this local law was put together, with the village engineer, our planning consultant, the village attorney, and, we spent a number of months looking at the zoning code to see, what items needed to be cleaned up and what potential, items needed to be u…
sections. So the battery energy storage system for signage says the signage shall be in compliance with ANSI z five thirty five, what whatever that means, and shall include the type of technology associated with the battery energy storage systems, an…
And then, you know, just to summarize what these changes are, and Vince might need some of your help with this. So, basically, what these what the cleanups are, there's a bunch around, transitioning the special permits from the village board to the p…
Right. Anything else before we kinda dig in here? Alright. So, you know, just looking at these, the stock. Number one, you know, throughout, we mentioned this clarify special permits are now handled by the planning board. Number two is a tier four so…
That's good. Good good catch. Alright. So we're going on to page 23. And, so planning the the planning board now is gonna handle site plan approval for several new things, a residential accessory building, tier three and four solar energy systems, ti…
Meanwhile, the village’s battery energy storage system (BESS) 2.0 project at Municipal Place is back on track after Luminace submitted a modified proposal on January 27 accepting changes to the site access easement. To maximize the site’s potential m…
We could we could we could be done with this in twenty minutes. I make a motion that we clean up the zoning code. Okay. So No second. I'm gonna start with my memo, and then we can look at the law. So for the past couple months, we've been working mys…
During a Sunday morning Zoom meeting, the Sustainability Committee revealed that Luminace, the developer tapped to build a half-sized battery energy storage system (BESS) at the Municipal Place facility, has backed out. The firm’s development directo…
On the solar front, the long-awaited commissioning of the train station solar canopies and Battery Energy Storage System (BESS) is slated for completion by the end of December. However, plans for a second, larger BESS behind the Municipal Place facil…
On the infrastructure front, the committee reviewed a lucrative proposal to lease village land for a large-scale battery energy storage system (BESS). A developer proposed building a ~5 MW system on the dirt plot behind the Municipal Place facility, …
Croton’s Sustainability Committee is eyeing a new way to fund green initiatives without relying on unpredictable government grants: leasing a small slice of village-owned land for a battery energy storage system.