Luminace

Organization 3 mentions · 2026-02-22
Battery Energy Storage System (BESS) Battery Energy Storage System battery energy storage Municipal Place Municipal Place facility Mayor Brian Pugh Westchester County Croton Point Solar Canopies Train Station Simon Sustainability Committee Croton Point Park Brian Pugh Len Simon
Article Sustainability Committee 2026-02-22 Read →
Meanwhile, the village’s battery energy storage system (BESS) 2.0 project at Municipal Place is back on track after Luminace submitted a modified proposal on January 27 accepting changes to the site access easement. To maximize the site’s potential m…
Article Sustainability Committee 2026-01-18 Read →
During a Sunday morning Zoom meeting, the Sustainability Committee revealed that Luminace, the developer tapped to build a half-sized battery energy storage system (BESS) at the Municipal Place facility, has backed out. The firm’s development directo…
Article Sustainability Committee 2025-12-07 Read →
On the solar front, the long-awaited commissioning of the train station solar canopies and Battery Energy Storage System (BESS) is slated for completion by the end of December. However, plans for a second, larger BESS behind the Municipal Place facil…