2022 Westchester Power Con Ed Extension MOU Revised 20220422 - renewable
resolution
4 pages
From the meeting:
Board Of Trustees — 2022-06-21
Agenda item: Proposed Resolutions — Consider authorizing the Village Manager to execute a revised Memorandum of Understanding with Sustainable Westchester to participate in the upcoming ESA with Westchester Power.
Resolution, 4 pages. Attached to agenda item: “Proposed Resolutions — Consider authorizing the Village Manager to execute a revised Memorandum of Understanding with Sustainable Westchester to participate in the upcoming ESA with Westchester Power.”
Retrieved 2026-07-31 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
2022 Con Ed ESA Template
2022 06 Westcheste Power Con Ed MOU 2022 06 20
Res 103-2022 CCA MOU 2022
Res 59-2022 Revised CCA MOU 2022
Westchester Power Email
Extracted text
CCA MOU - CON ED
2022-04-22
MEMORANDUM OF UNDERSTANDING
For
Participation in the Short-Term Westchester Power Extension Contract
For Communities in the Con Edison Service Territory
This Memorandum of Understanding is entered into by and between:
Sustainable Westchester, Inc., a New York non-profit corporation (“Sustainable
Westchester”), and the City / Town / Village of ___________________________________
(the “Municipality”), a local government member of Sustainable Westchester (each a
“Party” and collectively, the “Parties”).
1. Background:
a. In February 2015, the New York Public Service Commission (“PSC”) issued an
Order for Case 14-M-0564 as follows: “The Petition of Sustainable Westchester is
granted to the extent that its municipal members are authorized to undertake a
Community Choice Aggregation demonstration project consistent with the discussion
in the body of this Order…”
b. The PSC subsequently issued an Order for Case 14-M-0224 on April 21, 2016, which
authorized Community Choice Aggregation (“CCA”) throughout New York State
(the “CCA Order”) and on November 15, 2018 issued the “Order Approving Renewal
of the Sustainable Westchester Community Choice Aggregation Program”
reauthorizing the Sustainable Westchester CCA program under a Master
Implementation Plan.
c. Sustainable Westchester’s CCA Program enrolled Participating Customers from an
initial group of 20 participating municipalities in April 2016. Since then, nine
additional municipalities have joined and several other municipalities are actively
working towards participation.
d. For participating municipalities in the Con Edison utility territory, the current Electric
Service Agreement for the Sustainable Westchester CCA Program will terminate on
the first meter read date after June 30, 2022
e. In compliance with the PSC CCA Orders, the Municipality has adopted local
legislation to enable Community Choice Aggregation.
f. As a member of Sustainable Westchester in good standing and participant in the
Sustainable Westchester CCA Program, the Municipality wishes to continue to
engage the services of Sustainable Westchester as the Program Manager for
Community Choice Aggregation for the Operation and Maintenance of the Program.
2. Definitions:
a. 2021 ESA: The ESA which implemented the Sustainable Westchester CCA Program
during the period from January 1, 2021 to the first meter read date after June 30,
2022.
b. 2022 Extension ESA: The ESA which will implement Sustainable Westchester CCA
Program commencing on the first meter read date after July1, 2022 for the Con
Edison service territory. The 2022 Extension ESA shall have substantially the same
terms outlined in the attached 2022 Extension ESA Template (Attached as Exhibit 1)
and shall have a term of no longer than six months. The 2022 Extension ESA
CCA MOU - CON ED
2022-04-22
Template sets out the new prices and terms, as well as any items which require
clarification in the context of the extension
c. CCA Orders: Collectively, the February 26, 2015 “Order Granting Petition in Part”
issued by the PSC in Case 14-M-0564; the April 21, 2016 “Order Authorizing
Framework for Community Choice Aggregation Opt-out Program” issued by the PSC
in Case 14-M-0224 (the “CCA Framework Order”), which sets forth the
requirements, terms, and conditions under which CCA programs can proceed through
implementation; and the November 15, 2018 “Order Approving Renewal of the
Sustainable Westchester Community Choice Aggregation Program” issued by the
PSC in Case 14-M-0564, which reauthorizes the Sustainable Westchester CCA
program under a Master Implementation Plan.
d. Community Choice Aggregation Program or CCA Program or Program– A
municipal energy procurement program, which replaces the incumbent utility as the
default supplier for all Eligible Consumers within the Participating Municipality, as
defined in the PSC CCA Orders.
e. Competitive Supplier: An entity duly authorized to conduct business in the State of
New York as an energy service company (“ESCO”) that procures electric power for
Eligible Consumers in connection with this CCA Program.
f. Compliant Offer: Electric power supply offer from a Competitive Supplier that
meets the requirements specified in this MOU and the 2022 Extension ESA. A
Compliant Offer price must be inclusive of fees owed to Program Manager and be
less than:
i. Residential accounts: 13.90 cents/kwh;
ii. Small commercial accounts: 13.90 cents/kwh
g. Default Product: The product selected by the Municipality for supply to its Eligible
Consumers upon enrollment, unless they take action to select a different product or
opt out.
h. Distribution Utility: Owner or controller of the means of distribution of the natural
gas or electricity that is regulated by the Public Service Commission in the
Participating Municipality.
i. Electric Service Agreement (“ESA”): An agreement that implements a CCA
Program and contains all the terms and conditions of the Program.
j. Eligible Consumers – Residential and small commercial consumers of electricity
who have been served by the program under the 2021 ESA and have not opted out.
For the avoidance of doubt, all Eligible Consumers must reside or be otherwise
located at one or more locations within the geographic boundaries of the
Municipality, as such boundaries exist on the Effective Date of the 2021 ESA. the
2022 Extension ESA.
k. Participating Municipality: A dues-paying municipal member of Sustainable
Westchester, which has adopted the applicable local legislation for the Community
Choice Aggregation Program.
l. Participating Customers: Eligible Consumers enrolled in the Program, including
Opt-out Eligible Consumers who have been enrolled subsequent to the opt-out
process and other customers who have opted in.
m. Program Manager: Sustainable Westchester, a non-profit corporation of which the
Participating Municipality is a member.
CCA MOU - CON ED
2022-04-22
n. Public Service Commission (“PSC”): The New York State Public Service
Commission or the New York State Department of Public Service acting as staff on
behalf of the Public Service Commission.
o. Qualifications Review: A verification of the status of the Competitive Supplier as an
electricity supplier in the Distribution Utility’s service territory. A precondition for
attaining such status is that Competitive Supplier has met the credit requirements
established by the New York Independent Systems Operator.
3. Purpose: The purpose of the Memorandum of Understanding is as follows:
a. To establish participation by The Municipality (hereafter, the “Participating
Municipality”) in a Community Choice Aggregation Program (hereafter, the
“Program”) that will be managed on its behalf by Sustainable Westchester,
(hereafter, the “Program Manager”) under the 2022 Extension ESA.
b. To affirm that the Participating Municipality and Program Manager agree to adhere to
the terms and conditions of the 2022 Extension ESA in the event they execute it.
c. To affirm that the Participating Municipality and Program Manager agree to execute
the 2022 Extension ESA, subject to the conditions of review and approval outlined in
4(c) and 5(a), below.
4. Roles and responsibilities of the Program Manager: As Program Manager, Sustainable
Westchester agrees to perform all duties outlined in the 2022 Extension ESA and, prior to
execution of that agreement, Program Manager agrees to:
a. Provide the involved agencies and parties to the PSC CCA Orders, including, but not
limited to, the Public Service Commission and Distribution Utility, requested
information about and documentation of the actions undertaken by the Participating
Municipality in furtherance of enabling participation in the Program;
b. Manage the contract extension process including:
i. the collection of indicative pricing and other inputs against which to evaluate
the 2022 Extension ESA offers,
ii. the preparation of the 2022 Extension ESA,
iii. the acceptance, secure opening, and review of the indicative pricing and 2022
Extension ESA offers, and
iv. the organization of the Qualifications Review, offer evaluation, and selection
of a Competitive Supplier, all in a manner that is transparent to the
Participating Municipality and firms seeking to be the Competitive Supplier;
c. Sign the 2022 Extension ESA in a timely fashion subject to the conditions that:
i. the Competitive Supplier is deemed qualified for the duration of the 2022
Extension ESA by the Qualifications Review, and
ii. such Competitive Supplier’s offer is deemed by the Program Manager to be a
Compliant Offer as defined in Section 2 above.
d. Fulfill any other responsibilities as may reasonably adhere to facilitating the
implementation of the Program, subject to the Program Manager’s inherent and
original role as an organization driven by the deliberated priorities of its constituent
member municipalities.
5. Roles and responsibilities of the Participating Municipality: The Participating
Municipality agrees to:
CCA MOU - CON ED
2022-04-22
a. Sign the 2022 Extension ESA, selecting the 100% Renewable Clean Power Product
as the Default Product for its Eligible Consumers, in a timely fashion, subject to the
conditions that:
i. the Competitive Supplier is deemed qualified for the duration of the 2022
Extension ESA by the Qualifications Review, and
ii. such Competitive Supplier’s offer is deemed by the Program Manager to be a
Compliant Offer as defined in Section 2 above.
6. Term and Termination: Memorandum of Understanding shall expire on the earlier of June
30, 2022 or the date on which the 2022 Extension ESA is signed by the Participating
Municipality, the Program Manager, and the selected Competitive Supplier. Participating
Municipality shall have the right to terminate this Memorandum of Understanding for any of
the reasons set forth in the Termination section of the 2021 ESA attached hereto as Exhibit 2.
***
IN WITNESSETH WHEREOF, the Parties have signed this MEMORANDUM OF
UNDERSTANDING on the day and year appearing below their respective signatures.
City/Town/Village of ___________________________________________________
Authorized Official Name and Title: _______________________________________
Signature: ___________________________________________________________
Address: _____________________________________________________________
Telephone(s): ________________________________
E-Mail Address: ______________________________
Address for Notices: ________________________________________________
Sustainable Westchester, Inc.
Authorized Official Name and Title: Nina Orville, Executive Director
Signature: _______________________________________________________
Address: 40 Green Street, Mount Kisco, NY 10549
Telephone(s): (914) 242-4725
E-Mail Address:nina@sustainablewestchester.org
Address for Notices: 40 Green Street, Mount Kisco, NY 10549
Attachments:
Exhibit 1, 2022 Extension ESA Template
Exhibit 2, 2021 ESA
Machine-extracted for search and reference — the original PDF is the authoritative version.