to said Project Manager.
9.04
Ethics
Prior to the start of work, the Consultant will submit to the Sponsor a statement regarding conflicts
of interest.
9.05
Health and Safety Requirements
The Consultant must provide all necessary health and safety related training, supervision,
equipment and programs for their inspection staff assigned to the project.
9.06
Staff Qualifications and Training
The Consultant must provide sufficient trained personnel to adequately and competently perform
the requirements of this agreement. The Consultant will recommend inspectors to the Sponsor for
approval prior to their assignment to the project. Resumes, proof of required certification and the
proposed initial salary shall be furnished. The Sponsor may want to interview before approval, and
reserves the right to disapprove any application. The employment of all consultant personnel is
conditional, subject to satisfactory performance, as determined by the Sponsor.
For all construction inspection agreements, it is mandatory that all technician personnel be
identified by the National Institute for Certification in Engineering Technologies (NICET)
certification levels in the staffing tables. In addition, all Transportation Engineering Technicians-
Construction assigned to the project at and above level III, Engineering and Senior Engineering
Technicians, must be certified by NICET. Transportation Engineering Technicians-Construction
below level III assigned to the project must have successfully completed the General Work Element
requirements and at least those Special Work Elements which apply to their specific project
assignments at the level of their rating.
In lieu of the NICET certification requirements, the Sponsor may accept evidence that the person
proposed for employment (1) has satisfactorily performed similar duties as a former NYS
Department of Transportation (NYSDOT) employee or (2) has a combination of education and
appropriate experience commensurate with the scope of the position in question.
Technicians employed by the consultant that perform field inspection of Portland cement concrete
shall possess a current certification from the American Concrete Institute (ACI) as a Concrete field-
testing Technician-Grade 1, or have completed all of the following NICET work elements, which
are equivalent to the ACI certification:
NICET
NICET
NICET
LEVEL
CODE
WORK ELEMENT
I
Sample Fresh Concrete
I
Slump Test
II
Air Content, Pressure
II
Air Content, Gravimetric
II
Air Content, Volumetric
II
Field Prepared Test Specimens
Inspectors designated as the responsible person in charge of work zone traffic control must have
sufficient classroom training, or a combination of classroom training and experience, to develop
needed knowledge and skills. Acceptable training should consist of a formal course presented by
a recognized training program which includes at least two full days of classroom training. A
minimum of two days classroom training is normally required, although one day of classroom
training plus responsible experience may be considered. Recognized training providers include
American Traffic Safety Services Association (ATSSA), National Safety Council (NSC), Federal
Highway Administration’s National Highway Institute (FHWA-NHI), and accredited colleges and
universities with advanced degree programs in Civil/Transportation/Traffic Engineering. Former
DOT employees may be considered on the basis of at least one day of formal classroom training
combined with responsible M&PT experience.
Technicians employed by the consultant who perform field inspection of geotechnical construction
(earthwork), including, but not limited to embankment construction, subbase placement, structure
and culvert backfill placement, and testing of earthwork items for in-place density and/or gradation,
shall possess a current certification and/or proof of training from the following organization:
North East Transportation Technician Certification Program (NETTCP) Soils and Aggregate
Inspector Certification. An alternative to the certification/training listed above would be proof of
previous training (within the past 5 years) of the NYSDOT Earthwork Inspectors School, given by
the Department’s Geotechnical Engineering Bureau.
A Licensed Professional Engineer may be qualified to perform any testing based on demonstrated
experience.
9.07
Scope of Services/Performance Requirements
A.
Quality
The Consultant will enforce the specifications and identify in a timely manner to the Sponsor
local conditions, methods of construction, errors on the plans or defects in the work or
materials which would conflict with the quality of work, and conflict with the successful
completion of the project.
B.
Record Keeping & Payments to the Contractor
1) All records must be kept in accordance with the directions of the Sponsor and must
be consistent with the requirements of the NYSDOT Manual of Uniform
Recordkeeping (MURK).12 The Consultant must take all measurements and
collect all other pertinent information necessary to prepare daily inspection reports,
monthly and final estimates, survey notes, record plans showing all changes from
contract plans, photographs of various phases of construction, and other pertinent
data, records and reports for proper completion of records of the contract.
2) Any record plans, engineering data, survey notes or other data provided by the
Sponsor should be returned to the Sponsor at the completion of the contract. Original
tracings of record plans, maps, engineering data, the final estimate and any other
engineering data produced by the Consultant will bear the endorsement of the
Consultant. Any documents that require an appropriate review and approval of a
Professional Engineer (P.E.) licensed and registered to practice in New York State
must be signed by the P.E.
3) Unless otherwise modified by this agreement, the Sponsor will check, and when
acceptable, approve all structural shop drawings.
4) The Consultant must submit the final estimate of the contract to the Sponsor within
four (4) weeks after the date of acceptance of the contract. All project records must
be cataloged, indexed, packaged, and delivered to the Sponsor within five (5) weeks
after the date of the acceptance of the contract.
Health & Safety/Work Zone Traffic Control
1) The Consultant must ensure that all inspection staff assigned to the project are
knowledgeable concerning the health and safety requirements of the contract per
Sponsor policy, procedures and specifications and adhere to all standards.
Individual inspectors must be instructed relative to the safety concerns for
construction operations they are assigned to inspect to protect their personal safety
and to ensure they are prepared to recognize and address any contractor oversight or
disregard of project safety requirements.
2) The Consultant is responsible for monitoring the Contractor’s and Subcontractor’s
efforts to maintain traffic and protect the public from damage to person and property
within the limits of, and for the duration of the contract.
Monitoring Equal Opportunity/Labor Requirements
The Consultant must assign to one individual the responsibility of monitoring the
Contractor’s adherence to Equal Opportunity and Labor requirements contained in the
contract. When monitoring the Contractor’s Equal Opportunity and Labor compliance, the
12 https://www.dot.ny.gov/main/business-center/contractors/construction-division/forms-manuals-computer-applications-general-
information
Consultant, will utilize the guidance contained in the contract, standard specifications, and
the Sponsor’s policies. The Consultant is also to input required disadvantaged business
enterprise (DBE) information into the NYSDOT maintained Equitable Business
Opportunities (EBO) database13.
Section 10 - Estimating and Technical Assumptions
10.01 Estimating Assumptions
The following assumptions have been made for estimating purposes:
Section 1
Estimate six meetings (virtual) during the life of this agreement.
Estimate 12 cost and progress reporting periods will occur during the life of this
agreement.
Section 2
Estimate topographic survey with approximate boundary information. Survey
limits to be approximately 100ft from each end of bridge. One weekend daytime
on the railroad tracks to scan the underside of the bridge is assumed. No de-
energization of the 3rd track is assumed.
The cost of any flagman, under bridge or Hi-rail inspection vehicle, and MPT
set up, when required for survey, inspection, and testing services, are to be
borne by the Village.
Estimate two accidents will require analysis.
Section 3
Estimate four concepts will be evaluated.
Estimate three design alternative(s) will be analyzed in addition to the null
alternative.
Estimate three cost estimate(s) plus two updates will be required.
Section 4
Estimate two permits will be required.
Section 5
No Rights of Way activities are anticipated. Any work related to this item is
extra work.
Section 6
Detailed Design or Final Design
Final Design will include but not be limited to:
•
Development of highway and bridge plans.
•
Structural rehabilitation design.
•
Roadway design.
•
Development and design for public utilities.
•
Maintenance and protection of traffic during construction.
•
Preparation and submission of final Plans, Specifications, and Estimate
(PS&E) for the project.
13 https://www.dot.ny.gov/dotapp/ebo
Estimate three cost estimates plus three updates will be required.
Estimate one bridge will be rehabilitated.
Estimate three utility companies and two railroad agencies will be affected.
Section 7
Estimate five copies of the final contract bid documents will be needed for
prospective bidders.
Estimate advertisements will be placed in publications in addition to the NYS
Contract Reporter.
Analysis of bids.
Section 8
Construction Support will include but not be limited to:
•
Providing technical support during construction on questions relating to
the design.
•
Providing assistance in construction bid proceedings.
•
Review of shop drawings (if necessary).
Estimate twenty requests that require effort will be made during the
construction phase of the project.
Section 9
Construction Inspection will include but not be limited to:
•
Providing on-site construction inspection and oversight to ensure the
quality of construction and conformity with the final plans and
specifications.
•
Preparation of as-built plans.
Estimate construction will begin in April 2025, and will be completed by April
2026.
10.02 Technical Assumptions
Intentionally Left Blank
Section 11 – Fee Summary
11.1
Fee Summary Table
A summary of the estimated fee is provided below:
DESIGN SERVICES
Description
Fee
Structure
Est. Fee
Section 1 - General
LS
$14,440.00
Section 2 - Data Collection & Analysis
LS
$46,740.00
Section 3 - Preliminary Design
LS
$43,700.00
Section 4 – Environmental
LS
$22,110.00
Section 5 - Right of Way
LS
DESIGN SERVICES
Description
Fee
Structure
Est. Fee
Section 6 - Detailed Design
LS
$51,490.00
Section 7 - Advertising, Bid Opening, and Award
LS
$7,200.00
Section 8 - Construction Support
LS
$13,460.00
SUBTOTAL DESIGN FEE
$199,140.00
Section 9 - Construction Inspection (40 weeks assumed)
LS
$276,400.00
TOTAL ESTIMATED FEE
$475,540.00
11.2
Five copies of the final contact bid documents and electronic copies (PDF) of all project
deliverables are included in the lump sum fees. Out-of-pocket reimbursable expenses for travel,
photocopies, additional plan prints, and overnight mailings are not included in the lump sum fees
and will be billed at cost. The current schedule of rates for reimbursable expenses is as follows:
Reimbursable Expenses
Rate
Photocopies (Black & White)
$0.10 per 8 ½” x 11” sheet
Photocopies (Color)
$0.60 per 8 ½” x 11” sheet
Travel
$0.655 per mile (or current IRS rate)
Tolls
At cost
Plan Reproduction
$2.50 per plan sheet
Overnight Mail (e.g. FedEx)
At cost
11.3
Amounts invoiced for each lump sum item shall be based on the approximate percent complete for
each item. Amounts invoiced for time and materials items shall be based on actual labor and
expenses expended to date.
11.4
Fees shall be invoiced monthly, with payment due upon receipt.
11.5
The cost of any railroad flagman, railroad groundman, under bridge or hi-rail inspection vehicle,
police services, and maintenance of protection of traffic set up is not included in the lump sum fees
and will be borne by the Village or billed to the Village as direct cost.