WBP 1 Croton Point Cover Letter Application for Special Permit dated July 11%2C 2024
application
2 pages
Scanned/OCR — text may contain errors
Meeting: portal event 983 (no meeting page on file)
Agenda item: 7 PM Start: Public Hearing to consider the special permit application from WBP Development LLC for the construction of a multifamily development at 1 Croton Point Avenue.
Application, 2 pages. Attached to agenda item: “7 PM Start: Public Hearing to consider the special permit application from WBP Development LLC for the construction of a multifamily development at 1 Croton Point Avenue.” (Text recovered by OCR — may contain errors.)
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
Draft Phase II Environmental Site Assessment Report
Environmental Noise Study and Facade Glazing...
Insite Preliminary Wastewater Engineering Report dated...
Insite Preliminary Water Engineering Report dated July...
Insite Stormwater Pollution Prevention Plan dated July...
Insite engineering and landscape architecture plans...
Letter from Kimley Horn dated September 16%2C 2024...
Letter from NYSDOT consenting to the Board of Trustees...
Letter from the Division for Historic Preservation...
Memorandum by Longman Lindsey dated September 10%2C 2024
Memorandum from WBP Development LLC -re%3A1 Croton...
Memorandum re Fiscal Analysis prepared by KSCJ...
Extracted text
DEVELOPMENT LLC
July 11, 2024
The Honorable Brian Pugh
Mayor of The Village of Croton-on-Hudson
One Van Wyck Street
Croton-on-Hudson, NY 10520
Re: WBP Development LLC
1 Croton Point, Croton-on Hudson
Application tor Special Permit for a Proposed 100-Unit Multifamily Development
Dear Mayor Pugh and Members of the Village Board,
WBP Development LLC (“WBP”), as project Sponsor/Developer, is pleased to submit an Application for
Special Permit to the Village of Croton-on-Hudson Board of Trustees for a proposed 100-unit multifamily
development consisting of 46 one-bedroom and 54 two-bedroom homes in a to be constructed 5-story
building with requisite parking and amenities (the “Development”) to be located on lands fronting on
Croton Point Avenue consisting of (i) Tax Map Parcels 79.17-1-5 & 3 owned by the Village (“Lot A”); and
(ii) Tax Map Parcel 79.17-1-4 owned by Croton Point Realty Inc (the “CPR Parcel”).
It is our intention for this Development to be a 100% affordable condominium with AFFH units selling at
prices based on 80% of the area median income (AMI) for Westchester County to households with
income levels up to 100% AMI, and otherwise in accordance with Section 230-48 of the Village Code.
Proposed funding sources for the Development include (i) NYSHCR’s Affordable Home Ownership
Opportunity Program (AHOP); and (ii) Westchester County’s New Home Land Acquisition Program
(NHLA) which provides funding for acquisition of property used to develop fair and affordable housing in
Westchester County. WBP has recently been approved for such funding on two developments, in New
Rochelle and White Plains. These developments, of 126 condominiums and 68 condominiums, will
commence construction this fall. In the event that one or both of these funding sources are not
available for this Development, WBP will still proceed with the proposed site and building plans as
proposed for a development providing not less than 20% AFFH Units.
The Application is submitted in furtherance of the Board’s adoption of Resolution #86-2024 on April 24,
2024, wherein the Board selected WBP as the proposed purchaser and preferred developer of Lot A in
connection with an RFP process initiated by the Village in July, 2023. WBP is also Contract Vendee
pursuant to an Agreement of Purchase and Sale dated April 23, 2024, for the CPR Parcel.
The Application is also advanced in accordance with Local Law 14 of 2022 which, consistent with the
goals of the Village Master Plan, amended certain zoning provisions for the Light Industrial Zoning
District (within which the Development is located) to permit, as a special permit use, transit-oriented
480 BEDFORD ROAD CHAPPAQUA, NEW YORK 10514
T: 914.347.3333
F: 914.909.7328
development consisting of mixed use or multi-family residential buildings on lots located on Croton
Point Avenue on the west side of Route 9 and within 1,500 feet of the Metro North Croton Harmon
Train Station. .
In this regard, attached please find the following:
1. Application for Village Board Special Permit;
2. Check in the sum of $5,000 for the Application Fee;
3. Site Plans prepared by Insite Engineering;
4. Preliminary Stormwater Pollution Prevention Plan (SWPPP) prepared by Insite Engineering;
5. Preliminary Water Engineering Report prepared by Insite Engineering;
6. Preliminary Wastewater Engineering Report prepared by Insite Engineering;
7. Architectural Plans prepared by Arketekcher, including building floor plans and elevations;
8. Part 1 Environmental Assessment Form (EAF) prepared by KSCJ Consulting;
9. Coastal Assessment Form prepared by KSCJ Consulting.
As the Board is aware, Lot A is currently in use as a Village commuter parking lot. The CPR Parcel is
improved with an office building which is proposed to be demolished for the Development.
The proposed brick and metal panel building will be served by 100 parking spaces to be located ina
below grade parking level and two outdoor parking areas, including five (5) Level 2 EV charging stations.
Amenities within the building will include a community room, a fitness center, a co-working lounge, a
bike storage room and a roof-top deck providing expansive scenic views overlooking Croton Point Bay
and the Hudson River.
Sustainable building design features will likely include full electrification, solar readiness, high efficiency
HVAC equipment (cold climate air source heat pumps) and appliances (Energy Star Multifamily New
Construction Program) and low-flow water fixtures. WBP will build the Development to a recognized
“green building” standard. Recent WBP developments have been LEED Gold and LEED Platinum.
We respectfully request that this matter be added to your Board’s July 17, 2024 meeting agenda. We
also request that, upon review of the Application submission documents, the Board consider taking the
following actions:
1. Declare the Board’s intent to act as lead agency for purposes of SEQRA
2. Refer the Application to the Village’s Planning Board for its required report
3. Refer the Application to Westchester County Planning Department
Thank you for your consideration and we look forward to presenting the Application for this exciting
development to your Board.
John R. Bainlardi, Vice President