Agenda item: Proposed Resolutions — Consider authorizing the Village Manager to accept the proposal from Tectonic Engineering for additional scope of work related to the Half Moon Bay Bridge Rehabilitation Project in the amount of $41,540.
Resolution, 3 pages. Attached to agenda item: “Proposed Resolutions — Consider authorizing the Village Manager to accept the proposal from Tectonic Engineering for additional scope of work related to the Half Moon Bay Bridge Rehabilitation Project in the amount of $4”
Retrieved 2026-04-15 from the village's meeting portal. View the original PDF ↗
Also attached to this agenda item: Consultant Agreement - Tectonic Resolution 2-2026 HMB Bridge Additional Work Proposal Resolution 29-2024 Half Moon Bay Bridge Consulting Services Resolution 295-2025 HMB Bridge Consultant Agreement Scope of Services - Halfmoon Bridge Tectonic R1
1 Van Wyck Street, Croton-on-Hudson, N.Y. 10520 ATTN: Bryan T. Healy, Village Manager December 18, 2025 VIA EMAIL (bhealy@crotononhudson -ny.gov) RE: Half Moon Bay Bridge (BIN 2270050) Rehabilitation Village of Croton-on-Hudson, Westchester County, NY Proposal for Professional Services - Additional Scope 2 Dear Mr. Healy: In accordance with our recent coordination, Tectonic Engineering Consultants, Geologists & Land Surveyors, D.P.C. is pleased to submit our proposal to provide professional services for the additional scope of the Half Moon Bay Bridge (BIN 2270050) Rehabilitation project, Village of Croton-on-Hudson, NY. These services shall be performed for the Village of Croton-on-Hudson, herein referred to as Client. 1.0 SCOPE OF SERVICES In accordance with the recent coordination with NYSDOT and MNR regarding the pier cap beam repair and the recent direction from NYSDOT regarding the coastal assessment , additional scope will be needed. Pier Cap Beam Repair Design the structural repair for the existing pier cap beams at both piers. Per the last inspection, section losses due to corrosion are noted at the pier cap beams. Per the recent coordination with Metro North Railroad, c omplete replacement of the cap beams is not feasible due to close proximity to the railroad tracks. In the current design concept, the cap beams will be repaired by adding reinforced concrete inside the opening of the existing cap beams. This task consist s of preparation of the structural repair design, drafting repair details , modification of the contract drawing s, and coordination with NYSDOT and MNRR. It will require additional efforts under section 3 preliminary design stage and section 6 detailed design stage. Coastal Assessment The proposed project is located in the NYS Coastal Zone and Local Waterfront Revitalization Program (LWRP) area. In accordance with NYSDOT environmental review procedures, a Federal Aid Notification package will need to be submitted to the NYS Department o f State and a Coastal Assessment Form will need to be completed. The project will be reviewed in accordance with NY State Costal Policies and documentation of the project’s consistency with State Coastal Policies will be provided. Since the project is loca ted in a LWRP, notifications will be prepared for submittal to the municipality (Village of Croton -on-Hudson) including a discussion of the project’s consistency with all applicable policies of the LWRP. No federal permits are anticipated to be required for the project; therefore pre paration of a Federal Coastal Assessment Form would not be required and is not included as part of this scope . 2.0 FEES AND PAYMENTS Tectonic will perform the scope and quantity of work outlined in Section 1.0 above, based on the following fees. Task Description Estimated Additional Fee Section 3 Prelim Design $19,360.00 Section 4 Environmental $2,900.00 Section 6 Detailed Design $19,280.00 Estimated Total $41,540.00 Please have an authorized representative complete and sign the attached Authorization Form to indicate acceptance of this agreement. Please return to Tectonic one signed copy of the completed Authorization Form. If you have any questions or comment relative to this proposal, please do not hesitate to contact the undersigned directly at (860 ) 563.2341. TECTONIC ENGINEERING CONSULTANTS, GEOLOGISTS & LAND SURVEYORS, D.P.C. ____ Man Hou Sit____ Man Hou (Albert) Sit Project Manager Tectonic Engineering CC: Frank Balbi, P.E., Superintendent of Public Works , Village of Croton-on-Hudson Jeff Scala, P.E., Senior Vice President, Tectonic Engineering G:\Rocky Hill\Marketing\Proposals - Outstanding\23\PN23-1226 LDSA-Croton on Hudson Bridge Repl RFQ for Preliminary Design - PIN 8763.05\Scope & Cost proposal_addl scope 2025 04\Half Moon Bay Bridge Additional Scope.docx WORK AUTHORIZATION AND PROPOSAL ACCEPTANCE FORM Proposal No: 23-1226 Date: 12/18/2025 Retainer Amount Required: $0.00 Project Name & Location: Half Moon Bay Bridge (BIN 2270050) Rehabilitation , Village of Croton-on-Hudson, Westchester County, NY Proposed Services: Bridge Design – Additional Scope Proposal Acceptance Acceptance (Signature): Date: Printed Name: Title: Company or Organization Name: Client Contact Information (All of the following information about the person responsible for the identifie tasks must be provided prior to starting work) Scheduling Work and Receipt of Deliverables Name: Phone: Email: Receipt of Invoices (Original) Name: Phone: Email: Receipt of Invoices (Copies) Name: Phone: Email: Issuing Payments of Invoices Name: Phone: Email: