Project breakdown 1015-25
document
3 pages
From the meeting:
Board of Trustees Work Session — 2025-10-15
· our coverage →
Agenda item: Update on Departmental Operations and Projects from Superintendent of Public Works Frank Balbi.
Document, 3 pages. Attached to agenda item: “Update on Departmental Operations and Projects from Superintendent of Public Works Frank Balbi.”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Extracted text
Project Update
Capital Project Update
DEPARTMENT OF PUBLIC WORKS
10-15-2025
Brook Street Drainage Improvement –
•
Construction drawings have been developed by the engineering firm
•
SEQR and LWRP have been approved
•
Waiting for response from Westchester County regarding our funding request
Cleveland Drive Resurfacing –
•
Federal funding approved for the resurfacing of Cleveland Drive (between Benedict and Gerstein)
•
Additional roads to be resurfaced: Wood Road (Gerstein to 129), Gerstein (Wood to Cleveland),
Old Post Road South (Cleveland to High School)
•
Plans and specifications have been developed by the engineering firm, and currently being
reviewed by NYS DOT.
•
Meeting with design firm scheduled tomorrow to review NYS comments.
Walkway to Ossining –
•
Material has been delivered to the site
•
Village welder has been working on replacement of damaged/worn out railing
•
Project completion expected by the middle of December
Farrington Road Steps –
•
The replacement of the concrete staircase has been designed, and was bid in June of 2025
•
All bids received were much higher than the funding budgeted for this project ($150,000)
•
This project will be re-bid during the winter of 2025/2026 with anticipated construction to take
place in the spring of 2026.
2025 General Road repairs and Sidewalks –
•
The 2025 resurfacing program was completed in September
•
Roadways paved this year: Scenic Drive West (9A to Baltic), Lower North Highland (OPRN to
Ackerman), Cleveland Drive (Benedict to Piney Point), and Penfield (Benedict to Oneida)
•
Sidewalks completed so far located at the dead end of Thompson, and Whelen (near Oneida)
•
Additional sidewalks being considered for installation by the end of the year
Half Moon Bay Bridge –
•
The Village has hired a design firm to develop plans and specifications for the rehabilitation of
the bridge
•
Engineering firm has completed initial construction plans
•
Since this bridge crosses the railroad track, the plans are being reviewed by Metro-North
Municipal Building Improvements –
•
Bids received for HVAC improvements were higher than the funding available for this project
•
DPW working with HVAC contractors to perform most sensitive areas first
•
Work anticipated after the EMS addition is completed
•
Concept plan for Engineering Department improvements has been developed.
Project Update
Traffic Light Replacement –
•
Traffic signals on South Riverside Avenue are being updated at the intersections of Croton Point
Avenue and Benedict Blvd.
•
Waiting for proposals for material and equipment from the vendor. Once these are received, we
can start scheduling work with the electrical contractor.
OPRN Traffic Study –
•
Design firm analyzing OPRN in the vicinity of Michaels Lane for traffic and pedestrian safety
•
Traffic counts have been taken, and conceptual plans are being developed
•
Progress meeting with the design firm has been scheduled to discuss design options and proposed
schedule moving forward
Water Main Relining –
•
Continuation of water infrastructure improvement project
•
Complaints of brown water in the area make this the next candidate for re-lining
•
Currently in design. Once in design, plans must be reviewed by Westchester County for approval
Grand Street Firehouse Upgrades –
•
Proposed replacement of ceiling tiles in the Chemical Engine day-room
•
Replacing the kitchen floor
•
AC in the ladder day-room, the radio room and the chief’s office have been updated
EMS addition at Harmon Firehouse –
•
Working on finishes throughout the building. This includes installation of ceiling grid, flooring,
paint, cabinets, etc.
PD Renovation –
•
Bathroom in Detective Division in design (for juvenile protection)
•
Gathering construction estimates for separate entrance into Detective Division (also for juvenile
protection)
Washington Engine Parking –
•
Retaining wall is complete. Remainder of the site work ongoing
•
Asphalt binder should be installed by the end of this year
•
Final pavement in the spring of 2026
Dobbs Baseball Infield Improvements –
•
Awaiting the remainder of insurance documents from the contractor
•
Fencing material is ordered, and we are scheduling with the fencing contractor with is work
Dobbs Playground and Basketball Court Renovation –
•
Bids have been received
•
Pre-construction walk-through with the contractor is scheduled for this week
•
Playground equipment has been ordered. We are expecting delivery in approximately 8 weeks
Department of Public Works
Project Update
Gouveia Park Improvements –
•
Sewer line crossing Albany Post Road has been installed
•
Architect has completed the conceptual design and is working on the construction drawings
•
Site work will start after the completion of EMS addition
DPW Solar Canopy Project –
•
One bid received
•
The contractor has not submitted required documentation, so bids are expected to be rejected
•
Project will go out to bid again
EV Chargers at Train Station –
•
Contractor is reviewing the contract documents
•
Village will be working with a contractor to schedule the excavation and concrete work for the
conduit and EV chargers.
•
Village DPW will be responsible for the restoration of the area and re-striping the parking spots.
Food Scrap Program –
•
A new shed has been delivered to the train station parking lot directly behind the salt shed
•
This shed is larger than the current structure being used for this program
•
Plans to expand the program
Renewable Diesel Pilot Program–
•
Renewable diesel delivered to the Village fueling station on 9-23-2025
•
4 Village vehicles currently in the pilot program
•
We are planning to expand the pilot program in the next two weeks
•
Currently, no issues reported using the new diesel
Shoreline Resiliency and Flood Mitigation –
•
Conceptual plans have been developed
•
Grant writer contacting Westchester County to inquire about potential of funding
Train Station Solar Canopy Project –
•
Construction is complete
•
Contractor is expecting to be powered on some time in November
Machine-extracted for search and reference — the original PDF is the authoritative version.