07.02.2026 Proposal Additional Mill-Pave Cleveland Drive DB
resolution
2 pages
From the meeting:
Board Of Trustees — 2026-07-15
· our coverage →
Agenda item: Consent Agenda — Resolutions — Consider authorizing the Village Manager to execute a change order in the amount of $75,036.55 with ELQ Industries of New Rochelle, New York, to pave Cleveland Drive between Gerstein Street and Jacoby Street.
Resolution, 2 pages. Attached to agenda item: “Consent Agenda — Resolutions — Consider authorizing the Village Manager to execute a change order in the amount of $75,036.55 with ELQ Industries of New Rochelle, New York, to pave Cleveland Drive between Gerstein Street”
Retrieved 2026-09-29 from the village's meeting portal.
View the original file ↗
Also attached to this agenda item:
Bid 1-2026 Memo
Resolution 173-2026 Paving Change Order
Resolution 96-2026 Bid 1-2026 Paving Downtown Croton
Extracted text
1 | P a g e
July 2, 2026
Sent via email: fbalbi@crotononhudson-ny.gov
Village of Croton-on-Hudson
Department of Public Works
1 Van Wyck Street
Croton-on-Hudson, NY 10520
Attn: Frank Balbi, P.E.
Re: Change Order Request: Additional Asphalt Milling and Paving on Cleveland Drive
Dear Mr. Balbi:
As requested, we respectfully submit the following proposal for work associated with the following
scope of work, at the above referenced project.
Scope:
•
Code 753
•
Mobilization/Demobilization
•
Furnish all labor and equipment to mill 2” of asphalt pavement, inclusive of key cuts, sweeping,
and offsite disposal of millings
•
Furnish all labor, materials, and equipment to install 2” of 12.5 F3 asphalt top, inclusive of
compaction testing
•
Furnish and install asphalt tack at a rate of .05 gallons per square yard
•
Furnish and install asphalt joint adhesive
•
MPT for our work consisting of temporary construction signs, cones, and flagmen
Our lump sum change order request is based on contract unit pricing as per the attached
breakdown is : Seventy-Five Thousand Thirty-Six Dollars and Fifty-Five Cents ($75,036.55).
Sales tax is not included and will be added unless a tax-exempt certificate is provided.
Qualifications:
•
Asphalt price adjustment applies
•
Our proposal is based on approximately 3067 SY
•
Pavement markings are excluded
Exclusions:
•
Any work not listed above
•
Nights, weekend, overtime, or holiday work
•
Police for MPT
•
Design, Survey, as-built survey, bonds, and/or special insurance requirements
•
Testing or inspection unless noted above
•
Permits and associated fees
2 | P a g e
•
Temporary facilities or controls
•
Geotechnical engineer, electrician or plumber
•
Testing, handling, treating and removal of any contaminated/hazardous materials and the
installation/removal of any materials not specified above
•
Dewatering system or waterproofing/vapor barrier
•
Test pits/exploratory excavation/removal of unsuitables unless noted above
•
Rock removal
•
Building excavation, underpinning, or supply of any inserts
•
Support of excavation or of adjacent buildings unless noted above
•
Landscaping of any kind including mulch, topsoil, seeding, and/or watering/maintenance
•
Masonry work
•
Winter conditions (including but not limited to concrete)
•
Snow Removal
•
Capping/removal/relocation of existing utilities unless noted above
•
Tree removal including stumps
•
Additional mobilizations
•
Variation of plans exceeding the quantities stated above
Plans/Specifications:
•
N/A
Thank you for your interest in ELQ Industries, Inc. and please do not hesitate to contact me with
any questions or concerns. We look forward to working with you on this project.
Very Truly Yours,
Tony Silvs
Chief Estimator
ELQ INDUSTRIES, INC.