October 9th Resolution 190-2024 Change Order
resolution
1 page
Meeting: portal event 989 (no meeting page on file)
Agenda item: Proposed Resolutions — Consider the approval of two change orders related to Bid No. 4-2024 totaling $4,900 for additional construction work for the Harmon Firehouse Addition project.
Resolution, 1 page. Attached to agenda item: “Proposed Resolutions — Consider the approval of two change orders related to Bid No. 4-2024 totaling $4,900 for additional construction work for the Harmon Firehouse Addition project.”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
Contract Change Order %231 from Construction Plus...
Contract Change Order %232 from Construction Plus...
Extracted text
On motion of TRUSTEE -, seconded by TRUSTEE -, the following resolution was
adopted by the Board of Trustees of the Village of Croton-on-Hudson, New York
with the following vote:
Resolution #190-2024
WHEREAS, the Village of Croton-on-Hudson is undertaking the Harmon Firehouse
Addition project located at 30 Wayne Street; and
WHEREAS, the Village entered into a contract with Construction Plus Services LLC
for the completion of this project under Bid No. 04-2024; and
WHEREAS, design changes during the course of the project required two change
orders to be submitted for the bid; and
WHEREAS, the total cost of the additional work outlined in Change Orders No. 1 and
No. 2 amounts to $4,900; and
WHEREAS, the Superintendent of Public Works has reviewed the proposed change
orders and has determined that the additional work is necessary for the successful
completion of the project,
NOW THEREFORE BE IT RESOLVED: that the Village Board of Trustees hereby
authorizes the Village Manager to approve Change Order No. 1 and Change Order No.
2 in the total amount of $4,900.
Dated: October 9, 2024