EN GIN EERS OFFICE
Stanley H. Kellerhouse Municipal Building
One Van Wyck Street, 2nd floor
Croton-on-Hudson, NY 10520-2501
Mayor
Leo A.W. Wiegman
Trustees
Ann H. Gallelli
Ian W. Murtaugh
Gregory Schmidt
Casey Raskob
Village Manager
Abraham Zambrano
Assistant Village Manager
Janine King
Village Treasurer
Sandra Bullock
Village Engineer/Building Inspector
Daniel O’Connor, P.E.
Asst. Building Inspector/Assessor
Joseph Sperber
Fire Inspector
Peter Anfiteatro
MEMORANDUM
Date:
November 22, 2011
To:
Abe Zambrano (email only)
From:
Daniel O’Connor
Subject:
Asphalt Paving and Cold Milling Contract with ELQ Industries
The Village signed a contract with ELQ Industries on 8/27/10 (see attached) for the asphalt
paving and cold milling work in the Village; this contract was for a one year term. In the Fall of
2010 Grand Street, Batten Road, Alexander Lane, and Merwin Oak Parking lot were milled and
paved.
Additional work; which included Quaker Bridge and Niles Roads, was scheduled for the end of
August 2011 however was postponed due to tropical storm Irene. The work was later
rescheduled after the Village recovered from Irene and the contractor was available for non-
emergency work. Although the work was performed past the contract expiration date ELQ and
the Village verbally agreed to extend the contract. I would recommend that the contract
extension to 10/31/11 be formally approved by the Village and therefore be placed on the next
Village Board agenda to have the Village Board formally agree to extend the contract with ELQ
Industries for the asphalt paving and cold milling work in the Village until 10/31/11.
Attached is a letter from ELQ Industries requesting the contract extension.
Please let me know if any additional information is needed.
Enc.
cc:
Janine King w/enc. (email only)
Paula DiSanto w/enc. (email only)
File w/enc.
ELQ INDUSTRIES INC.
Paving • Site Development
567 Fifth Avenue
New Rochelle, NY 10801
PHONE (914) 654-1040 • FAX (914) 654-1307
November 21, 2011
SENT VIA EMAIL
Village Of Croton-On-Hudson
1 Van Wyck Street
Croton-On-Hudson, NY 10520
Attention: Dan O’Connor, P.E. Village Engineer
Re:
Contract Cold Milling and Paving Project 2010
Dear Mr. O’Connor:
Due to inclement weather, ELQ Industries, Inc. (“ELQ”) did not complete work schedule
for the late August under the above referenced contract until October 6, 2011. Therefore,
we respectfully request that the contract be extended until October 31, 2011 so that we
may bill the work complete after the original contract closed on August 27, 2011.
Thank you for your attention to this matter. If you have any questions or comments
regarding the content of this letter please do not hesitate to contact me directly.
Jose Monteiro