Agenda item: Proposed Resolutions — Consider authorizing the Village Manager to accept the proposal from D&B Engineers for design services related to the Brook Street Drainage Improvements in the amount of $90,500.
Resolution, 1 page. Attached to agenda item: “Proposed Resolutions — Consider authorizing the Village Manager to accept the proposal from D&B Engineers for design services related to the Brook Street Drainage Improvements in the amount of $90,500.”
Resolution #151-2026, dated June 17, 2026, authorizes the Village Manager to accept a $90,500 proposal from D&B Engineers for design services for the Brook Street Drainage Project. The resolution notes flooding along Brook Street has existed for many years, that a 2023 drainage study identified a preferred alternative to improve drainage along Brook Street and Terrace Place, and that the Village has received $701,000 in funding from Westchester County for the project.
AI summary — generated from the document text; check the original before relying on details
Extracted text
adopted by the Board of Trustees of the Village of Croton- on- Hudson, New York
Resolution #151-2026
WHEREAS, flooding issues along Brook Street have existed for many years in the
Village; and
WHEREAS, in 2023, the Village Board of Trustees adopted Resolution 142-2023 to
accept a proposal from D&B Engineers to conduct an updated drainage study along
the Brook Street drainage basin; and
WHEREAS, the study has been completed and a preferred alternate has been selected
to improve drainage along Brook Street and Terrace Place; and
WHEREAS, the Village has received funding for this project from Westchester
County in the amount of $701,000; and
WHEREAS, D&B Engineers has now provided a proposal to move forward with the
design services for this project in the amount of $90,500; and
WHEREAS, Frank Balbi, Superintendent of Public Works, has reviewed the proposal
and recommended moving forward with the scope of work,
NOW THEREFORE BE IT RESOLVED: that the Village Board hereby authorizes the
Village Manager to accept the proposal from D&B Engineers in the amount of $90,500
for design services related to the Brook Street Drainage Project.
Dated: June 17, 2026