Half Moon Bay Bridge Reconstruction Project Webinar
Half Moon Bay Bridge plan calls for staged work and alternating traffic
Jan 5, 2026
7447 words transcribed
At the January 5 webinar, engineers outlined repairs and plans to preserve access during construction. The village now anticipates an early-2027 start and about 14 months of work; traffic details and approvals remained part of project planning.
Key Actions & Decisions
●
Presented a two-stage bridge rehabilitation plan with alternating one-way traffic.
●
Discussed school-bus access, emergency notifications, waterfront events and boat passage.
●
January cost estimate was $1.7 million–$2.3 million; the current village page anticipates construction in early 2027 lasting approximately 14 months.