Half Moon Bay Bridge Reconstruction Project Webinar
Village Unveils $2M Plan to Rehabilitate Half Moon Bay Bridge; Construction Set to Last Over Two Years
2026-01-057447 words transcribed
Croton-on-Hudson officials detailed a $2.3 million reconstruction project for the Half Moon Bay Bridge, addressing significant structural decay found during a recent inspection. The project, funded by federal and state money, will utilize alternating one-way traffic for over two years beginning in late 2026 while maintaining access to Senasqua Park.
●**Project Scope:** The existing concrete bridge deck will be entirely replaced, and structural steel components—currently showing "moderate to heavy rust"—will be cleaned and painted.
●**Construction Timeline:** Design completion is targeted for July 2026, with construction starting in December 2026 and finishing by March 2028.
●**Traffic Management:** The bridge will remain open via alternating one-way traffic controlled by temporary signals, though full closures may be needed temporarily for heavy equipment movement.
●**Cost Estimate:** Total costs are estimated between $1.7 million and $2.3 million, funded through federal money passing through the state.
●**Emergency Coordination:** The village will coordinate with the school district for bus priority signals and notify fire and EMS of lane changes during construction.