EN GIN EERS OFFICE
Stanley H. Kellerhouse Municipal Building
One Van Wyck Street, 2nd floor
Croton-on-Hudson, NY 10520-2501
Mayor
Leo A.W. Wiegman
Trustees
Ann H. Gallelli
Ian W. Murtaugh
Gregory Schmidt
Casey Raskob
Village Manager
Abraham Zambrano
Assistant Village Manager
Janine King
Village Treasurer
Sandra Bullock
Village Engineer/Building Inspector
Daniel O’Connor, P.E.
Asst. Building Inspector/Assessor
Joseph Sperber
Fire Inspector
Peter Anfiteatro
MEMORANDUM
Date:
December 28, 2011
To:
Abe Zambrano
From:
Daniel O'Connor, P.E.
Washington Engine Fire House Sprinkler System - Professional Design and
Construction Inspection Services
The Washington Engine Fire House was completed in 1979. The original design plans for the
fire house did not include a fire sprinkler system. The Croton Fire Department requested that the
Village fund the installation of a sprinkler system and funding was provided in the FY 2011-2012
budget. In order for a sprinkler system to be installed the system will need to be designed and
bid documents prepared and the project bid.
Fire Systems Services, Inc in Ossining was contacted and a request was made to provide a
proposal for professional design services for the necessary design and construction inspection
work. A site visit was conducted today with a representative from Fire Systems Services to
discuss the installation of the sprinkler system, the proposal and to review the accuracy of the
design plans with the existing conditions. The work will also include the design and preparation
of documents for submission to the WCHD for the installation of a backflow prevention device
that will be required on the new 4" water service line for the sprinkler system. The proposal is
attached a W-9 is already on file with the Village. Fire System Services recently completed the
design of the sprinkler system for the Harmon Fire House. The total cost (see attached cost
summary sheet) for the professional services is $7637.50. The cost of the professional services is
considered reasonable; another firm quoted $3500 on a different project just for the preparation
of the documents for the backflow prevention device.
The FY 2011-2012 approved budget included $26,000 in the capital budget for the installation of
the sprinkler system in the Washington Engine Fire House. The above amount should be charged
to capital account #12237 for this project. It is unlikely that the balance of the funds will cover
the cost of the sprinkler system installation since it includes a new 4” water service line and new
backflow prevention device.
Harmon Fire House Sprinkler System - Professional Design and Construction Inspection Services Page 2 of 2
Tel: 914-271-4783
www.crotononhudson-ny.gov
Fax: 914-271-3790
It is requested that this be placed on the next Village Board agenda to have the Village board pass
a resolution authorizing the Village Manager to sign the proposal from Fire System Services, Inc
in the amount of $7637.50.
The bid for the Harmon Fire House was postponed until the spring since the fire apparatus will
need to be temporarily located outside when the sprinkler installation work is being performed in
the bays. It is expected that the design work on the Washington Fire House sprinkler system will
be completed in time that the work there can also be bid this spring. This will allow both fire
house sprinkler installation bids to be combined into a single bid with options. The bid will be
structured to include a separate bid for each fire house sprinkler system and then a single bid for
both fire house sprinkler systems. The Village will have the option of awarding each single bid
separately or the combined bid if cost savings is achieved.
If any additional information is needed please let me know.
Enc (proposal, cost summary sheet)
Janine King w/enc. (email only)
Ronnie Rose w/enc. (email only)
Sandra Bullock w/enc. (email only)
File w/enc.
Washington Engine Fire House Sprinkler System Engineering Design Services
No
Item
Quanity
Unit
Unit price
Amount
1 Sprinkler system design, technical specifications, estimates construction cost
1 LS
$3,000.00
$3,000.00
2 Preparation of digital (AutoCAD) floor plans from scanned paper plans1
1 LS
$1,000.00
$1,000.00
3 Backflow prevention device approval documents
1 LS
$1,200.00
$1,200.00
4 Bidding Assistance (prebid meeting with contractors, written response to questions)
3 Hours
$125.00
$375.00
5 Pre-construction meeting with contractor
2 Hours
$125.00
$250.00
6 Construction inspections (4 estimated)
6 Hours
$125.00
$750.00
7 Final inspection and acceptance testing
2.5 Hours
$125.00
$312.50
8 Preparation of as-built plans
6 Hours
$125.00
$750.00
Total
$7,637.50
1. We were not able to acquire copies of the digital AutoCAD files from the architectural firm that designed the Washington Engine Fire
House.