Half Moon Bay Bridge Additional Scope
resolution
3 pages
Meeting: portal event 1040 (no meeting page on file)
Agenda item: Proposed Resolutions — Consider authorizing the Village Manager to accept the proposal from Tectonic Engineering of Rocky Hill, Connecticut, for an additional scope of work related to the Half Moon Bay Bridge Replacement Project in the amount of $38,460.
Resolution, 3 pages. Attached to agenda item: “Proposed Resolutions — Consider authorizing the Village Manager to accept the proposal from Tectonic Engineering of Rocky Hill, Connecticut, for an additional scope of work related to the Half Moon Bay Bridge Replacement”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
Resolution 90-2025 HMB Bridge Additional Scope
Extracted text
--- PAGE 1 ---
Tectonic’
Village of Croton-on-Hudson
1 Van Wyck Street,
Croton-on-Hudson, N.Y. 10520
ATTN: Bryan T. Healy, Village Manager
April 17, 2025
VIA EMAIL (bhealy@crotononhudson-ny.gov)
RE: — Half Moon Bay Bridge (BIN 2270050) Rehabilitation
Village of Croton-on-Hudson, Westchester County, NY
Proposal for Professional Services - Additional Scope
Dear Mr. Healy:
In accordance with our recent coordination, Tectonic Engineering Consultants, Geologists & Land
Surveyors, D.P.C. is pleased to submit our proposal to provide professional services for the additional scope
of the Half Moon Bay Bridge (BIN 2270050) Rehabilitation project, Village of Croton-on-Hudson, NY.
These services shall be performed for the Village of Croton-on-Hudson, herein referred to as Client.
1.0 SCOPE OF SERVICES
In accordance with the email from DOT on 04/09/2025, additional scope will be needed. As part
of the preliminary design process environmental screenings are required. The following
documentation will need to be prepared:
e Social, Economic and Environmental Conditions Checklist
e Cultural Resources: Section 106 Project Submittal Package (PSP)
e Endangered Species Act, Section 7 Submittal Package
e Hazardous Waste/Contaminated Materials.
e State Environmental Quality Review Act (SEQR) documentation
e Federal Environmental Approval Worksheet
e Bridge Bat Survey and Assessment Form
Corporate Office
70 Pleasant Hill Road, PO Box 37 | Mountainville, NY 10953
845.534.5959 Tel | 845.534.5999 Fax
tectonicengineering.com
Equal Opportunity Employer
--- PAGE 2 ---
Tectonic’
2.0 FEES AND PAYMENTS
Tectonic will perform the scope and quantity of work outlined in Section 1.0 above, based on the
following fees.
Social, Economic and Environmental Review Checklist $1,560.00
Cultural Resources: Section 106 Project Submittal Package (PSP $14,630.00
Endangered Species Act, Section 7 Checklist $3,280.00
Hazardous Waste / Contaminated Materials Checklist $2,860.00
State Environmental Quality Review Act (SEQR) documentation $2,310.00
Federal Environmental Approvals Worksheet (FEAW) $5,160.00
Bridge Bat Survey (BBS) and Form $2,580.00
Project Management and Incorporation to DAD $6,080.00
Estimated Total $38,460.00
Please have an authorized representative complete and sign the attached Authorization Form to
indicate acceptance of this agreement. Please return to Tectonic one signed copy of the completed
Authorization Form.
If you have any questions or comment relative to this proposal, please do not hesitate to contact
the undersigned directly at (860) 563.2341.
Sincerely,
TECTONIC ENGINEERING CONSULTANTS, GEOLOGISTS & LAND SURVEYORS, D.P.C.
Prepared by: Man Hou Sit
Man Hou (Albert) Sit
Project Manager
Tectonic Engineering
CC: — Frank Balbi, P.E., Superintendent of Public Works, Village of Croton-on-Hudson
Jeff Scala, P.E., Senior Vice President, Tectonic Engineering
G:\Rocky Hill\Marketing\Proposals - Outstanding\23\PN23-1226 LDSA-Croton on Hudson Bridge Repl RFQ for Preliminary Design - PIN
8763.05\Scope & Cost proposal_addl scope 2025 04\Half Moon Bay Bridge Additional Scope.docx
page 2 of 3
--- PAGE 3 ---
Tectonic!
WORK AUTHORIZATION AND PROPOSAL ACCEPTANCE FORM
Proposal No: 23-1226 Date: 04/17/2025 Retainer Amount Required: $0.00
Project Name & Location: Half Moon Bay Bridge (BIN 2270050) Rehabilitation, Village of Croton-on-Hudson,
Westchester County, NY
Proposed Services: Bridge Design — Additional Scope
Proposal Acceptance
Acceptance (Signature): Date:
Printed Name: Title:
Company or Organization Name:
Client Contact Information (All of the following information about the person responsible for the identified
tasks must be provided prior to starting work)
Receipt of
Deliverables
Name: Phone: Email:
Receipt of Invoices
rr
Name: Phone: Email:
Receipt of Invoices
ons
Issuing Payments of
page 3 of 3