Agenda item: Continued review of the special permit application from WBP Development LLC for the construction of a multifamily development at 1 Croton Point Avenue.
Application, 2 pages. Attached to agenda item: “Continued review of the special permit application from WBP Development LLC for the construction of a multifamily development at 1 Croton Point Avenue.”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
1 Croton Point Neg Dec DRAFT Reasons in Support 2024.11.20
10152024 Response Letter
1CrotonPoint Fiscal 20241016
1CrotonPoint PSAC 20241016
1CrotonPoint Part 2 FEAF 20241120
AKRF Memo 1 Croton Point SUP Conditions 20241202
Draft Phase II Environmental Site Assessment Report
Environmental Noise Study and Facade Glazing...
Insite Preliminary Wastewater Engineering Report dated...
Insite Preliminary Water Engineering Report dated July...
Insite Stormwater Pollution Prevention Plan dated July...
Insite engineering and landscape architecture plans...
Extracted text
Part 3 - Evaluation of the Magnitude and Importance of Project Impacts
and
Determination of Significance
Part 3 provides the reasons in support of the determination of significance. The lead agency must complete Part 3 for every question
in Part 2 where the impact has been identified as potentially moderate to large or where there is a need to explain why a particular
element of the proposed action will not, or may, result in a significant adverse environmental impact.
Based on the analysis in Part 3, the lead agency must decide whether to require an environmental impact statement to further assess
the proposed action or whether available information is sufficient for the lead agency to conclude that the proposed action will not
have a significant adverse environmental impact. By completing the certification on the next page, the lead agency can complete its
determination of significance.
Reasons Supporting This Determination:
To complete this section:
•
Identify the impact based on the Part 2 responses and describe its magnitude. Magnitude considers factors such as severity,
size or extent of an impact.
•
Assess the importance of the impact. Importance relates to the geographic scope, duration, probability of the impact
occurring, number of people affected by the impact and any additional environmental consequences if the impact were to
occur.
•
The assessment should take into consideration any design element or project changes.
•
Repeat this process for each Part 2 question where the impact has been identified as potentially moderate to large or where
there is a need to explain why a particular element of the proposed action will not, or may, result in a significant adverse
environmental impact.
•
Provide the reason(s) why the impact may, or will not, result in a significant adverse environmental impact
•
For Conditional Negative Declarations identify the specific condition(s) imposed that will modify the proposed action so that
no significant adverse environmental impacts will result.
•
Attach additional sheets, as needed.
Determination of Significance - Type 1 and Unlisted Actions
SEQR Status:
Type 1
Unlisted
Identify portions of EAF completed for this Project: Part 1
Part 2
Part 3
Agency Use Only [IfApplicable]
Project :
Date :
FEAF 2019
Refer to supporting document attached.
November 20, 2024
Upon review of the information recorded on this EAF, as noted, plus this additional support information
and considering both the magnitude and importance of each identified potential impact, it is the conclusion of the
as lead agency that:
A. This project will result in no significant adverse impacts on the environment, and, therefore, an environmental impact
statement need not be prepared. Accordingly, this negative declaration is issued.
B. Although this project could have a significant adverse impact on the environment, that impact will be avoided or
substantially mitigated because of the following conditions which will be required by the lead agency:
There will, therefore, be no significant adverse impacts from the project as conditioned, and, therefore, this conditioned negative
declaration is issued. A conditioned negative declaration may be used only for UNLISTED actions (see 6 NYCRR 617.7(d)).
C. This Project may result in one or more significant adverse impacts on the environment, and an environmental impact
statement must be prepared to further assess the impact(s) and possible mitigation and to explore alternatives to avoid or reduce those
impacts. Accordingly, this positive declaration is issued.
Name of Action:
Name of Lead Agency:
Name of Responsible Officer in Lead Agency:
Title of Responsible Officer:
Signature of Responsible Officer in Lead Agency:
Date:
Signature of Preparer (if different from Responsible Officer)
Date:
For Further Information:
Contact Person:
Telephone Number:
E-mail:
For Type 1 Actions and Conditioned Negative Declarations, a copy of this Notice is sent to:
Chief Executive Officer of the political subdivision in which the action will be principally located (e.g., Town / City / Village of)
Other involved agencies (if any)
Applicant (if any)
Environmental Notice Bulletin: http://www.dec.ny.gov/enb/enb.html
Refer to supporting document attached.
1 Croton Point Avenue
Village of Croton-on-Hudson Board of Trustees
Bryan Healy
Village Manager, Village of Croton-on-Hudson
Bryan Healy, Village Manager, Village of Croton-on-Hudson
1 Van Wyck Street, Croton-on-Hudson, NY 10520
914-271-4848
bhealy@crotononhudson-ny.gov
Village of Croton-on-Hudson Board of Trustees
PRINT FULL FORM
Machine-extracted for search and reference — the original PDF is the authoritative version.