Resolution 91-2023 Half Moon Bay Bridge Rehabilitation Project
resolution
2 pages
From the meeting:
Board Of Trustees — 2026-10-07
· our coverage →
Agenda item: Proposed Resolutions — Consider authorizing the Village Manager to execute a supplemental agreement with the New York State Department of Transportation for the Half Moon Bay Bridge Reconstruction Project.
Resolution, 2 pages. Attached to agenda item: “Proposed Resolutions — Consider authorizing the Village Manager to execute a supplemental agreement with the New York State Department of Transportation for the Half Moon Bay Bridge Reconstruction Project.”
Retrieved 2026-10-05 from the village's meeting portal.
View the original file ↗
Also attached to this agenda item:
8763.05 Master Agreement
PIN 8763.05 Cover Letter
PIN 8763.05 Sup 1 D040907
Resolution 250-2026 NYSDOT HMB Supplemental Agreement
Extracted text
On motion of TRUSTEE ___, seconded by TRUSTEE ____, the following
resolution was adopted by the Board of Trustees of the Village of Croton- on-Hudson,
New York, with a - vote.
Resolution #91-2023
WHEREAS, a Project for the NY-17 Half Moon Bay Bridge (BIN 2270050)
Reconstruction Project, PIN 8763.05 (the “Project") is eligible for funding under
Title 23 U.S. Code, as amended, that calls for the apportionment of the costs such
program to be borne at the ratio of 80% Federal funds and 20% non-federal funds;
and
WHEREAS, the Village of Croton-on-Hudson desires to advance the Project by
making a commitment of 100% of the non-federal share of the costs of Preliminary
Engineering,
NOW THEREFORE BE IT RESOLVED: that the Village Board hereby approves
the above-subject project;
AND BE IT FURTHER RESOLVED: that the Village Board hereby authorizes the
Village of Croton-on-Hudson to pay in the first instance 100% of the federal and
non-federal share of the cost of Preliminary Engineering work for the Project or
portions thereof;
AND BE IT FURTHER RESOLVED: that the sum of $400,000 is hereby
appropriated in Capital Project Account H5110.2106.15287 and made available to
cover the cost of participation in the above phase of the Project;
AND BE IT FURTHER RESOLVED: that in the event the full federal and non-
federal share costs of the project exceeds the amount appropriated above, the Village
Board shall convene as soon as possible to appropriate said excess amount
immediately upon the notification by the Village Manager thereof;
AND BE IT FURTHER RESOLVED: that the Village Manager of the Village of
Croton-on-Hudson be and is hereby authorized to execute all necessary Agreements,
certifications or reimbursement requests for Federal Aid and/or applicable
Marchiselli Aid on behalf of the Village of Croton-on-Hudson with the New York
State Department of Transportation in connection with the advancement or approval
of the Project and providing for the administration of the Project and the
municipality's first instance funding of project costs and permanent funding of the
local share of federal-aid and state-aid eligible Project costs and all Project costs
within appropriations therefore that are not so eligible;
AND BE IT FURTHER RESOLVED: that in addition to the Village Manager, the
following municipal titles, Superintendent of Public Works and Village Treasurer,
are also hereby authorized to execute any necessary Agreements or certifications on
behalf of the Municipality/Sponsor, with NYSDOT in connection with the
advancement or approval of the project identified in the State/Local Agreement;
AND BE IT FURTHER RESOLVED: that a certified copy of this resolution be filed
with the New York State Commissioner of Transportation by attaching it to any
necessary Agreement in connection with the Project;
AND BE IT FURTHER RESOLVED: that this Resolution shall take effect
immediately.
Dated: April 24, 2023