Agenda item: Public Hearings — Public Hearing to consider the special permit application submitted by Ryan Kao of CTRH LLC for the construction of a three-story mixed-use building at 325 South Riverside Avenue.
Application, 2 pages. Attached to agenda item: “Public Hearings — Public Hearing to consider the special permit application submitted by Ryan Kao of CTRH LLC for the construction of a three-story mixed-use building at 325 South Riverside Avenue.”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
325 S. Riverside Ave. - Coastal Assessment Form Dated...
325 S. Riverside Ave. - Narrative Dated July 10%2C 2024
325 S. Riverside Ave. - Short EAF Form Dated July 10%2C 2024
325 S. Riverside Ave. - Special Permit Application...
325 S. Riverside Avenue Renderings from ARQ...
325 S. Riverside Avenue Updated Renderings from ARQ...
Letter from Village Planning Board Dated August 7%2C 2024
Extracted text
Members
STUART GREENBAUM
STEVE KRISKY
IAN W. MURTAUGH
LEO WIEGMAN
Attorney
LINDA WHITEHEAD
Village Engineer
DANIEL O’CONNOR, P.E.
TO: Mayor Brian Pugh and the Village Board of Trustees
FROM: Chairman Simon, Waterfront Advisory Committee
RE: Referral from Village Board for a Local Waterfront Revitalization Program (LWRP)
Consistency review for proposed demolition of existing structure on site and proposed
construction of a new three-story mixed-use building at 325 South Riverside Avenue.
DATE: September 30, 2024
On Thursday, September 26, 2024, the Waterfront Advisory Committee (WAC) reviewed for
consistency with the Village’s Local Waterfront Revitalization Program (LWRP) the referral listed
above. Based on the Committee’s review of the 44 LWRP policies, the Waterfront Advisory
Committee made a recommendation of consistency with the LWRP.
The WAC reviewed the Coastal Assessment Form and suggested the following changes:
1) In section B, part 1c, the WAC thought that Site Plan Approval from the Planning Board and
Variances from the Zoning Board of Appeals should be added.
2) Also in section B, part 6, the Zoning classification should be C-2, General Commercial/
Harmon/South Riverside Gateway Overlay Districts.
3) In section C, part 1, the entire Village is in the coastal area.
4) Section C, numbers 3 “c” through 3 “k” should all be checked “No” instead of N/A.
5) Section C number 4 “o” and “p” should be marked “Yes” as the physical building is being
changed.
The WAC reviewed the Short Environmental Assessment Form and determined that there were
no changes necessary.
The committee reviewed the 44 LWRP policies and determined that the following policies are
relevant:
POLICY 5: Encourage the location of development in areas where public services and
facilities essential to such development are adequate.
POLICY 5A: When feasible, development within the Village should be directed within the
current service area of existing water and sewer facilities or in close proximity to areas
where distribution lines currently exist.
POLICY 7E: Runoff from public and private parking lots and from storm sewer overflows
shall be effectively managed so as to prevent oil, grease, and other contaminants from
polluting surface and ground water and impact to the significant fish and wildlife
habitats.
POLICY 33: Best Management Practices will be used to ensure the control of stormwater
runoff and combined sewer overflows draining into coastal waters.
POLICY 33A: The flow of stormwater discharge shall be controlled to limit the flow of
pollutants from street and parking areas, etc. directly into the rivers and water bodies.
POLICY 41: Land use or development in the coastal area will not cause national or State
air quality standards to be violated.
The project is a redevelopment of a site that is served by public water and sewer. A storm water
management system will be designed to treat storm water flow from the redevelopment of the
site and control erosion and sediment during construction activities.
It is for the reasons contained in this memorandum that the WAC issues its recommendation of