Appendix F - Full Traffic Study 1
resolution
146 pages
Meeting: portal event 795 (no meeting page on file)
Agenda item: Proposed Resolutions — Consider scheduling a Public Hearing for September 19, 2022, at 7 PM, in the Georgianna Grant Meeting Room of the Stanley H. Kellerhouse Municipal Building to consider Local Law Introductory No. 11 of 2022 and Local Law Introductory No. 12 of 2022 to amend Chapter 230 of the Village Code, Zoning, determining that the Proposed Action is a Type 1 Action under SEQRA, declaring the Village Board to be Lead Agency under SEQRA, issuing the EAF and CAF and referring the necessary documents to the Village Planning Board, Waterfront Advisory Committee and Westchester County Planning Board as required by law.
Resolution, 146 pages. Attached to agenda item: “Proposed Resolutions — Consider scheduling a Public Hearing for September 19, 2022, at 7 PM, in the Georgianna Grant Meeting Room of the Stanley H. Kellerhouse Municipal Building to consider Local Law Introductory No. 11”
Retrieved 2026-07-31 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
Appendix A - Proposed Local Laws
Appendix B - FEAF Part 2 to come
Appendix C - Village CAF 1
Appendix D - Buildout Backup Tables 1
Appendix E - Rutgers CUPR Multipliers 1
HSRG and LI Zoning Amd FEAF Part 1 2022.08.31 signed
HSRG and LI Zoning Amd FEAF Supplemental Narrative 2022.08.31
Res 129-2022 LL 11 12 of 2022
Extracted text
Traffic Impact Study
Environmental, Planning, and Engineering Consultants
34 South Broadway
Suite 300
White Plains, NY 10601
tel: 914 949-7336
fax: 914 949-7559
www.akrf.com
Offices in New York ● New Jersey ● Pennsylvania ● Maryland ● Connecticut
Technical Memorandum
To:
From:
AKRF, Inc.
Date:
July 6, 2022
Re:
HSRG Overlay and LI District Zoning Amendments – Traffic Impact Study (Full
Buildout)
This Traffic Impact Study (TIS) presents the detailed traffic analysis that was completed to assess the
potential traffic and transportation impacts related to the theoretical maximum buildout projected under the
proposed Harmon/South Riverside Gateway (HSRG) Overlay and Light Industrial (LI) District zoning
amendments in the Village of Croton-on-Hudson (the “Proposed Action”).
Prior to the preparation of the TIS, AKRF prepared preliminary trip generation numbers (summarized in
the attached February 25, 2022 memorandum, see Attachment A), to determine if the incremental trip
generation numbers associated with the theoretical maximum buildout would exceed the 100 vehicle-trip
threshold for any given peak hour that would require a quantified traffic analysis in order to satisfy the State
Environmental Quality Review Act (SEQRA) requirements. As this threshold of 100-vehicle trips was
found to be exceeded during at least one peak hour, the quantified analysis, as presented in this
memorandum, was conducted to assess the potential for traffic impacts, under SEQRA, as assumed through
the conservative buildout calculations.
The theoretical maximum buildout scenario for the HSRG Overlay parcels resulted in a total of 383
residential units and 583 off-street parking spaces. The theoretical maximum buildout scenario for the LI
district parcels resulted in a total of 87 residential units, 21,831 square feet of ground floor commercial
space, and 142 off-street parking spaces (55 spaces for commercial uses and 87 spaces for residential uses).
Complete lists of assumptions utilized to complete the buildout and parking calculations, which have been
vetted through the Village, is included in the FEAF Part 3 Supplemental Narrative prepared by AKRF.
Based on the maximum theoretical buildout scenarios presented in Tables 3 and 4 of the FEAF Part 3
Supplemental Narrative, up to 470 residential units, 21,831 sf of commercial floor area, and 725 off-street
parking spaces could theoretically be developed within the overall Project Area as a result of the Proposed
Action. As previously discussed, the chance of either scenario fully occurring, even over a long period of
time, is highly unlikely.
This TIS describes traffic operations for existing conditions within the Study Area and for conditions in the
future with the Proposed Action (the “Build” analysis).
July 6, 2022
A. TRAFFIC ANALYSIS
DATA COLLECTION
Turning Movement Counts (TMCs) and Vehicle Classification Counts (VCC) were collected at the
following locations for the weekday AM (6:30 to 9:30 AM) and PM (4:00 to 6:00 PM) periods in April,
2022:
1.
Croton Point Ave. and Veterans Plaza (signalized)
2.
Croton Point Ave. and Rt. 9/9A Southbound Ramps (signalized)
3.
Croton Point Ave. and Rt. 9/9A Northbound Ramps (signalized)
4.
Croton Point Ave. and S. Riverside Ave. (signalized)
5.
S. Riverside Ave. and Benedict Blvd. (signalized)
6.
S. Riverside Ave. and Clinton St. (unsignalized)
Field inventories of the intersection roadway geometries were conducted and signal timing plans were
obtained from the New York State Department of Transportation (NYSDOT) and the Village of Croton-
on-Hudson. Descriptions of the study area roadways and agency signal timing plans are provided in
Attachment A.
PRELIMINARY SCREENING
Prior to conducting the traffic analysis, a preliminary screening analysis was completed to estimate the
likelihood of traffic impacts occurring at of any of the six intersections where traffic counts were counted
and proposed for analysis (summarized in the attached May 27, 2022 memorandum, see Attachment A).
This screening was based on an assessment of the collected traffic volumes and proposed trip assignments.
Based on the results of this screening, the number of intersections analyzed as part of the TIS was reduced
from six to five (with the intersection of South Riverside Ave. and Clinton Street screening out). As a result,
the following five signalized intersections have been selected for quantified analysis in the TIS:
1.
Croton Point Ave. and Veterans Plaza
2.
Croton Point Ave. and Rt. 9/9A Southbound Ramps
3.
Croton Point Ave. and Rt. 9/9A Northbound Ramps
4.
Croton Point Ave. and S. Riverside Ave.
5.
S. Riverside Ave. and Benedict Blvd.
TRAFFIC VOLUME DEVELOPMENT
2022 EXISTING VOLUMES
The 2022 Existing conditions traffic volumes are based on the TMC data collected at the study area
intersection in April 2022 during the weekday AM (6:30 AM – 9:30 AM) and PM (4:00 PM – 6:00 PM)
peak periods. Data collection sheets are provided in Appendix A.
2042 BUILD CONDITIONS
For the purposes of this analysis, it was conservatively assumed that the future design year (i.e., the future
year by which the full theoretical buildout from the Proposed Action would occur) would be 2042 (2022 +
20 years). Applying this assumption is consistent with the methodology utilized for the assessment of
potential traffic impacts from the 2010-2011 HSRG Overlay zoning amendments.
Future 2042 grown traffic volumes were developed by increasing the Existing 2022 traffic volumes in the
study by a 1 percent per year compounded growth rate. This growth rate reflected increases in background
traffic growth that would be expected to occur with or without the rezoning. 2042 Future Build traffic
Village of Croton-on-Hudson Board of Trustees
July 6, 2022
volumes were developed by adding the trips estimated to be generated by the Proposed Action (“Project
Generated trips”) to the 2042 grown traffic volumes.
The Existing 2022, 2042 Grown, Project Generated, and 2042 Build traffic volumes are illustrated in
Figures 1 through 8.
The trip generation (as presented in AKRF’s February 25, 2022 memorandum to the Village, see
Attachment A) was based on data presented in the Institute of Transportation Engineers (ITE) Trip
Generation Manual, 11th Edition. Assumptions regarding potential driveway locations were utilized to
develop trip assignments for the Proposed Action’s theoretical maximum buildout for the weekday AM and
PM peak periods. Individual trip assignments were developed for groups of parcels (“zones”) assumed to
share common driveways/access points. Figures 9 and 10 illustrate the zone locations and reference the
parcels included in each zone. The cumulative trip assignments were then utilized to estimate the increase
in traffic that would pass through each study area intersection as a result of the Proposed Action (see
Attachment A for tables which illustrate the development of the parcel trip assignments for the HSRG
Overlay and LI District).
CAPACITY ANALYSIS
Potential impacts of the Proposed Action were analyzed using methodologies based on the Highway
Capacity Manual, 6th Edition (HCM 6) methodology (Synchro 11 software) to calculate existing and future
traffic operating conditions (Level of Service (“LOS”) and total delay) at each of the Study Area
intersections. LOS is based on a grading scale of “A” through “F” with “A” representing optimum traffic
conditions and “F” representing poor traffic conditions (LOS D or better is typically considered acceptable
operating conditions). Further descriptions of the capacity analysis methodology are provided in
Attachment B.
For the purpose of this analysis, traffic impacts are identified as: (1) any change from LOS D or better to
LOS E or F; (2) any change from LOS E to LOS F; or (3) any increase of 10 percent or greater in delay for
LOS F between Existing and Build conditions. The significant impact criteria are applied to the
approach/lane group LOS for signalized intersections and approach/movement group LOS for unsignalized
intersections.
Table 1 presents a comparison of the 2022 Existing and 2042 Build LOS conditions for the Proposed
Action. Synchro 11 outputs for the 2042 Build condition are provided in Appendix B.
Under the 2042 Build condition, absent any additional improvements, there would be impacts expected at
the following locations;
Croton Point Avenue and Veterans Plaza—the southbound approach would deteriorate from LOS E to
LOS F during the Weekday AM peak hour and within LOS F during the Weekday PM peak hour.
Croton Point Avenue and Route 9/9A Southbound Ramps—the northbound approach would deteriorate
within LOS F during the Weekday AM and PM peak hours.
South Riverside Avenue and Benedict Boulevard—the westbound approach would deteriorate from
LOS D to LOS E during the Weekday PM peak hour. The southbound approach would deteriorate
within LOS F during the Weekday AM and PM peak hours.
POTENTIAL MITIGATION MEASURES
For the impacted locations described above, recommended potential mitigation measures are as follows:
Croton Point Avenue and Veterans Plaza—Signal timing adjustments
Croton Point Avenue and Route 9/9A Southbound Ramps—Signal timing adjustments
South Riverside Avenue and Benedict Boulevard—Signal timing adjustments and pavement/lane
restriping and/or narrowing of the median of Benedict Boulevard to provide two lanes at each approach
to South Riverside Avenue.
HSRG Overlay and LI District Zoning Amendments
Eastbound
LTR
0.10
4.4
A
LTR
0.15
8.8
A
LTR
0.12
4.5
A
LTR
0.19
12.2
B
L
0.20
2.8
A
L
0.29
4.6
A
L
0.11
2.6
A
L
0.19
7.3
A
LTR
0.20
4.5
A
LTR
0.28
7.6
A
LTR
0.09
3.8
A
LTR
0.17
9.0
A
LTR
0.50
30.2
C
LTR
0.57
36.1
D
LTR
0.70
27.9
C
LTR
0.53
13.3
B
R
0.25
14.0
B
R
0.23
10.0
A
R
0.47
13.3
B
R
0.40
7.1
A
Southbound
LTR
0.16
79.5
E
LTR
0.65
110.4
F
LTR
0.33
90.0
F
LTR
1.26
226.3
F
8.0
A
14.4
B
12.9
B
36.3
D
Eastbound
TR
0.30
45.4
D
TR
0.44
49.1
D
TR
0.42
40.2
D
TR
0.58
43.5
D
Westbound
LT
0.23
5.2
A
LT
0.37
8.5
A
LT
0.20
2.4
A
LT
0.32
4.9
A
LTR
0.77
85.1
F
LTR
0.84
87.7
F
LTR
0.59
85.7
F
LTR
0.71
86.2
F
R
0.78
87.1
F
R
0.83
87.6
F
R
0.51
81.9
F
R
0.50
73.2
E
38.0
D
38.3
D
28.4
C
30.8
C
Eastbound
LTR
0.09
5.8
A
LTR
0.15
5.1
A
LTR
0.16
8.9
A
LTR
0.27
10.5
B
Westbound
LTR
0.20
6.8
A
LTR
0.34
8.8
A
LTR
0.24
7.3
A
LTR
0.38
9.2
A
Northbound
LTR
0.97
104.4
F
LTR
1.30
203.9
F
LTR
1.59
318.1
F
LTR
2.24
597.1
F
Southbound
LTR
-
-
-
LTR
0.06
30.3
C
LTR
-
-
-
LTR
0.02
35.0
C
36.3
D
61.5
E
125.8
F
226.9
F
Croton Point Avenue
Eastbound
LR
0.24
8.9
A
LR
0.34
10.1
B
LR
0.43
9.4
A
LR
0.61
12.9
B
Northbound
LT
0.08
10.9
B
LT
0.13
11.2
B
LT
0.34
13.2
B
LT
0.45
14.5
B
T
0.06
10.9
B
T
0.09
11.1
B
T
0.16
11.8
B
T
0.21
12.2
B
R
0.26
0.4
A
R
0.59
4.2
A
R
0.26
3.0
A
R
0.22
0.3
A
5.4
A
7.5
A
9.7
A
11.0
B
Eastbound
LTR
0.29
17.4
B
LTR
0.36
18.4
B
LTR
0.42
19.9
B
LTR
0.60
24.5
C
Westbound
LTR
0.37
17.3
B
LTR
0.52
20.2
C
LTR
0.80
29.1
C
LTR
1.05
73.5
E
LT
0.26
12.2
B
LT
0.44
14.8
B
LT
0.49
15.2
B
LT
0.72
21.3
C
R
0.04
2.1
A
R
0.08
3.5
A
R
0.04
2.1
A
R
0.08
3.6
A
Southbound
LTR
0.79
25.1
C
LTR
1.16
110.2
F
LTR
0.57
17.0
B
LTR
1.11
97.3
F
19.7
B
59.6
E
21.0
C
57.8
E
Notes: L = Left Turn, T = Through, R = Right Turn, LOS = Level of Service, EB = Eastbound, WB = Westbound, NB = Northbound, SB = Southbound.
Yellow highlights denote potential traffic impact locations.
S. Riverside Avenue and Benedict Boulevard
Benedict Boulevard
S Riverside Avenue
Northbound
Intersection
Intersection
Intersection
Intersection
Intersection
S Riverside Avenue
Southbound
Intersection
Intersection
Intersection
Intersection
Intersection
Croton Point Avenue and S. Riverside Avenue
Croton Point Avenue
Route 9/9A NB Ramps
Intersection
Intersection
Croton Point Avenue and Route 9/9A NB Ramps
Intersection
Croton Point Avenue
Route 9/9A SB On-Ramp
Southbound
Croton Point Avenue and Route 9/9A SB On-Ramp
Intersection
Intersection
Intersection
Intersection
Intersection
Veterans Plaza
Northbound
Intersection
Intersection
Croton Point Avenue
Westbound
Croton Point Avenue and Veterans Plaza
LOS
Lane
Group
v/c Ratio
Delay
(sec)
LOS
Lane
Group
v/c Ratio
Delay
(sec)
LOS
Lane
Group
v/c Ratio
Delay
(sec)
Table 1
2022 Existing Conditions vs. 2042 Build Conditions LOS Analysis
Approach
Weekday AM
Weekday PM
2022 Existing Conditions
2042 Build Conditions
2022 Existing Conditions
2042 Build Conditions
Lane
Group
v/c Ratio
Delay
(sec)
LOS
Village of Croton-on-Hudson Board of Trustees
July 6, 2022
Because the Proposed Action represents a proposed Local Law (rezoning) as opposed to a specific
development proposal, assumptions were made to evaluate potential impacts should the Local Law be
adopted. As noted elsewhere in the SEQRA documents for the Proposed Action, should the Local Law be
adopted, individual development proposals that come before the Village would be subject to site-specific
environmental reviews pursuant to SEQRA. Specifically, a special permit approval process would subject
individual development proposals on the study area parcels to a site-specific environmental review
(including site-specific traffic studies) under SEQRA in connection with discretionary land use approvals
and public hearings through the Village Board of Trustees, Village Planning Board, Village Waterfront
Advisory Committee (WAC), and other involved agencies. Any future special permit for new development
on Village-owned parcels would not be able to proceed without the Village’s selection of a developer
through a competitive request for proposals (RFP) process. Within each site-specific traffic study, any
impacts and mitigation, if required, for that specific project will be identified and addressed on a case-by-
case basis.
PUBLIC TRANSIT
Public rail and bus service is offered in the study area. The Metropolitan Transportation Authority’s (MTA)
Metro-North Railroad offers commuter rail service in the study area via its Hudson Line. Amtrak offers
regional passenger rail service via its Empire Corridor Line. The Croton-Harmon train station is the stop
located in the immediate vicinity of the study area and is accessible via Veterans Plaza.
The Westchester County Bee-Line Bus System operates the following bus routes within the study area:
Routes 10 (“Croton Commuter”), 11 (“Croton Express”), and 14 (“Peekskill-Ossining-White Plains”).
These bus routes offer service to several other Westchester County municipalities. Routes 10 and 11 make
stops at the Croton-Harmon train station.
No significant changes are expected in public transit conditions by the Build year 2042. However, it is the
policy of the mass transit agencies (Metro-North Commuter Railroad and the Bee-Line Bus System) to
adjust their operating schedules to reflect demand as needed.
PEDESTRIAN AND BICYCLE CONDITIONS
Pedestrian volumes were observed to be low to moderate in the study area. Sidewalks exist along the
following study area roadways: Croton Point Avenue, South Riverside Avenue, and the Metro-North
parking lot driveways/Veterans Plaza. Observations conducted during field visits showed low to moderate
levels of pedestrian activity at the study area intersections. Sidewalks are present along Croton Point
Avenue, South Riverside Avenue, Veterans Plaza, and Benedict Boulevard. Crosswalks and pedestrian
signals are present at each of the five study area intersections. Many of the pedestrian facilities along Croton
Point Avenue were recently improved or installed as part of the Croton Point Avenue Improvement project.
Bicycle volumes were observed to be low in the study area. Bike lanes were recently installed along both
sides of Croton Point Avenue as part of the Croton Point Avenue Improvement project.
PARKING
Estimated parking supply numbers associated with the Proposed Action were calculated based on the
buildout assumptions included in the FEAF Part 3 Supplemental Narrative which yield an estimated parking
supply requirement of 725 spaces.
B. OVERALL CONCLUSIONS
Assuming the full theoretical maximum buildout under the proposed rezoning occurs by 2042, it is
anticipated that traffic impacts could be experienced at the following three intersections studied:
Croton Point Avenue and Veterans Plaza
Croton Point Avenue and Route 9/9A Southbound Ramps
South Riverside Avenue and Benedict Boulevard
Village of Croton-on-Hudson Board of Trustees
July 6, 2022
Potential mitigation measures include traffic signal timing adjustments, pavement/lane restriping, and
narrowing roadway medians.
Should the Proposed Action be approved and the Project Area rezoned, the Village’s special permit
approval process would subject individual development proposals throughout the Project Area to a site-
specific environmental review under SEQRA in connection with discretionary land use approvals and
public hearings through the Village Board of Trustees, Village Planning Board, Village WAC, and other
involved agencies. Through this discretionary approval process, potential traffic and parking impacts, as
well as any mitigation measures, would be analyzed on a case-by-case basis.
July 6, 2022
TRAFFIC IMPACT STUDY FIGURES
Figure V-1
Existing 2022 AM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
Figure V-2
Existing 2022 PM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
Figure V-3
2042 Grown AM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
Figure V-4
2042 Grown PM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
Figure V-5
Project Generated AM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
Figure V-6
Project Generated PM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
Figure V-7
2042 Build AM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
Figure V-8
2042 Build PM Peak Hour Volumes
HSRG Overlay and LI District Zoning Amendments
S. Riverside Ave.
Benedict Blvd.
Benedict Blvd.
Metro-North Parking
Route 9/9A SB Off-Ramp
Restaurant Driveway
Croton Point Ave.
Route 9/9A SB On-Ramp
Route 9/9A NB Ramps
S. Riverside Ave.
Veterans Plaza
ATTACHMENT A
Study Area Intersection Roadway Descriptions and Jurisdiction Map
Agency Traffic Signal Timing Plans
Turning Movement Count (TMC) Data
Trip Generation Backup
- Trip Assignment Zone Maps
- Zone Trip Generation Tables
- Zone Trip Assignment Detail Tables
Previous AKRF Memorandums
- Trip Generation Memorandum (2/25/2022)
- Traffic Screening Memorandum (5/27/2022)
Study Area Intersection Roadway Descriptions
and Jurisdiction Map
ROADWAY CHARACTERISTICS
The following is a brief description of the major roadways within the study area. Figure A-1
shows the maintenance jurisdictions of each of the roadways as sourced from NYSDOT.
U.S. Route 9. U.S. Route 9 is a divided highway that generally runs in a north-south direction and
provides 2 to 3 moving lanes in each direction within the study area. U.S. Route 9 is under the
jurisdiction of the New York State Department of Transportation (NYSDOT). South of Croton
Point Avenue, U.S. Route 9 is also designated as NYS Route 9A. Based on field observations,
the pavement for the U.S. Route 9 ramps at Croton Point Avenue is generally in excellent
condition.
Croton Point Avenue. Croton Point Avenue is a local arterial that generally runs in an east-west
direction within the study area and is under the jurisdiction of NYSDOT, Westchester County
Department of Public Works, and the Village of Croton-on-Hudson. Croton Point Avenue
generally provides one to two moving lanes in each direction and varies in width from
approximately 28 to 50 feet within the study area. Between the northbound U.S. Route 9 ramps
and South Riverside Avenue, Croton Point Avenue is also designated as NYS Route 9A. Based
on field observations, the pavement along Croton Point Avenue within the study area varies
between good-to-excellent condition. Sidewalks and bike lanes are provided on both sides of
Croton Point Avenue within the study area.
South Riverside Avenue. South Riverside Avenue is a local arterial that generally traverses in a
north-south direction and is maintained by the Village of Croton-on-Hudson. South Riverside
Avenue generally provides two moving lanes in each direction and varies in width from 40 to 48
feet within the study area. South Riverside Avenue is also designated as NYS Route 9A north of
its intersection with Croton Point Avenue. Based on field observations, the pavement along South
Riverside Avenue within the study area is generally in fair condition. Sidewalks are provided on
both sides of South Riverside Avenue within the study area.
Veterans Plaza/Metro-North Train Station Parking Lot Driveway. There are two parking lots
provided for Metro-North Commuter Railroad riders at the Croton-Harmon station. The main lot
is located on the south side of Croton Point Avenue and a smaller auxiliary lot is located on the
north side of Croton Point Avenue. The driveway to the main lot is also designated as Veterans
Plaza and is a local roadway maintained by the Village of Croton-on-Hudson. Veterans Plaza
generally provides one to two moving lanes in each direction and is approximately 29 feet wide
at its intersection with Croton Point Avenue. The driveway to the northern lot is a curb cut
entrance with one entrance lane and one exit lane, approximately 34 feet in total width. Based on
field observations, the pavement along the Veterans Plaza and the northern Metro-North parking
lot driveway is generally in good condition.
Benedict Boulevard. Benedict Boulevard is a major collector roadway that generally traverses in
an east-west direction and is maintained by the Village of Croton-on-Hudson. Benedict Boulevard
generally provides one moving lane in each direction with a landscaped median within the study
area. Based on field observations, the pavement along Benedict Boulevard is generally in good
condition. Sidewalks are provided on both sides of Benedict Boulevard within the study area.
.
© Latitude Geographics Group Ltd.
0.1
THIS MAP IS NOT TO BE USED FOR NAVIGATION
NAD_1983_UTM_Zone_18N
Miles
0.1
Notes
Please enter the notes
Legend
This map is a user generated static output from an Internet mapping site and is for
reference only. Data layers that appear on this map may or may not be accurate,
current, or otherwise reliable.
0.06
1: 4,000
New York State Department of Transportation
Roadway Maintenance Jurisdictions
Maintenance Jurisdiction
01 NYSDOT
02 County
03 Town
04 City or village
31 NYS Thruway
Interstate
900 Route
US Highway
State Highway
County Touring
County Highway
StateShoreline_Lines
Cities_Towns_Shore
Towns_Shoreline
NYS_Background
FIGURE A-1
Agency Traffic Signal Timing Plans
Signal #
Electric Company:
Intersection:
Zip:
CITY
VILLAGE
TOWN
OF:
CON EDISON
CROTON POINT AVE @ RT 9 RAMPS
CROTON-ON-HUDSON
W-636/W-637
W-636/W-637
D26xxxx
8780.41
55.11-9
Signal:
File:
D/HWP:
PIN:
in the Village of CROTON‐ON‐HUDSON
STATE OF NEW YORK - DEPARTMENT OF TRANSPORTATION
TRAFFIC AND SAFETY DIVISION
Plan of
Operation
Apr 2021
Printed: 4/15/2022
ROUTE 9 SB OFF-RAMP
CROTON POINT AVE
ROUTE 9 SB ON-RAMP
Ø7
SP 7
OVL-3
Ø1
SP 1
PED 2
Ø6
SP 12
Ø3
SP 3
OVL-1
Ø1+Ø2+Ø4
SP 9
Ø3
SP 13
ROUTE 9 NB RAMPS
CROTON POINT AVE
2 1 3 4
6 7 8
Phase Sequence
W-637
W-636
PED 1
Ø2
SP 11
PED 3
Ø7
SP 10
PED 4
Ø2
SP 14
A
B
C
D
E
F
G
H
I
J
K
L
M
N
N
#23
#22
#21
#24
N
T J
L
R
W
QUEUE LOOP
Ø7
QUEUE
LOOP
Ø3
S‐1
S‐2
S‐3
S‐4
S‐5
S‐6
S‐7
MICROWAVE
DETECTORS 9A, 9B
Ø3
2-6
W-637 FACES
J
SIGNS
7-14
W-636 FACES
SIGNS
OVL-2
Ø6+Ø8
SP 8
OVL-6
Ø4+Ø6
SP 6
OVL-12
Ø2+Ø8
SP 2
PREEMPT ‘4’ - Ø4
PREEMPT ‘3’ - Ø3
DWY.
Phase Times [1.1.1]
Coordination Patterns [2.4] and Coordination Split Tables [2.7.1]
Pat#
Cyc
Off
Split
Seq
Pat#
Cyc
Off
Split
Seq Pat#
Cyc
Off
Split
Seq
Pat#
Cyc
Off
Split
Seq
Min Green
Gap, Ext
Max 1
Max 2
Ring/Startup [1.1.4]
Yel Clearance
3.5 3.5
3.5
Phs
Ring
Start
Enable
Red Clearance
1.5 1.5
1.5
Red
ON
Walk
Green
ON
Ped Clearance
Red
ON
Red Revert
Red
ON
Add Initial
Red
OFF
Max Initial
Green
ON
Time B4 Reduct
Red
ON
Cars B4 Reduct
Split
Split
Red
ON
Time To Reduce
Coor
Coor
Reduce By
NON Max NON NON NON Max NON NON
NON NON NON NON NON NON NON NON Test OpMode
Min Gap
Coor
Coor
Correction
SHRT/LNG
DyMaxLim
NON Max NON NON NON Max NON NON
NON NON NON NON NON NON NON NON Maximum
MAX 1
Max Step
Coor
Coor
Force-Off
Float
Options [1.1.2]
NON Max NON NON NON Max NON NON
NON NON NON NON NON NON NON NON Closed Loop
ON
Enable
ON ON ON ON OFF ON ON ON
Coor
Coor
Stop-in-Walk
ON
Min Recall
OFF ON OFF OFF OFF ON OFF OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Auto Reset
ON
Max Recall
OFF OFF OFF OFF OFF OFF OFF OFF
Coor
Coor
Expand Splt
OFF
Ped Recall
OFF OFF OFF OFF OFF OFF OFF OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Ped Recycle
NO_RECYCLE
Soft Recall
OFF OFF OFF OFF OFF OFF OFF OFF
Coor
Coor
Before
TIMED
Lock Calls
OFF OFF ON OFF OFF OFF ON OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON After
TIMED
Auto Flash Entry
OFF OFF OFF OFF OFF OFF OFF OFF
Coor
Coor
Auto Flash Exit
OFF OFF OFF OFF OFF OFF OFF OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Auto Flash
Dual Entry
OFF OFF OFF OFF OFF OFF OFF OFF
Coor
Coor
Flash Yel
Enable Simul Gap
ON ON ON ON ON ON ON ON
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Flash Red
Gaurantee Passage OFF OFF OFF OFF OFF OFF OFF OFF
Coor
Coor
Rest In Walk
OFF OFF OFF OFF OFF OFF OFF OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Phase Mode
STD8
Conditon Service
OFF OFF OFF OFF OFF OFF OFF OFF
Coor
Coor
IO Mode
User
Non-Actuated 1
OFF OFF OFF OFF OFF OFF OFF OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Loc Flsh Start
ON
Non-Actuated 2
OFF OFF OFF OFF OFF OFF OFF OFF
Coor
Coor
Start Flash(s)
Add Init Calc
OFF OFF OFF OFF OFF OFF OFF OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Start AllRed(s)
Options+ [1.1.3]
Coor
Coor
Yellow < 3"
OFF
Reservice
OFF OFF OFF OFF OFF OFF OFF OFF
NON NON NON NON NON NON NON NON
NON NON NON NON NON NON NON NON Display Time
PedClr Thru Yel
OFF OFF OFF OFF OFF OFF OFF OFF
Red Revert
Skip Red No Call
OFF OFF OFF OFF OFF OFF OFF OFF
8 Phase Times/Options; Patterns/Splits; Ring Startup; Coord/Flash Mode; Unit Param
MCE Timeout
Red Rest
OFF OFF OFF OFF OFF OFF OFF OFF
16 Phase Times/Options; Patterns/Splits; Ring Startup; Coord/Flash Mode; Unit Param
Feature Profile
Max II
OFF OFF OFF OFF OFF OFF OFF OFF
Overlaps; Channel Settings; Coord Alt Table+ (values not associated with time-of-day)
Free Ring Seq
Call Phase
Detection; Sample Time and Unit Parameters related to detection
Auxswitch
STOPTM
Conflicting Phase
Preemption and Alternate Phase Time and Phase Options
SDLC Retry
Omit Yellow
Annual Schedule
TS2 Det Faults
ON
Ped Delay
OFF OFF OFF OFF OFF OFF OFF OFF
Day Plans; Action Tables; Coord Alt Table+ (values varied by time-of-day)
Auto Ped Clear
Grn/Ped Delay
Communications; Secutiry; I/O Setup
SDLC Retry
Misc - Events/Alarms; Call/Inhibit/Redirect; P/OLAP Auto Flash; CIC; Misc Unit Param
RT 9 RAMPS @ CROTON POINT A
Auto Flash [1.4.1]
Unit Params [1.2.1]
Coord Modes [2.1]
OFF
04/07/22
PH OVER
Page#
1A&1B
Overlap 1-16 Program Parms & Parm+ [1.5.2.1] [1.5.2.2]
Coord Transition, CoorPhs [2.5]
Pat# Short Long Dwell
E-Yld
Offset
RetHld Float Min Veh Perm Min Ped Perm
Included Ø
Type NORMAL
Included Ø
Type NORMAL
EndGRN
ON
OFF
OFF
ON
Modifier Ø
Grn
9 Modifier Ø
Grn
EndGRN
ON
OFF
OFF
ON
Conflict Ø
Yel
Conflict Ø
Yel
3.5
EndGRN
OFF
OFF
OFF
OFF
A
Conflict Olap
Red
I
Conflict Olap
Red
1.5
EndGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
EndGRN
OFF
OFF
OFF
OFF
Included Ø
Type NORMAL
Included Ø
Type NORMAL
EndGRN
OFF
OFF
OFF
OFF
Modifier Ø
Grn
10 Modifier Ø
Grn
EndGRN
ON
OFF
OFF
ON
Conflict Ø
Yel
Conflict Ø
Yel
3.5
EndGRN
ON
OFF
OFF
ON
B
Conflict Olap
Red
J Conflict Olap
Red
1.5
EndGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
EndGRN
OFF
OFF
OFF
OFF
Included Ø
Type NORMAL
Included Ø
Type NORMAL
EndGRN
OFF
OFF
OFF
OFF
Modifier Ø
Grn
11 Modifier Ø
Grn
EndGRN
OFF
OFF
OFF
OFF
Conflict Ø
Yel
Conflict Ø
Yel
3.5
EndGRN
OFF
OFF
OFF
OFF
C
Conflict Olap
Red
K Conflict Olap
Red
1.5
EndGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
EndGRN
OFF
OFF
OFF
OFF
Included Ø
Type NORMAL
Included Ø
Type NORMAL
EndGRN
OFF
OFF
OFF
OFF
Modifier Ø
Grn
12 Modifier Ø
Grn
EndGRN
OFF
OFF
OFF
OFF
Conflict Ø
Yel
3.5
Conflict Ø
Yel
EndGRN
OFF
OFF
OFF
OFF
D
Conflict Olap
Red
1.5
L Conflict Olap
Red
EndGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
EndGRN
OFF
OFF
OFF
OFF
Included Ø
Type NORMAL
Included Ø
Type NORMAL
EndGRN
OFF
OFF
OFF
OFF
Modifier Ø
Grn
13 Modifier Ø
Grn
EndGRN
OFF
OFF
OFF
OFF
Conflict Ø
Yel
3.5
Conflict Ø
Yel
3.5
EndGRN
OFF
OFF
OFF
OFF
E
Conflict Olap
Red
1.5
M Conflict Olap
Red
1.5
EndGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
BegGRN
OFF
OFF
OFF
OFF
Included Ø
Type NORMAL
Included Ø
Type NORMAL
BegGRN
OFF
OFF
OFF
OFF
Modifier Ø
Grn
14 Modifier Ø
Grn
BegGRN
OFF
OFF
OFF
OFF
Conflict Ø
Yel
Conflict Ø
Yel
3.5
BegGRN
OFF
OFF
OFF
OFF
F
Conflict Olap
Red
N Conflict Olap
Red
1.5
BegGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
BegGRN
OFF
OFF
OFF
OFF
Included Ø
Type NORMAL
Included Ø
Type NORMAL
BegGRN
OFF
OFF
OFF
OFF
Modifier Ø
Grn
15 Modifier Ø
Grn
BegGRN
OFF
OFF
OFF
OFF
Conflict Ø
Yel
3.5
Conflict Ø
Yel
3.5
BegGRN
OFF
OFF
OFF
OFF
G
Conflict Olap
Red
1.5
O Conflict Olap
Red
1.5
BegGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
BegGRN
OFF
OFF
OFF
OFF
Included Ø
Type NORMAL
Included Ø
Type NORMAL
BegGRN
OFF
OFF
OFF
OFF
Modifier Ø
Grn
16 Modifier Ø
Grn
BegGRN
OFF
OFF
OFF
OFF
Conflict Ø
Yel
3.5
Conflict Ø
Yel
3.5
BegGRN
OFF
OFF
OFF
OFF
H
Conflict Olap
Red
1.5
P Conflict Olap
Red
1.5
BegGRN
OFF
OFF
OFF
OFF
Conflict Ped
LG
Conflict Ped
LG
BegGRN
OFF
OFF
OFF
OFF
Channel Settings [1.8.1]
BegGRN
OFF
OFF
OFF
OFF
……Channel ->>
11 12
BegGRN
OFF
OFF
OFF
OFF
Phase / Olap #
BegGRN
OFF
OFF
OFF
OFF
Channel Type
OLP OLP VEH VEH VEH OLP VEH OLP OLP
PED
PED PED VEH PED VEH VEH VEH VEH VEH VEH VEH VEH VEH
VEH
BegGRN
OFF
OFF
OFF
OFF
Channel Flash
Red Red Red Red Red Red Red Red Red
Red
Red Red
Red
Red Red Red DRK DRK DRK DRK DRK DRK DRK
DRK
BegGRN
OFF
OFF
OFF
OFF
Alt Hz
OFF OFF OFF OFF OFF OFF OFF OFF OFF
OFF
OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
OFF
BegGRN
OFF
OFF
OFF
OFF
Channel+ Settings [1.8.4]
BegGRN
OFF
OFF
OFF
OFF
……Channel ->>
11 12
BegGRN
OFF
OFF
OFF
OFF
Flash Red+
OFFOFFOFFOFFOFFOFFOFFOFFOFF
OFF
OFFOFF OFF OFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF
Channel Params[1.8.3]
Flash Yellow+
OFFOFFOFFOFFOFFOFFOFFOFFOFF
OFF
OFFOFF OFF OFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF
User
SINGLE
OFF
Flash Green+
OFFOFFOFFOFFOFFOFFOFFOFFOFF
OFF
OFFOFF OFF OFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF
Flash Inh Red+
OFFOFFOFFOFFOFFOFFOFFOFFOFF
OFF
OFFOFF OFF OFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF
Olap Ovrd
Invert Rail Input
C1 IO Mode
Single BIU Map
No Shortway Ø
Overlap Conflict Lock
OFF
Overlap Lock Inhibit
ON
OFF
Parent Ph Clearance
7637 RT 9 RAMPS @ CROTON POINT AVE
OFF
Extra Included Ph
04/07/22
Veh Par 1-64 [5.1]
Veh Par 1-64 [5.1]
Vehicle Options 1-64 [5.2]
Vehicle Options 1-64 [5.2]
Parameters+ 1-64 [5.3]
Det
Call Swi Dlay
Ext
Que
No
Max Err
Fail
Det
Call
Swi Dlay
Ext
Que
No
Max
Err
Fail
Det
Call
Ext
Que
Add
Red
Yell occ
vol
Det
Call
Ext
Que Add
Red
Yell occ vol
Det
oc
oc
oc
Dlay Dlay
Type
Src
#
Ø
Ø
Act
Pres Cnt Time
#
Ø
Ø
Act
Pres Cnt
Time
#
Init
Lock Lock
#
AddInit Lock Lock
#
G
Y
R
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
ON ON OFF
ON OFF OFF OFF OFF
ON
ON OFF ON OFF OFF OFFOFF
OFF OFFOFF
NORM
Parameters+ 1-64 [5.3]
Ped Det Parms [5.4]
Unit Paramters [1.2.1]
Det
occ occ
occ
Dlay Dlay Type
Src Det occ
occ
occ
Dlay Dlay
Src
Det
occ
occ
occ
Dlay Dlay Type
Src
Det Call No
Max
Err
TS2 Det Faults
ON
#
Grn Yell Red
#
Grn
Yell
Red
#
Grn
Yell
Red
#
Ø
Act
Pres
Cnt
Vol/Occ Report Parm [1.5.8]
OFFOFF OFF
NORM 3
44 OFF
OFF
OFF
NORM
55 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 13
45 OFF
OFF
OFF
NORM
56 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 4
46 OFF
OFF
OFF
NORM
57 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 7
47 OFF
OFF
OFF
NORM
58 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 14
48 OFF
OFF
OFF
NORM
59 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 17
49 OFF
OFF
OFF
NORM
60 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 0
50 OFF
OFF
OFF
NORM
61 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 0
51 OFF
OFF
OFF
NORM
62 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 0
52 OFF
OFF
OFF
NORM
63 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 0
53 OFF
OFF
OFF
NORM
64 OFF OFF
OFF
NORM 0
OFFOFF OFF
NORM 0
54 OFF
OFF
OFF
NORM
###
Type
4/7/2022
RT 9 RAMPS @ CROTON POINT AVE
Vol/Occ Period Minutes
Vol/Occ Period Minutes
Preemption Times [3.1], Options+ [3.6]
Track Clear Phases [3.2], Track Clear Overlaps+ [3.5]
Pre #
Enable
Type
Output
Delay
MinDura
Pre # Track Phases
Track Overlaps
ON
RAIL
Dwell
ON
RAIL
Dwell
ON
EMERG
Dwell
ON
EMERG
Dwell
ON
EMERG
Dwell
ON
EMERG
Dwell
Pre #
MaxPres
MinGrn
MinWlk
PedClr
Co+Pre
Dwell Phases [3.2] and Overlaps+ [3.5]
ON
Pre #
ON
Phases
ON
Overlaps 0
ON
Peds
ON
Phases
ON
Overlaps 0
Pre #
Track Grn Min Dwell Ext Dwell PedClr+
Yel
Peds
Phases
Overlaps 2
Peds
Phases
Overlaps 1
Peds
Pre #
Red
Pattern
Skip
Phases
OFF
Overlaps 0
OFF
Peds
OFF
Phases
OFF
Overlaps 0
OFF
Peds
OFF
Preemption Options+ [3.6]
Low Priority Preempts
Exit Phases [3.2]
Pre # Lock
Override
Override
Flsh
Pre #
Type
Min
Max
Pre # Exit Phase
Auto Flsh
Higher
Dwell Link
OFF
ON
ON
ON
OFF
OFF
ON
ON
ON
OFF
OFF
OFF
ON
ON
OFF
OFF
OFF
ON
ON
OFF
ON
ON
ON
OFF
Unit Parameters [1.2.1]
ON
ON
ON
OFF
Stop Timer Over Preempt
OFF
Preempt or Ext Output
PRE
Max Seek Track Time
Max Seek Dwell Time
Channel Parameters [1.8.3]
D Conn Mappings
None
Pre Invert Rail Input
OFF
4/7/2022
RT 9 RAMPS @ CROTON POINT AVE
Alt# 1 Times Table [1.1.6.1.2]
Alt# 1 Veh Parameters [5.5.1.1]
Column#..... ->
Column#..... ->
Assign Ø
Assign Det#
Min Grn
Call
Gap, Ext
Swiitch
Max 1
Delay
Max 2
Extend
Yel Clr
Queue
Red Clr
No Activity
Walk
Max Presence
Ped Clr
Erratic Count
Alt# 2 Times Table [1.1.6.1.2]
Fail Time
Column#..... ->
Alt# 1 Veh Options [5.5.1.2]
Assign Ø
Column#..... ->
Min Grn
Assign Det#
Gap, Ext
Call
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max 1
Extend
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max 2
Queue
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Yel Clr
Added Initial
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Red Clr
Red Lock
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Walk
Yellow Lock
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Ped Clr
Occupancy
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Alt# 3 Times Table [1.1.6.1.3]
Volume
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Column#..... ->
Alt# 1 Veh Parameters+ [5.5.1.3]
Assign Ø
Column#..... ->
Min Grn
Assign Det#
Gap, Ext
Occ-on-green
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max 1
Occ-on-yellow
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max 2
Occ-on-red
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Yel Clr
Delay Phase 1
Red Clr
Delay Phase 2
Walk
Detector Mode
NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM
Ped Clr
Source
Alt# 1 Options Table [1.1.6.2.1]
Alt# 1 Ped Parameters+ [5.5.1.4]
Column # ->
Column#..... ->
Assign Ø
Assign Det#
Lock Calls
ON
ON
ON
ON
ON
ON
ON
ON
Call
Soft Recall
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
No Activity
Dual Enrty
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max Presence
Enabl SimGap
ON
ON
ON
ON
ON
ON
ON
ON
Erratic Count
Guar Passage
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Rest In Walk
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Cond Service
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Reservice
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Non-Act 1
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Red Rest
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max2
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Ped Delay
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Conflicting Ø1
7637 RT 9 RAMPS @ CROTON POINT AVE
4/7/2022
Alt# 2 Options Table [1.1.6.2.2]
Alt# 2 Veh Parameters [5.5.2.1]
Column # ->
Column#..... ->
Assign Ø
Assign Det#
Lock Calls
ON
ON
ON
ON
ON
ON
ON
ON
Call
Soft Recall
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Swiitch
Dual Enrty
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Delay
Enabl SimGap
ON
ON
ON
ON
ON
ON
ON
ON
Extend
Guar Passage
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Queue
Rest In Walk
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
No Activity
Cond Service
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max Presence
Reservice
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Erratic Count
Non-Act 1
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Fail Time
Red Rest
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Alt# 2 Veh Options [5.5.2.2]
Max2
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Column#..... ->
Ped Delay
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Assign Det#
Conflicting Ø1
Call
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Alt# 3 Options Table [1.1.6.2.3]
Extend
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Column # ->
Queue
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Assign Ø
Added Initial
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Lock Calls
ON
ON
ON
ON
ON
ON
ON
ON
Red Lock
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Soft Recall
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Yellow Lock
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Dual Enrty
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Occupancy
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Enabl SimGap
ON
ON
ON
ON
ON
ON
ON
ON
Volume
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Guar Passage
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Alt# 2 Veh Parameters+ [5.5.2.3]
Rest In Walk
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Column#..... ->
Cond Service
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Assign Det#
Reservice
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Occ-on-green
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Non-Act 1
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Occ-on-yellow
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Red Rest
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Occ-on-red
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max2
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Delay Phase 1
Ped Delay
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Delay Phase 2
Conflicting Ø1
Detector Mode
NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM NORM
Alt# 4 Options Table [1.1.6.2.4]
Source
Column # ->
Alt# 2 Ped Parameters+ [5.5.2.4]
Assign Ø
Column#..... ->
Lock Calls
ON
ON
ON
ON
ON
ON
ON
ON
Assign Det#
Soft Recall
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Call
Dual Enrty
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
No Activity
Enabl SimGap
ON
ON
ON
ON
ON
ON
ON
ON
Max Presence
Guar Passage
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Erratic Count
Rest In Walk
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Cond Service
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Reservice
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Non-Act 1
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Red Rest
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Max2
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Ped Delay
OFF
OFF
OFF
OFF
OFF
OFF
OFF
OFF
Conflicting Ø1
4/7/2022
RT 9 RAMPS @ CROTON POINT AVE
Annual Schedule [4.3]
Month of Year
Day of Week
Date
Day Link
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
Plan
To
ON ON ON ON ON ON ON ON ON ON ON ON
OFF ON ON ON ON ON OFF
ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON ON
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
J
F
M
A
M
J
J
A
S
O
N
D
S
M
T
W
T
F
S
OFFOFFOFFOFFOFFOFF OFF OFFOFFOFFOFFOFF
OFFOFF OFF OFFOFFOFFOFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFFOFF
4/7/2022
RT 9 RAMPS @ CROTON POINT AVE
Day Plans [4.4]
Action Table [4.5]
Coord Alternate Tables - Pat+ [2.6]
Day Plan 1
Day Plan 2
Day Plan 3
Overlap Off
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Act#
Pat# A1
A2
A3
S1
S2
S3
S4
S5
S6
S7
S8
Pat#
ØOpt ØTime DetG Call Inh CIC CNA1
Dia
Max2
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Day Plan 4
Day Plan 5
Day Plan 6
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
10 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
11 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
12 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
13 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
14 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
15 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
16 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
17 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
18 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Day Plan 7
Day Plan 8
Day Plan 9
19 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
20 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
21 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
22 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
23 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
24 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Day Plan 10
Day Plan 11
Day Plan 12
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Day Plan 13
Day Plan 14
Day Plan 15
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
Hour Min Act
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
255 OFFOFFOFFOFFOFFOFFOFFOFFOFFOFF OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
OFF OFFOFFOFFOFFOFFOFFOFFOFF DFT OFF
04/07/22
RT 9 RAMPS @ CROTON POINT A
C1-USER IO Map [1.8.9.1 In ]
C1-USER IO Map [1.8.9.2 Out ]
C1-USER IO Map [1.8.9.2 Out ]
IO Logic [1.8.7]
I1-1
Veh Call 1
O1-1
Ch1 Red
O7-1
Ch16 Yellow
Op1
Result
O1Fcn Inv1
IO1 Opn1
O2Fnc
Inv2
IO2
Opn2
O3Fnc Inv3
IO3
Opn3
Dly
Sec
I1-2
Veh Call 2
O1-2
Ch1 Green
O7-2
Ch16 Red
I
=
----
-
I
----
-
I
----
-
I
DLY
I1-3
Veh Call 3
O1-3
Ch2 Red
O7-3
Ch16 Green
I
=
----
-
I
----
-
I
----
-
I
DLY
I1-4
Veh Call 4
O1-4
Ch2 Yellow
O7-4
Not Used
I
=
----
-
I
----
-
I
----
-
I
DLY
I1-5
Veh Call 5
O1-5
Ch2 Green
O7-5
Not Used
I
=
----
-
I
----
-
I
----
-
I
DLY
I1-6
Veh Call 6
O1-6
Ch3 Red
O7-6
Not Used
I
=
----
-
I
----
-
I
----
-
I
DLY
I1-7
Veh Call 7
O1-7
Ch3 Yellow
O7-7
Not Used
I
=
----
-
I
----
-
I
----
-
I
DLY
I1-8
Veh Call 8
O1-8
Ch3 Green
O7-8
Ch15 Red
I
=
----
-
I
----
-
I
----
-
I
DLY
I2-1
Veh Call 9
O2-1
Ch4 Red
C11S-USER IO Map [1.8.9.1 In ]
I
=
----
-
I
----
-
I
----
-
I
DLY
I2-2
Unused
O2-2
Ch4 Green
I4-1
I
=
----
-
I
----
-
I
----
-
I
DLY
I2-3
Veh Call 11
O2-3
Ch5 Red
I4-2
I
=
----
-
I
----
-
I
----
-
I
DLY
I2-4
Veh Call 12
O2-4
Ch5 Yellow
I4-3
Security Access Levels [8.2]
Com Parameters [6.1]
I2-5
Veh Call 13
O2-5
Ch5 Green
I4-4
Station ID
I2-6
Veh Call 14
O2-6
Ch6 Red
I7-1
Unused
Group ID
I2-7
Veh Call 15
O2-7
Ch6 Yellow
I7-2
Unused
Master ID
I2-8
Veh Call 16
O2-8
Ch6 Green
I7-3
Unused
Backup Time
I3-1
Veh Call 17
O3-1
Ch7 Red
I7-4
Unused
SysUp Modem [6.1]
I3-2
Veh Call 18
O3-2
Ch7 Green
I7-5
Unused
Enable Modem
I3-3
Veh Call 19
O3-3
Ch8 Red
I7-6
Unused
Idle Time
I3-4
Veh Call 20
O3-4
Ch8 Yellow
I7-7
Unused
Dial Time
I3-5
Ped Call 1
O3-5
Ch8 Green
I7-8
Unused
Tel:
I3-6
Ped Call 2
O3-6
Ch9 Red
I8-1
Unused
Alt:
I3-7
Ped Call 3
O3-7
Ch9 Yellow
I8-2
Unused
I3-8
Ped Call 4
O3-8
Ch9 Green
I8-3
Unused
2070 Port Parms [6.2]
I4-1
Unused
O4-1
Ch10 Red
I8-4
Unused
Port
Baud Rate
I4-2
Unused
O4-2
Ch10 Green
I8-5
Unused
SP1
I4-3
Unused
O4-3
Ch11 Red
I8-6
Unused
SP2
I4-4
Unused
O4-4
Ch11 Yellow
I8-7
Unused
SP3
I4-5
Door Open
O4-5
Ch11 Green
I8-8
Unused
SP4
I4-6
Unused
O4-6
Ch12 Red
C11S-USER IO Map [1.8.9.2 Out]
SP5
I4-7
33xCMUStop
O4-7
Ch12 Yellow
O8-1
Not Used
SP6
I4-8
33xFlashSns
O4-8
Ch12 Green
O8-2
Not Used
SP7
I5-1
Veh Call 25
O5-1
Ch4 Yellow
O8-3
Not Used
SP8
I5-2
Veh Call 26
O5-2
Ch10 Yellow
O8-4
Not Used
I5-3
Pre 4 In
O5-3
Ch1 Yellow
O8-5
Not Used
2070 IP 1 Addressing [6.5]
2070 IP 2 Addressing [6.5]
I5-4
Pre 3 In
O5-4
Ch7 Yellow
O8-6
Not Used
Addressing
Addressing
I5-5
Unused
O5-5
Ch15 Yellow
O8-7
Not Used
Addr
Addr
I5-6
Unused
O5-6
Ch15 Green
O8-8
Not Used
Mask
Mask
I5-7
Unused
O5-7
115 Not Used
Brdcst
Brdcst
I5-8
Unused
O5-8
114 Watchdog
GtWay
GtWay
I6-1
Unused
O6-1
115 Not Used
Port
Port
I6-2
Unused
O6-2
115 Not Used
I6-3
Unused
O6-3
Ch13 Red
2070 Port Binding Ports [6.6]
2070 Port Binding Functions [6.6]
I6-4
Unused
O6-4
Ch13 Yellow
Port
Echo
Mode
Function
Channel
Function Channel
I6-5
Unused
O6-5
Ch13 Green
ASYNC1
SP1
OFF
TS2/CVM
None
SYSUp
ASYNC2
I6-6
Unused
O6-6
Ch14 Red
ASYNC2
SP2
OFF
CMU/MMU
None
SYSDown
ASYNC1
I6-7
Unused
O6-7
Ch14 Yellow
ASYNC3
SP3
OFF
Opticom
None
Shell
None
I6-8
Unused
O6-8
Ch14 Green
ASYNC4
SP4
OFF
Loop Det.
None
SYNC1
SP5S SYNC3
OFF
GPS
-
SYNC2
OFF SYNC4
OFF
None
RT 9 RAMPS @ CROTON POINT AVE
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
SECURE
None
SWLOAD
None
None
OFF
MODE 6
MODE 6
None
None
None
MODE 6
None
None
None
None
None
None
None
None
04/07/22
FCM
MODE 6
AUTO
AUTO
AUTO
AUTO
#
Event / Alarm
Ev
Alr
Call Phases[1.1.5]
Redirect Phases[1.1.5]
Inhibit Phases[1.1.5]
Power Up Alarm.
ON
ON
Ø
Ø
Phases Called By Ø
From To From To
From
To From To
Stop Timing
ON
ON
1 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
TS1 Cabinet Door
OFF OFF
2 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
Coordination Failure
ON
ON
3 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
External Alarm # 1
ON
ON
4 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
External Alarm # 2
ON
ON
5 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
External Alarm # 3
OFF OFF
6 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
External Alarm # 4
OFF OFF
7 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
Closed Loop Disabled
ON
ON
8 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
10 External Alarm # 5
OFF OFF
9 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
11 External Alarm # 6
OFF OFF
10 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
12 Manual Control Enable
ON
ON
11 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
13 Coord Free Input
OFF OFF
12 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
14 Local Flash Input
ON
ON
13 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
15 MMU Flash
OFF OFF
14 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
16 CMU Flash
OFF OFF
15 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
17 Cycle Fault
ON
ON
16 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
18 Cycle Failure
ON
ON
Alt Call & Redirect # 1 [1.1.6.3]
Alt Inhibit Phases # 1 [1.1.6.3]
19 Coordination Fault
ON
ON
Col
Ø
Phases Called By Ø
From To From
To
From To From To
20 Controller Fault
ON
ON
1 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
21 Detector SDLC Failure
OFF OFF
2 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
22 MMU SDLC Failure
OFF OFF
3 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
23 Critical SDLC Failure
OFF OFF
4 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
24 Reserved
OFF OFF
5 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
25 EEPROM CRC Fault
ON
ON
6 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
26 Detector Diagnostic FailureOFF OFF
7 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
27 BIU Detector Failure
ON
ON
8 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
32 Queue detector alarm
ON
ON
Alt Call & Redirect # 2 [1.1.6.3]
Alt Inhibit Phases # 2 [1.1.6.3]
29 Ped Detector Fault
ON
ON
Col
Ø
Phases Called By Ø
From
To
From
To
From
To
From To
30 Coord Diagnostic Fault
OFF OFF
1 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
41 TempAlert Probe Ch. A
OFF OFF
2 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
42 TempAlert Probe Ch. B
OFF OFF
3 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
47 Coord Active
OFF OFF
4 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
48 Preempt Active
ON
ON
5 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
49 Preempt 1 Input
ON
ON
6 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
50 Preempt 2 Input
ON
ON
7 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
51 Preempt 3 Input
ON
ON
8 OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF OFF
52 Preempt 4 Input
ON
ON
Coord, CIC Plans [2.3]
Unit Parameters [1.2.1]
53 Preempt 5 Input
ON
ON
CIC
CoØ
Grow
Allow Skip Yellow
Max Cycle Time
54 Preempt 6 Input
ON
ON
OFF
TOD Dim Enable
Cycle Fault Action
55 Preempt 7 Input
ON
ON
OFF
Tone Disable
56 Preempt 8 Input
ON
ON
OFF
Diamond Mode
57 Preempt 9 Input
ON
ON
OFF
Backup Time (s)
58 Preempt 10 Input
ON
ON
Auto Flash Phase/Olap Settings [1.4.2]
Disable Init Ped
61 In Transition
ON
ON
Yel Ø
Cycle Fault Action
81 FIO Status Alarm
OFF OFF
Yel (olaps)
Enable Run Timer
###
Alarm
ON
Alarm
OFF
OFF
OFF
4Ph
RT 9 RAMPS @ CROTON POINT AVE 04/07/22
OFF
Signal #
Electric Company:
Intersection:
Zip:
CITY
VILLAGE
TOWN
OF:
CON EDISON
CROTON POINT AVE @ RT 9 RAMPS
CROTON-ON-HUDSON
W-636/W-637
W-636/W-637
D26xxxx
8780.41
55.11-9
Signal:
File:
D/HWP:
PIN:
MODEL 2070 SIGNAL OPERATION
PROGRAMMABLE FEATURES
SIGNAL OPERATION SPECIFICATION
SWITCH
PACK
FUNCTION INDICATIONS
FACE
TERMINAL
WIRE COLOR CODE
FACE
TERMINAL
WIRE COLOR CODE
14.
SP 14 R
SP 14 Y
SP 14 G
Grnd Bus
Ground Wire
PED-4
Ø2
SP 14 R
SP 14 Y
SP 14 G
Grnd Bus
SP 13 R
SP 13 Y
SP 13 G
Grnd Bus
Ground Wire
Ø3
SP 13 R
SP 13 Y
SP 13 G
Grnd Bus
12.
SP 12 R
SP 12 Y
SP 12 G
Grnd Bus
Ground Wire
PED-2
Ø6
SP 12 R
SP 12 Y
SP 12 G
Grnd Bus
11.
SP 11 R
SP 11 Y
SP 11 G
Grnd Bus
Ground Wire
SP 11 R
SP 11 Y
SP 11 G
Grnd Bus
SP 10 R
SP 10 Y
SP 10 G
Grnd Bus
Ground Wire
SP 10 R
SP 10 Y
SP 10 G
Grnd Bus
SP 9 R
SP 9 Y
SP 9 G
Grnd Bus
Ground Wire
Ø7
SP 9 R
SP 9 Y
SP 9 G
Grnd Bus
SP 8 R
SP 8 Y
SP 8 G
Grnd Bus
Ground Wire
OVL-2
Ø6+Ø8
SP 8 R
SP 8 Y
SP 8 G
Grnd Bus
7.
SP 7 R
SP 7 Y
SP 7 G
Grnd Bus
Ground Wire
SP 7 R
SP 7 Y
SP 7 G
Grnd Bus
6.
SP 6 R
SP 6 Y
SP 6 G
Grnd Bus
Ground Wire
OVL-6
Ø4+Ø6
SP 6 R
SP 6 Y
SP 6 G
Grnd Bus
5.
SP 5 R
SP 5 Y
SP 5 G
Grnd Bus
SP 5 R
SP 5 Y
SP 5 G
Grnd Bus
4.
SP 4 R
SP 4 Y
SP 4 G
Grnd Bus
SP 4 R
SP 4 Y
SP 4 G
Grnd Bus
SP 3 R
SP 3 Y
SP 3 G
Grnd Bus
Ø3
SP 3 R
SP 3 Y
SP 3 G
Grnd Bus
SP 2 R
SP 2 Y
SP 2 G
Grnd Bus
OVL-12
Ø2+Ø8
SP 2 R
SP 2 Y
SP 2 G
Grnd Bus
SP 1 R
SP 1 Y
SP 1 G
Grnd Bus
- - - - -
OVL-3
Ø1
SP 1 R
SP 1 Y
SP 1 G
Grnd Bus
Ground Wire
Ground Wire
Ground Wire
TABLE OF SWITCH PACKS
PED-1
Ø2
OVL-1
Ø1+Ø2+Ø4
PED-3
Ø7
Ground Wire
Date:
Ground Wire
SP 16 R
SP 16 Y
SP 16 G
Grnd Bus
Ground Wire
SP 16 R
SP 16 Y
SP 16 G
Grnd Bus
SP 15 R
SP 15 Y
SP 15 G
Grnd Bus
Ground Wire
SP 15 R
SP 15 Y
SP 15 G
Grnd Bus
4/12/2022
Ground Wire
- - - - -
Ground Wire
Red
Yellow
Green
Ground Wire
Red
Yellow
Green
Ground Wire
Red
Yellow
Green
Ground Wire
Red
Yellow
Green
Ground Wire
Red
Yellow
Green
Ground Wire
Red
Yellow
Green
Ground Wire
Red
Yellow
Green
14 / 10C - C - O
- G
- W
14 / 05C - F - R
- O
- G
- W
14 / 10C - C - R
- O
- G
- W
14 / 05C - E - R
- O
- G
- W
14 / 05C - N - R
- O
- G
- W
14 / 05C - M - R
- O
- G
- W
14 / 05C - G - R
- O
- G
- W
14 / 05C - H - R
- O
- G
- W
14 / 05C - B - R
- O
- G
- W
14 / 05C - A - R
- O
- G
- W
14 / 05C - L - R
- O
- G
- W
14 / 05C - K - R
- O
- G
- W
14 / 05C - J - R
- O
- G
- W
14 / 05C - I - R
- O
- G
- W
14 / 05C - D - R
- O
- G
- W
Ground Wire
HAND
- - - - - - -
MAN
Ground Wire
HAND
- - - - - - -
MAN
Ground Wire
HAND
- - - - - - -
MAN
Ground Wire
HAND
- - - - - - -
MAN
14 / 05C - 1P - R
- - - - -
- G
- W
14 / 05C - 2P - R
- - - - -
- G
- W
14 / 05C - 3P - R
- - - - -
- G
- W
14 / 05C - 4P - R
- - - - -
- G
- W
Signal #
Electric Company:
Intersection:
Zip:
CITY
VILLAGE
TOWN
OF:
CON EDISON
CROTON POINT AVE @ RT 9 RAMPS
CROTON-ON-HUDSON
W-636/W-637
W-636/W-637
D26xxxx
8780.41
55.11-9
Signal:
File:
D/HWP:
PIN:
MODEL 2070 SIGNAL OPERATION
PROGRAMMABLE FEATURES
SIGNAL OPERATION SPECIFICATION
TRAFFIC SIGNAL MONITOR PROGRAMMING
Notes:
4/12/2022
CONFLICT MONITOR DIODES TO BE CUT
(SWITCH PACKS TO RUN TOGETHER)
YELLOW DISABLE:
WIRE JUMPERS
TO BE INSTALLED FOR
PEDS
210NYR MONITOR BOARD
(SWITCH PACKS TO MONITOR)
CURRENT MONITOR DIODES
TO BE CUT
(SWITCH PACKS TO NOT MONITOR)
1, 4-5, 10-12, 14-16
CURRENT MONITOR BOARD
(IF USED)
Date:
DEFAULT
SETTINGS
DO NOT
CHANGE
DIP SWITCHES:
X = ON
BLANK = OFF
RED FAIL ENABLE
SWITCH PACKS TO MONITOR
(3-COLOR BALLS & 3-COLOR ARROWS ONLY)
(NO PEDS OR SOLO SUPPLEMENTAL HEADS)
1 – 6
1 - 8
1 - 9
2 – 6
2 - 8
2 - 9
2 - 11
2 – 12
2 – 14
3 – 7
3 - 10
3 – 13
6 - 8
6 - 9
6 - 11
6 - 12
6 – 14
7 – 10
7 – 13
8 - 9
8 - 11
8 – 12
8 - 14
X
X
X
X
9 – 11
9 – 12
9 – 14
10 - 13
11 – 12
11 – 14
12 – 14
Signal #
Electric Company:
Intersection:
Zip:
CITY
VILLAGE
TOWN
OF:
CON EDISON
CROTON POINT AVE @ RT 9 RAMPS
CROTON-ON-HUDSON
W-636/W-637
W-636/W-637
D26xxxx
8780.41
55.11-9
Signal:
File:
D/HWP:
PIN:
MODEL 2070 SIGNAL OPERATION
PROGRAMMABLE FEATURES
SIGNAL OPERATION SPECIFICATION
TABLE OF INPUT WIRING
Date:
4/12/2022
TERM.
NUMBER
FUNCTION
DET.
NO.
DET. TYPE
DET. AN
OVER
REMARKS
1A, 1B
Ø 1
2A, 2B
Ø 2
3A, 3B
4A, 4B
Ø 7
5A, 5B
Ø 2
6A, 6B
Ø 6
7A, 7B
Ø 7
QUADRAPOLE
PRESENCE LOOP
8A, 8B
Ø 6
QUADRAPOLE
PRESENCE LOOP
9A, 9B
Ø 3
9AB
MICROWAVE
MICROWAVE
10A, 10B
11A, 11B
12A, 12B
13A, 13B
14A, 14B
NORMAL
PRESENCE LOOP
15A, 15B
NORMAL
PRESENCE LOOP
16A, 16B
NORMAL
PRESENCE LOOP
17A, 17B
NORMAL
PRESENCE LOOP
18A, 18B
Ø 6
NORMAL
PRESENCE LOOP
19A, 19B
Ø 6
QUADRAPOLE
PRESENCE LOOP
20A, 20B
Ø 6
NORMAL
PRESENCE LOOP
21A, 21B
22A, 22B
23A, 23B
24A, 24B
25A, 25B
PRESENCE LOOP
26A, 26B
Ø 2
NORMAL
PRESENCE LOOP
27A, 27B
28A, 28B
Ø 3
QUADRAPOLE
PRESENCE LOOP
PRESENCE LOOP
PRESENCE LOOP
QUADRAPOLE
QUADRAPOLE
QUADRAPOLE
PRESENCE LOOP
NORMAL
PRESENCE LOOP
Ø 2
Ø 7
Ø 3
QUADRAPOLE
NORMAL
NORMAL
Ø 1
Ø 2
Ø 3
Ø 7
Ø 2
Ø 6
Ø 7
QUADRAPOLE
PRESENCE LOOP
PRESENCE LOOP
QUADRAPOLE
NORMAL
NORMAL
PRESENCE LOOP
PRESENCE LOOP
QUEUE LOOP
QUEUE LOOP
PED 1 - Ø 2
BUTTON
PEDESTRIAN
PED 2 - Ø 6
BUTTON
PEDESTRIAN
PED 3 - Ø 7
BUTTON
PEDESTRIAN
PED 4 - Ø 2
BUTTON
PEDESTRIAN
Turning Movement Count (TMC) Data
Turning Movement Counts
GENERAL INFORMATION
PROJECT NAME:
PROJECT NO:
DATE:
ANALYST:
INTERSECTION INFORMATION
NOTES:
SURVEY DATE:
1.)
INTERSECTION:
STREET (E-W):
2.)
STREET (N-S):
3.)
SURVEY PERIOD:
AM PEAK PERIOD
TO
MIDDAY PEAK PERIOD
TO
PM PEAK PERIOD
TO
TRAFFIC VOLUMES
Time Period
Eastbound
Westbound
Northbound
Southbound
Begin
End
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
AM PEAK PERIOD
7:00 AM
-
7:15 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
8:15 AM
-
8:30 AM
8:30 AM
-
8:45 AM
8:45 AM
-
9:00 AM
9:00 AM
-
9:15 AM
9:15 AM
-
9:30 AM
9:30 AM
-
9:45 AM
9:45 AM
-
10:00 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
N/A
0.76
0.63
0.81
0.86
0.82
0.56
0.91
0.50
N/A
0.82
0.78
0.63
N/A
N/A
0.63
PM PEAK PERIOD
4:00 PM
-
4:15 PM
4:15 PM
-
4:30 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
5:30 PM
-
5:45 PM
5:45 PM
-
6:00 PM
6:00 PM
-
6:15 PM
6:15 PM
-
6:30 PM
6:30 PM
-
6:45 PM
6:45 PM
-
7:00 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
N/A
0.77
0.88
0.77
0.87
0.89
0.63
0.92
0.50
N/A
0.83
0.82
0.31
N/A
N/A
0.31
Generalized AM Peak Hour Only
Generalized PM Peak Hour Only
HSRG Overlay and LI District Zoning Amendments
July 5, 2022
Haley Hutson
10:00 AM
Croton PT Avenue
Parking Lot/ Veterans Plaza
7:00 AM
15 minute values should be input by the user.
Time values should be entered in military time.
4:00 PM
April 20, 2022
If there is no volume for a movement or time
period, a zero should be entered in the appropriate
cell(s).
7:00 PM
AKRF, Inc.
Turning Movement Counts
GENERAL INFORMATION
PROJECT NAME:
PROJECT NO:
DATE:
ANALYST:
INTERSECTION INFORMATION
NOTES:
SURVEY DATE:
1.)
INTERSECTION:
STREET (E-W):
2.)
STREET (N-S):
3.)
SURVEY PERIOD:
AM PEAK PERIOD
TO
MIDDAY PEAK PERIOD
TO
PM PEAK PERIOD
TO
TRAFFIC VOLUMES
Time Period
Eastbound
Westbound
Northbound
Southbound
Begin
End
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
AM PEAK PERIOD
7:00 AM
-
7:15 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
8:15 AM
-
8:30 AM
8:30 AM
-
8:45 AM
8:45 AM
-
9:00 AM
9:00 AM
-
9:15 AM
9:15 AM
-
9:30 AM
9:30 AM
-
9:45 AM
9:45 AM
-
10:00 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
N/A
0.73
0.89
0.82
0.85
0.81
N/A
0.89
N/A
N/A
N/A
N/A
0.90
N/A
0.80
0.85
PM PEAK PERIOD
4:00 PM
-
4:15 PM
4:15 PM
-
4:30 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
5:30 PM
-
5:45 PM
5:45 PM
-
6:00 PM
6:00 PM
-
6:15 PM
6:15 PM
-
6:30 PM
6:30 PM
-
6:45 PM
6:45 PM
-
7:00 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
N/A
0.84
0.88
0.88
0.87
0.88
N/A
0.87
N/A
N/A
N/A
N/A
0.84
N/A
0.79
0.90
HSRG Overlay and LI District Zoning Amendments
July 5, 2022
Haley Hutson
April 20, 2022
Generalized AM Peak Hour Only
Generalized PM Peak Hour Only
15 minute values should be input by the user.
Time values should be entered in military time.
4:00 PM
7:00 PM
If there is no volume for a movement or time
period, a zero should be entered in the appropriate
cell(s).
Croton Pt Ave
9/9A SB Ramp
7:00 AM
10:00 AM
12:00 AM
12:00 AM
AKRF, Inc.
Turning Movement Counts
GENERAL INFORMATION
PROJECT NAME:
PROJECT NO:
DATE:
ANALYST:
INTERSECTION INFORMATION
NOTES:
SURVEY DATE:
1.)
INTERSECTION:
STREET (E-W):
2.)
STREET (N-S):
3.)
SURVEY PERIOD:
AM PEAK PERIOD
TO
MIDDAY PEAK PERIOD
TO
PM PEAK PERIOD
TO
TRAFFIC VOLUMES
Time Period
Eastbound
Westbound
Northbound
Southbound
Begin
End
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
AM PEAK PERIOD
7:00 AM
-
7:15 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
8:15 AM
-
8:30 AM
8:30 AM
-
8:45 AM
8:45 AM
-
9:00 AM
9:00 AM
-
9:15 AM
9:15 AM
-
9:30 AM
9:30 AM
-
9:45 AM
9:45 AM
-
10:00 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
N/A
0.84
0.88
0.89
0.80
0.89
N/A
0.90
0.88
N/A
0.89
0.95
N/A
N/A
N/A
N/A
PM PEAK PERIOD
4:00 PM
-
4:15 PM
4:15 PM
-
4:30 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
5:30 PM
-
5:45 PM
5:45 PM
-
6:00 PM
6:00 PM
-
6:15 PM
6:15 PM
-
6:30 PM
6:30 PM
-
6:45 PM
6:45 PM
-
7:00 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
N/A
0.83
0.93
0.90
0.78
0.94
N/A
0.93
0.85
N/A
0.94
0.94
N/A
N/A
N/A
N/A
HSRG Overlay and LI District Zoning Amendments
July 5, 2022
Haley Hutson
April 20, 2022
Generalized AM Peak Hour Only
Generalized PM Peak Hour Only
15 minute values should be input by the user.
4:00 PM
7:00 PM
Croton Pt Ave
9A NB Ramp
If there is no volume for a movement or time
period, a zero should be entered in the appropriate
cell(s).
7:00 AM
10:00 AM
12:00 AM
12:00 AM
Time values should be entered in military time.
AKRF, Inc.
Turning Movement Counts
GENERAL INFORMATION
PROJECT NAME:
PROJECT NO:
DATE:
ANALYST:
INTERSECTION INFORMATION
NOTES:
SURVEY DATE:
1.)
INTERSECTION:
STREET (E-W):
2.)
STREET (N-S):
3.)
SURVEY PERIOD:
AM PEAK PERIOD
TO
MIDDAY PEAK PERIOD
TO
PM PEAK PERIOD
TO
TRAFFIC VOLUMES
Time Period
Eastbound
Westbound
Northbound
Southbound
Begin
End
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
AM PEAK PERIOD
7:00 AM
-
7:15 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
8:15 AM
-
8:30 AM
8:30 AM
-
8:45 AM
8:45 AM
-
9:00 AM
9:00 AM
-
9:15 AM
9:15 AM
-
9:30 AM
9:30 AM
-
9:45 AM
9:45 AM
-
10:00 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
0.81
N/A
0.87
0.88
N/A
N/A
N/A
N/A
0.86
0.93
N/A
0.97
N/A
0.92
0.89
0.90
PM PEAK PERIOD
4:00 PM
-
4:15 PM
4:15 PM
-
4:30 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
5:30 PM
-
5:45 PM
5:45 PM
-
6:00 PM
6:00 PM
-
6:15 PM
6:15 PM
-
6:30 PM
6:30 PM
-
6:45 PM
6:45 PM
-
7:00 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
0.96
N/A
0.86
0.91
N/A
N/A
N/A
N/A
0.89
0.89
N/A
0.90
N/A
0.86
0.94
0.93
HSRG Overlay and LI District Zoning Amendments
July 5, 2022
Haley Hutson
April 20, 2022
Generalized AM Peak Hour Only
Generalized PM Peak Hour Only
15 minute values should be input by the user.
4:00 PM
7:00 PM
Croton Pt Ave
S Riverside Ave
If there is no volume for a movement or time
period, a zero should be entered in the appropriate
cell(s).
7:00 AM
10:00 AM
12:00 AM
12:00 AM
Time values should be entered in military time.
AKRF, Inc.
Turning Movement Counts
GENERAL INFORMATION
PROJECT NAME:
PROJECT NO:
DATE:
ANALYST:
INTERSECTION INFORMATION
NOTES:
SURVEY DATE:
1.)
INTERSECTION:
STREET (E-W):
2.)
STREET (N-S):
3.)
SURVEY PERIOD:
AM PEAK PERIOD
TO
MIDDAY PEAK PERIOD
TO
PM PEAK PERIOD
TO
TRAFFIC VOLUMES
Time Period
Eastbound
Westbound
Northbound
Southbound
Begin
End
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
AM PEAK PERIOD
7:00 AM
-
7:15 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
8:15 AM
-
8:30 AM
8:30 AM
-
8:45 AM
8:45 AM
-
9:00 AM
9:00 AM
-
9:15 AM
9:15 AM
-
9:30 AM
9:30 AM
-
9:45 AM
9:45 AM
-
10:00 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
0.58
N/A
0.50
0.69
N/A
N/A
N/A
N/A
0.63
0.86
N/A
0.87
N/A
0.86
0.63
0.86
PM PEAK PERIOD
4:00 PM
-
4:15 PM
4:15 PM
-
4:30 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
5:30 PM
-
5:45 PM
5:45 PM
-
6:00 PM
6:00 PM
-
6:15 PM
6:15 PM
-
6:30 PM
6:30 PM
-
6:45 PM
6:45 PM
-
7:00 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
0.58
N/A
0.75
0.63
N/A
N/A
N/A
N/A
0.58
0.96
N/A
0.95
N/A
0.94
0.75
0.94
HSRG Overlay and LI District Zoning Amendments
July 5, 2022
Haley Hutson
April 20, 2022
Generalized AM Peak Hour Only
Generalized PM Peak Hour Only
15 minute values should be input by the user.
4:00 PM
7:00 PM
Clinton Street
S Riverside Ave
If there is no volume for a movement or time
period, a zero should be entered in the appropriate
cell(s).
7:00 AM
10:00 AM
12:00 AM
12:00 AM
Time values should be entered in military time.
AKRF, Inc.
Turning Movement Counts
GENERAL INFORMATION
PROJECT NAME:
PROJECT NO:
DATE:
ANALYST:
INTERSECTION INFORMATION
NOTES:
SURVEY DATE:
1.)
INTERSECTION:
STREET (E-W):
2.)
STREET (N-S):
3.)
SURVEY PERIOD:
AM PEAK PERIOD
TO
MIDDAY PEAK PERIOD
TO
PM PEAK PERIOD
TO
TRAFFIC VOLUMES
Time Period
Eastbound
Westbound
Northbound
Southbound
Begin
End
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
Left
Thru
Right
Total
AM PEAK PERIOD
7:00 AM
-
7:15 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
8:15 AM
-
8:30 AM
8:30 AM
-
8:45 AM
8:45 AM
-
9:00 AM
9:00 AM
-
9:15 AM
9:15 AM
-
9:30 AM
9:30 AM
-
9:45 AM
9:45 AM
-
10:00 AM
7:15 AM
-
7:30 AM
7:30 AM
-
7:45 AM
7:45 AM
-
8:00 AM
8:00 AM
-
8:15 AM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
0.90
0.95
0.80
0.95
0.63
0.80
0.83
0.82
0.75
0.78
0.82
0.83
0.81
0.88
0.93
0.86
PM PEAK PERIOD
4:00 PM
-
4:15 PM
4:15 PM
-
4:30 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
5:30 PM
-
5:45 PM
5:45 PM
-
6:00 PM
6:00 PM
-
6:15 PM
6:15 PM
-
6:30 PM
6:30 PM
-
6:45 PM
6:45 PM
-
7:00 PM
4:30 PM
-
4:45 PM
4:45 PM
-
5:00 PM
5:00 PM
-
5:15 PM
5:15 PM
-
5:30 PM
Peak Hour Total
Peak 15 Minute Vol
Calculated PHF
0.75
0.83
0.70
0.80
0.75
0.71
0.89
0.77
0.79
0.90
0.86
0.94
0.78
0.92
0.47
0.94
HSRG Overlay and LI District Zoning Amendments
July 5, 2022
Haley Hutson
April 20, 2022
Generalized AM Peak Hour Only
Generalized PM Peak Hour Only
15 minute values should be input by the user.
4:00 PM
7:00 PM
Benedict Blvd
S Riverside Ave
If there is no volume for a movement or time
period, a zero should be entered in the appropriate
cell(s).
7:00 AM
10:00 AM
12:00 AM
12:00 AM
Time values should be entered in military time.
AKRF, Inc.
Trip Generation Backup
Trip Assignment Zone Maps
Zone Trip Generation Tables
Zone Trip Assignment Detail Tables
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zones (Parcel Groups) for
Trip Assignments - HSRG
Zone Groups
Note:
Zone
Parcel(s) Map ID
Parcels with assumed multiple
1-8, 37-42
access points may be included in
33-36, 38, 43-46
multiple zones.
9-12, 31-34
30-32, 43, 44
13, 14
15-20, 25-29
21, 47
24-27
Zone 1
Zone 2
Zones (Parcel Groups) for
Trip Assignments - LI TOD
Zone Groups
Zone
Parcel(s) Map ID
48, 50
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily
Housing (3 story
max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
0 Units
LI TOD
Multifamily
Housing (5 story
max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
74 Units
74 Units
-1
-1
-2
-2
-1
-3
-2
-1
-3
-2
-2
-2
-1
-3
-1
-2
-3
74 Units
6.304 kSF (8)
-1
-1
-1
-1
-1
-1
-1
-1
6.675 kSF (8)
-1
-1
-2
-2
-2
-4
-2
-2
-4
-1
-1
-2
-2
-4
-2
-2
-4
Pass-by Trips (9)
-2
-1
-6
-6
-12
-5
-5
-9
5.562 kSF (6)
-3
-1
-4
-4
-2
-6
-3
-1
-4
-3
-2
-5
Pass-by Trips (10)
-1
-10
-5
-15
-16
-11
-27
18.541 kSF
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(3) ITE rate of 1.67 trips/1,000 SF (82% entering, 18% exiting) was used for the Weekday AM Peak Hour
ITE rate of 2.16 trips/1,000 SF (34% entering, 66% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.53 trips/1,000 SF (54% entering, 46% exiting) was used for the Saturday Midday Peak Hour. ITE Rates unavailable for the "Small Office Building" land use for the
Saturday Midday Peak Hour, therefore, "General Office Building" land use rates were utilized instead.
(4) ITE rate of 2.36 trips/1,000 SF (60% entering, 40% exiting) was used for the Weekday AM Peak Hour
ITE rate of 6.59 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday PM Peak Hour
ITE rate of 6.57 trips/1,000 SF (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour
(5) ITE rate of 0.73 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday AM Peak Hour
ITE rate of 7.80 trips/1,000 SF (67% entering, 33% exiting) was used for the Weekday PM Peak Hour
ITE rate of 10.68 trips/1,000 SF (59% entering, 41% exiting) was used for the Saturday Midday Peak Hour
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
(8) The commercial square footage was assumed to be 34% office, 36% retail, and 30% restaurant.
(9) Pass-by trip percentage of 34% utilized for the Weekday PM peak hour and 26% utilized for the Saturday Midday peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 820 "Shopping Center". ITE Pass-by trip percentage unavailable for Land Use 820 for the
Weekday AM peak hour and was developed from the ratio of Weekday AM to Weekday PM peak hour trips yielding a pass-by trip percentage of 20%.
(10) Pass-by trip percentage of 44% utilized for the Weekday PM peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 931 "Quality Restaurant". ITE Pass-by trip percentages unavailable for Land Use 931 for the
Weekday AM and Saturday Midday peak hours and were developed from the ratio of Weekday AM and Saturday Midday to Weekday PM peak hour trips yielding pass-by trip percentages of
24% and 57% for the Weekday AM and Saturday Midday peak hours, respectively.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - LI TOD ZONE 1
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
Strip Retail Plaza (<40k)(4)
Internal Trips (6)
Mass Transit Credit (7)
Total Retail
Restaurant
Fine Dining Restaurant(5)
Internal Trips (6)
Mass Transit Credit (7)
Total Restaurant
Retail
Total Commercial
TOTAL TRIP GENERATION
Commercial
LI TOD
Office
712 / 710
Small Office Building (AM, PM) /
General Office Building (Sat.)(3)
Internal Trips (6)
Mass Transit Credit (7)
Total Office
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily
Housing (3 story
max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
0 Units
LI TOD
Multifamily
Housing (5 story
max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
13 Units
13 Units
-1
-1
-1
-1
-1
-1
-1
-1
13 Units
1.119 kSF (8)
1.185 kSF (8)
-1
-1
-1
-1
-1
-1
-1
-1
Pass-by Trips (9)
-1
-1
-2
-1
-1
-2
0.987 kSF (6)
-1
-1
-1
-1
-1
-1
-1
-1
Pass-by Trips (10)
-2
-1
-3
-2
-3
-5
3.291 kSF
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.32(X) + 5.84 (26% entering, 74% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(3) ITE rate of 1.67 trips/1,000 SF (82% entering, 18% exiting) was used for the Weekday AM Peak Hour
ITE rate of 2.16 trips/1,000 SF (34% entering, 66% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.53 trips/1,000 SF (54% entering, 46% exiting) was used for the Saturday Midday Peak Hour. ITE Rates unavailable for the "Small Office Building" land use for the
Saturday Midday Peak Hour, therefore, "General Office Building" land use rates were utilized instead.
(4) ITE rate of 2.36 trips/1,000 SF (60% entering, 40% exiting) was used for the Weekday AM Peak Hour
ITE rate of 6.59 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday PM Peak Hour
ITE rate of 6.57 trips/1,000 SF (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour
(5) ITE rate of 0.73 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday AM Peak Hour
ITE rate of 7.80 trips/1,000 SF (67% entering, 33% exiting) was used for the Weekday PM Peak Hour
ITE rate of 10.68 trips/1,000 SF (59% entering, 41% exiting) was used for the Saturday Midday Peak Hour
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
(8) The commercial square footage was assumed to be 34% office, 36% retail, and 30% restaurant.
(9) Pass-by trip percentage of 34% utilized for the Weekday PM peak hour and 26% utilized for the Saturday Midday peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 820 "Shopping Center". ITE Pass-by trip percentage unavailable for Land Use 820 for the
Weekday AM peak hour and was developed from the ratio of Weekday AM to Weekday PM peak hour trips yielding a pass-by trip percentage of 20%.
(10) Pass-by trip percentage of 44% utilized for the Weekday PM peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 931 "Quality Restaurant". ITE Pass-by trip percentages unavailable for Land Use 931 for the
Weekday AM and Saturday Midday peak hours and were developed from the ratio of Weekday AM and Saturday Midday to Weekday PM peak hour trips yielding pass-by trip percentages of
24% and 57% for the Weekday AM and Saturday Midday peak hours, respectively.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - LI TOD ZONE 2
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
Strip Retail Plaza (<40k)(4)
Internal Trips (6)
Mass Transit Credit (7)
Total Retail
Restaurant
Fine Dining Restaurant(5)
Internal Trips (6)
Mass Transit Credit (7)
Total Restaurant
Retail
Total Commercial
TOTAL TRIP GENERATION
Commercial
LI TOD
Office
712 / 710
Small Office Building (AM, PM) /
General Office Building (Sat.)(3)
Internal Trips (6)
Mass Transit Credit (7)
Total Office
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
80 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
80 Units
-1
-4
-5
-4
-2
-6
-2
-1
-3
-1
-3
-4
-3
-2
-5
-2
-1
-3
80 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 1
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
42 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
42 Units
-1
-3
-4
-3
-1
-4
-1
-1
-2
-1
-2
-3
-2
-2
-4
-1
-1
-2
42 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 2
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
47 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
47 Units
-1
-3
-4
-3
-1
-4
-1
-1
-2
-1
-2
-3
-2
-2
-4
-1
-1
-2
47 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 3
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
17 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
17 Units
-1
-2
-3
-2
-1
-3
-1
-1
-1
-2
-3
-2
-1
-3
-1
-1
17 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 4
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
17 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
17 Units
-1
-2
-3
-2
-1
-3
-1
-1
-1
-2
-3
-2
-1
-3
-1
-1
17 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 5
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
66 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
66 Units
-1
-3
-4
-3
-2
-5
-1
-2
-3
-1
-3
-4
-3
-1
-4
-1
-1
-2
66 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 6
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
70 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
70 Units
-1
-4
-5
-3
-2
-5
-2
-1
-3
-1
-3
-4
-3
-2
-5
-1
-2
-3
70 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 7
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
26 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
26 Units
-1
-2
-3
-2
-1
-3
-1
-1
-1
-2
-3
-2
-1
-3
-1
-1
26 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 8
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
9 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
9 Units
-1
-2
-3
-2
-2
-1
-1
-2
-1
-1
-2
9 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 9
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
10 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
0 Units
10 Units
-1
-2
-3
-2
-1
-3
-1
-1
-2
-1
-1
-2
10 Units
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
*Source: ITE Trip Generation Manual, 11th Edition
Trip Generation*
HSRG Overlay and LI District Zoning Amendments - HSRG ZONE 10
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
TOTAL TRIP GENERATION
HSRG Build Projects - Trip Generation Assignments
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
AM
PM
INTERSECTIONS
AM
PM
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
IN
OUT
1. Croton Point Avenue & Veterans Plaza
EB L
T
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
R
WB L
15%
15%
15%
15%
15%
15%
15%
15%
15%
15%
T
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
R
NB L
T
R
15%
15%
15%
15%
15%
15%
15%
15%
15%
15%
SB L
T
R
2. Croton Point Avenue & Route 9/9A SB Ramps
EB T
20%
20%
20%
20%
20%
20%
20%
20%
20%
20%
R
WB L
35%
35%
35%
35%
35%
35%
35%
35%
35%
35%
T
20%
20%
20%
20%
20%
20%
20%
20%
20%
20%
SB L
15%
15%
15%
15%
15%
15%
15%
15%
15%
15%
T
R
3. Croton Point Av & Route 9/9A NB Ramps/Restaurant Drvwy.
EB L
35%
T
35%
35%
35%
35%
35%
35%
35%
35%
30%
R
15%
WB L
15%
15%
15%
15%
15%
15%
15%
15%
T
55%
55%
55%
55%
55%
55%
55%
55%
30%
R
30%
NB L
35%
T
35%
R
35%
35%
35%
35%
35%
35%
35%
35%
SB L
30%
T
15%
R
55%
4. South Riverside Avenue/Croton Point Avenue
EB L
70%
70%
70%
70%
70%
70%
25%
25%
25%
R
70%
5%
5%
5%
NB L
70%
5%
5%
5%
T
5%
5%
5%
5%
5%
5%
25%
SB T
5%
5%
5%
5%
5%
5%
25%
R
70%
70%
70%
70%
70%
70%
25%
25%
25%
5. South Riverside Avenue/Benedict Blvd.
EB L
T
R
WB L
75%
10%
10%
10%
10%
10%
T
10%
R
10%
10%
10%
15%
NB L
75%
T
75%
75%
75%
15%
15%
15%
15%
15%
R
75%
10%
10%
10%
10%
10%
SB L
10%
10%
10%
15%
T
75%
75%
75%
15%
15%
15%
15%
15%
R
15%
Zone 8
Zone 9
Zone 1
RESIDENTIAL PROJECT TRAFFIC
Zone 2
Zone 3
Zone 10
Zone 4
Zone 5
Zone 6
Zone 10
Zone 4
Zone 5
Zone 6
Zone 7
Zone 7
Zone 8
Zone 9
HSRG Overlay and LI District Zoning Amendments
Zone 1
Zone 2
Zone 3
HSRG BUILD INCREMENT
LI TOD Resid. Build Projects
Trip Generation Assignments
IN
OUT
IN
OUT
AM
PM
INTERSECTIONS
AM
PM
IN
OUT
IN
OUT
1. Croton Point Avenue & Veterans Plaza
EB L
5%
T
R
5%
WB L
80%
T
R
80%
NB L
5%
T
15%
R
80%
SB L
80%
T
15%
R
5%
2. Croton Point Avenue & Route 9/9A SB Ramps
EB T
45%
45%
R
35%
35%
WB L
T
65%
65%
SB L
T
R
15%
15%
3. Croton Point Av & Route 9/9A NB Ramps/Restaurant Drvwy.
EB L
T
30%
30%
R
15%
15%
WB L
T
30%
30%
R
NB L
35%
35%
T
R
SB L
T
R
4. South Riverside Avenue/Croton Point Avenue
EB L
25%
25%
R
5%
5%
NB L
5%
5%
T
SB T
R
25%
25%
5. South Riverside Avenue/Benedict Blvd.
EB L
T
R
WB L
10%
10%
T
R
NB L
T
15%
15%
R
10%
10%
SB L
T
15%
15%
R
HSRG Overlay and LI District Zoning Amendments
Zone 1
Zone 2
LI TOD BUILD INCREMENT
RESIDENTIAL PROJECT TRAFFIC
Zone 1
Zone 2
LI TOD Comm. Build Projects
Trip Generation Assignments
IN
OUT
IN
OUT
AM
PM
INTERSECTIONS
AM
PM
IN
OUT
IN
OUT
1. Croton Point Avenue & Veterans Plaza
EB L
5%
T
R
5%
WB L
80%
T
R
80%
NB L
5%
T
15%
R
80%
SB L
80%
T
15%
R
5%
2. Croton Point Avenue & Route 9/9A SB Ramps
EB T
45%
45%
R
35%
35%
WB L
T
65%
65%
SB L
T
R
15%
15%
3. Croton Point Av & Route 9/9A NB Ramps/Restaurant Drvwy.
EB L
T
30%
30%
R
15%
15%
WB L
T
30%
30%
R
NB L
35%
35%
T
R
SB L
T
R
4. South Riverside Avenue/Croton Point Avenue
EB L
25%
25%
R
5%
5%
NB L
5%
5%
T
SB T
R
25%
25%
5. South Riverside Avenue/Benedict Blvd.
EB L
T
R
WB L
10%
10%
T
R
NB L
T
15%
15%
R
10%
10%
SB L
T
15%
15%
R
HSRG Overlay and LI District Zoning Amendments
Zone 1
Zone 2
LI TOD BUILD INCREMENT
COMMERCIAL PROJECT TRAFFIC
Zone 1
Zone 2
Previous AKRF Memorandums
Trip Generation Memorandum (2/25/2022)
Traffic Screening Memorandum (5/27/2022)
Environmental, Planning, and Engineering Consultants
34 South Broadway
Suite 300
White Plains, NY 10601
tel: 914 949-7336
fax: 914 949-7559
www.akrf.com
Offices in New York ● New Jersey ● Pennsylvania ● Maryland ● Connecticut
Memorandum
To:
From:
AKRF, Inc.
Date:
February 25, 2022
Re:
Trip Generation Summary – Proposed HSRG Overlay and LI District Zoning
Amendments
AKRF has completed trip generation calculations for the theoretical maximum buildout projected
under the proposed HSRG Overlay and LI District zoning amendments. The calculations are based
on trip generation rates and data provided in the Institute of Transportation Engineers (ITE) Trip
Generation Manual, 11th Edition (the most recent edition available at this time). The results of the
trip generation calculations are presented in Table 1.
To generate a theoretical maximum buildout scenario for the HSRG Overlay area, it was assumed
that all parcels within the existing HSRG Overlay district and proposed expansion area would be
redeveloped with multifamily residential buildings with a floor area ratio (FAR) of 0.8, a
maximum height of three stories/35 feet, and compliance with on-site (off-street) parking
requirements as per the proposed zoning amendments. The theoretical maximum buildout scenario
for the HSRG Overlay resulted in a total of 383 residential units and 583 off-street parking spaces.
To generate a theoretical maximum buildout scenario for the LI district parcels, the calculations
assumed that each of the three parcels (48, 49, and 50) would be redeveloped with a 1.2 FAR
mixed-use building containing ground floor commercial space with residential space above, at a
maximum height of five stories, while also meeting the on-site parking requirements as per the
proposed zoning amendments. The theoretical maximum buildout scenario for the LI district
parcels resulted in a total of 87 residential units, 21,831 square feet of ground floor commercial
space, and 142 off-street parking spaces (55 spaces for commercial uses and 87 spaces for
residential uses).
Off-street parking requirements for any new multifamily residential uses in the HSRG Overlay
area are expected to be the same as what is currently permitted for mixed-use buildings through
Section 230-20.3(d) of the Village Zoning Code (one parking space per unit, plus one additional
parking space for each bedroom in the unit in excess of one bedroom). However, because the
buildout calculations did not account for bedrooms and assumed each residential unit would be
Village of Croton-on-Hudson
February 25, 2022
1,000 square feet in area, a ratio of 1.5 parking spaces per projected unit was applied for the HSRG
Overlay, which is considered conservative. Due to the Village’s desire to introduce a Transit-
Oriented Development (TOD) concept to the LI district parcels included in the study, which are
within close proximity to public transit and municipal parking lots, off-street parking requirements
for mixed-use development on the three LI district parcels was assumed to be 1 parking space per
residential unit and 1 parking space per 400 square feet of commercial floor area. For context, the
Village's C-2 (General Commercial) district currently permits the greater of 1 space per 300 square
feet of office floor area or 1 space per 250 square feet of retail/service area.
For both the HSRG Overlay and LI district parcels included in the study, projected uses were
assumed to be accommodated within one building per parcel, with the projected amount of
required parking accommodated on each parcel as well. The area calculation for the required
number of parking spaces assumed that one space requires 325 sf. This was calculated by adding
the area of a typical parking space (10 ft. x 20 ft. = 200 sf) to the area equal to half the circulation
aisle (10 ft. x 12.5 ft = 125 sf).
The complete lists of assumptions utilized to complete the buildout and parking calculations,
which have been vetted through the Village, will be included in the FEAF Part 3 Supplemental
Narrative being prepared by AKRF.
Trip generation calculations were performed for the Weekday AM, Weekday PM, and Saturday
Midday peak hours. Credits were taken account for internal trips between the land uses (i.e.,
pedestrian trips between land uses that would not generate additional vehicle trips) within the
Project Area, and for mass transit usage. In addition, pass-by trip1 credits were taken for the retail
and restaurant land uses. As shown in Table 1, the total trip generation numbers would be 165,
241, and 216 trips for the Weekday AM, Weekday PM, and Saturday Midday peak hours.
Since the number of trips for each peak hour examined exceeds 100 trips, it is anticipated that a
quantified analysis at key intersections will be required. The quantified analysis would assist the
Village in assessing the potential for traffic impacts, in the unlikely event that the entirety of the
Project Area is fully redeveloped under the parameters of the proposed zoning amendments, as
assumed through the conservative buildout calculations. Selection of any intersections to be
included in the analysis would be determined based on consultation with the Village.
Figure 1 shows the nine intersections proposed for quantified analysis and also illustrates the
general trip distribution pattern percentages to and from the Project Area. Figures 2, 3, and 4
illustrate the estimated net trips (i.e., less any trip credits such as pass-by or transit credits) that
would be distributed across the roadway network based on the percentages shown in Figure 1. It
is important to note that the illustrated study area intersections, trip distribution patterns, and trip
assignments are for preliminary discussion purposes only and are subject to modification based on
consultation with the Village and any traffic data that would be collected in support of the
quantified analysis (e.g., traffic counts).
1 A pass-by trip is a trip already present in the traffic stream and is made as an intermediate stop on the way from an
origin to a separate primary trip destination without a route diversion. Pass-by trips are not considered as new trips to
the overall roadway network.
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
383 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
87 Units
470 Units
-4
-13
-17
-14
-8
-22
-10
-9
-19
-4
-11
-15
-12
-8
-20
-9
-8
-17
470 Units
7.423 kSF (8)
-1
-1
-1
-1
-2
-1
-1
-1
-1
7.859 kSF (8)
-1
-1
-2
-3
-2
-5
-3
-2
-5
-1
-1
-2
-2
-3
-5
-2
-3
-5
Pass-by Trips (9)
-2
-1
-7
-7
-14
-6
-5
-11
6.549 kSF (6)
-1
-1
-3
-2
-5
-4
-3
-7
-3
-2
-5
-4
-2
-6
Pass-by Trips (10)
-1
-1
-12
-6
-18
-19
-14
-32
21.831 kSF
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(3) ITE rate of 1.67 trips/1,000 SF (82% entering, 18% exiting) was used for the Weekday AM Peak Hour
ITE rate of 2.16 trips/1,000 SF (34% entering, 66% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.53 trips/1,000 SF (54% entering, 46% exiting) was used for the Saturday Midday Peak Hour. ITE Rates unavailable for the "Small Office Building" land use for the
Saturday Midday Peak Hour, therefore, "General Office Building" land use rates were utilized instead.
(4) ITE rate of 2.36 trips/1,000 SF (60% entering, 40% exiting) was used for the Weekday AM Peak Hour
ITE rate of 6.59 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday PM Peak Hour
ITE rate of 6.57 trips/1,000 SF (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour
(5) ITE rate of 0.73 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday AM Peak Hour
ITE rate of 7.80 trips/1,000 SF (67% entering, 33% exiting) was used for the Weekday PM Peak Hour
ITE rate of 10.68 trips/1,000 SF (59% entering, 41% exiting) was used for the Saturday Midday Peak Hour
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
(8) The commercial square footage was assumed to be 34% office, 36% retail, and 30% restaurant.
(9) Pass-by trip percentage of 34% utilized for the Weekday PM peak hour and 26% utilized for the Saturday Midday peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 820 "Shopping Center". ITE Pass-by trip percentage unavailable for Land Use 820 for the
Weekday AM peak hour and was developed from the ratio of Weekday AM to Weekday PM peak hour trips yielding a pass-by trip percentage of 20%.
(10) Pass-by trip percentage of 44% utilized for the Weekday PM peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 931 "Quality Restaurant". ITE Pass-by trip percentages unavailable for Land Use 931 for the
Weekday AM and Saturday Midday peak hours and were developed from the ratio of Weekday AM and Saturday Midday to Weekday PM peak hour trips yielding pass-by trip percentages of
24% and 57% for the Weekday AM and Saturday Midday peak hours, respectively.
*Source: ITE Trip Generation Manual, 11th Edition
Total Commercial
TOTAL TRIP GENERATION
Strip Retail Plaza (<40k)(4)
Internal Trips (6)
Mass Transit Credit (7)
Total Retail
Restaurant
Fine Dining Restaurant(5)
Internal Trips (6)
Mass Transit Credit (7)
Total Restaurant
Commercial
LI TOD
Office
712 / 710
Small Office Building (AM, PM) /
General Office Building (Sat.)(3)
Internal Trips (6)
Mass Transit Credit (7)
Total Office
Retail
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
Table 1
Trip Generation*
Croton Zoning Study
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
5%
10%
15%
10%
15%
5%
35%
20%
70%
Exiting Trip Distribution Percentages
(Reverse for entering trips)
15%
General Project Area
Outline
PROPOSED STUDY AREA
INTERSECTIONS AND TRIP
DISTRIBUTION PERCENTAGES
Proposed Study Area Intersections
1. Croton Point Ave. and Veterans Plaza
2. Croton Point Ave. and Rt. 9/9A Southbound Ramps
3. Croton Point Ave. and Rt. 9/9A Northbound Ramps
4. Croton Point Ave. and S. Riverside Ave.
5. S. Riverside Ave. and Shopping Center Driveway
6. S. Riverside Ave. and Benedict Blvd.
7. S. Riverside Ave. and Clifton St.
8. S. Riverside Ave. and Oneida Ave.
9. Benedict Blvd. and Wayne St.
Proposed Turning Movement Count (TMC) Time Periods
Weekday AM: 7:00 AM - 10:00 AM
Weekday PM: 4:00 PM - 7:00 PM
Saturday Midday: 11:00 AM - 2:00 PM
Estimated Two-Way Project Generated Traffic
Volumes
Estimated One-Way Project Generated Traffic
Volumes
General Project Area
Outline
ESTIMATED NET TRIP
ASSIGNMENT VOLUMES -
WEEKDAY AM PEAK HOUR
Estimated Two-Way Project Generated Traffic
Volumes
Estimated One-Way Project Generated Traffic
Volumes
General Project Area
Outline
ESTIMATED NET TRIP
ASSIGNMENT VOLUMES -
WEEKDAY PM PEAK HOUR
Estimated Two-Way Project Generated Traffic
Volumes
Estimated One-Way Project Generated Traffic
Volumes
General Project Area
Outline
ESTIMATED NET TRIP
ASSIGNMENT VOLUMES -
SATURDAY PEAK HOUR
Environmental, Planning, and Engineering Consultants
34 South Broadway
Suite 300
White Plains, NY 10601
tel: 914 949-7336
fax: 914 949-7559
www.akrf.com
Offices in New York ● New Jersey ● Pennsylvania ● Maryland ● Connecticut
Technical Memorandum
To:
From:
AKRF, Inc.
Date:
May 27, 2022
Re:
Traffic Screening Analysis – Proposed HSRG Overlay and LI District Zoning
Amendments
This memorandum presents the results of the preliminary screening analysis that was conducted in advance
of the preparation of the Traffic Impact Study (TIS) related to the theoretical maximum buildout projected
under the proposed Harmon/South Riverside Gateway (HSRG) Overlay and Light Industrial (LI) District
zoning amendments.
As indicated in the scope of work dated March 21, 2022, the following six intersections were proposed for
analysis in the TIS:
1.
Croton Point Ave. and Veterans Plaza
2.
Croton Point Ave. and Rt. 9/9A Southbound Ramps
3.
Croton Point Ave. and Rt. 9/9A Northbound Ramps
4.
Croton Point Ave. and S. Riverside Ave.
5.
S. Riverside Ave. and Benedict Blvd.
6.
S. Riverside Ave. and Clinton St.
The preliminary screening analysis was conducted to estimate the likelihood of traffic impacts occurring at
any of the intersections listed above. Any intersections determined to “screen-out” based on the criteria
outlined below would be removed from the TIS study area list of intersections for quantified analysis.
A. SCREENING PROCEDURES
ASSESSMENT OF PROJECT GENERATED TRIPS
The first step of the screening process involved estimating the increase in traffic through each of the six
intersections as a result of the proposed zoning amendments. The trip generation (as presented in AKRF’s
February 25, 2022 memorandum to the Village, see Attachment A) was based on data presented in the
Institute of Transportation Engineers (ITE) Trip Generation Manual, 11th Edition. Assumptions regarding
potential driveway locations were utilized to develop trip assignments for the theoretical maximum buildout
for the weekday AM and PM peak periods. Individual trip assignments were developed for groups of parcels
Village of Croton-on-Hudson Board of Trustees
May 27, 2022
assumed to share common driveways/access points. The cumulative trip assignments were then utilized to
estimate the increase in traffic that would pass through each intersection as a result of the proposed zoning
amendments (see Attachment A for the cumulative parcel trip assignments for the HSRG Overlay and LI
District).
Table 1 summarizes the anticipated increase in traffic as a result of the proposed zoning amendments for
the six intersections examined. The increases are shown for individual vehicle movements (left, through,
right) as well as for the overall intersection.
As shown in Table 1 each of the six intersections are anticipated to experience an overall increase in traffic
in excess of 100 vehicles during both the weekday AM and PM peak periods. A threshold of a 100 vehicle
increase through a given intersection during a peak hour is not uncommon for consideration of a quantified
analysis. However, the increases in traffic for individual vehicle movements were also reviewed.
In examining the increase in traffic for individual vehicle movements, the following four intersections
contain at least one movement which would experience an increase of greater than 50 vehicles:
Croton Point Ave. and Rt. 9/9A Southbound Ramps
Croton Point Ave. and Rt. 9/9A Northbound Ramps
Croton Point Ave. and S. Riverside Ave.
S. Riverside Ave. and Benedict Blvd.
As the common threshold increases for both overall intersection (100 vehicles) and intersection movements
(50 vehicles) would be met at these locations, it is recommended that a quantified analysis is conducted as
part of the TIS for the four intersections listed above.
Since only the increase in traffic for individual vehicle movements would be less than 50 vehicles for the
other two intersections (Croton Point Avenue/Veterans Plaza and S. Riverside Avenue/Clinton Street),
further examination was conducted to determine if a quantified analysis would be warranted.
CROTON POINT AVENUE AND VETERANS PLAZA
As Veterans Plaza provides a direct link to the parking facilities for the Croton-Harmon station of the Metro-
North Railroad and is a major trip origin/destination location in the area, the intersection of Croton Point
Avenue and Veterans Plaza is recommended for quantified analysis.
S. RIVERSIDE AVENUE AND CLINTON STREET
At the intersection of S. Riverside Avenue and Clinton Street, the highest increases in traffic are anticipated
to occur on the Riverside Avenue through movements (all less than 50 vehicles). In order to estimate the
potential effects of these increases, a preliminary capacity analysis was performed for this intersection.
Table 2 presents the preliminary capacity analysis results for the S. Riverside Avenue and Clinton Street
intersection. The Existing Conditions traffic volumes were derived from traffic counts collected in April
2022. A comparison of future No Build (i.e., without the proposed zoning) with future Build (i.e., with the
proposed zoning) was made. For the purposes of this analysis, it was conservatively assumed that the future
design year (i.e., the future year by which the full theoretical buildout from the rezoning would occur)
would be 2042 (2022 + 20 years).
Future No Build traffic volumes were developed by increasing the Existing 2022 traffic volumes in the
study by a 1 percent per year compounded growth rate. This reflected increases in background traffic growth
that would be expected to occur with or without the rezoning. Future Build traffic volumes were developed
by adding the trips that were generated by the rezoning to the No Build network. The weekday AM and PM
peak-hour models of the S. Riverside Avenue and Clinton Street intersection were then evaluated with the
2042 No Build and Build volumes.
May 27, 2022
Movement
Intersection
Movement
Intersection
Traffic Intersections
EB
L
T
R
WB
L
T
R
NB
L
T
R
SB
L
T
R
EB
T
R
WB
L
T
SB
L
T
R
EB
L
T
R
WB
L
T
R
NB
L
T
R
SB
L
T
R
EB
L
R
NB
L
T
SB
T
R
EB
L
T
R
WB
L
T
R
NB
L
T
R
SB
L
T
R
EB
L
R
NB
L
T
SB
T
R
Table 1
Croton Zoning Generated Trips - By Movement & Intersection
Notes:
EB = Eastbound, WB = Westbound, NB = Northbound, SB = Southbound; L = Left, T = Through, R = Right
Croton Point Av & Route 9/9A
NB Ramps/Restaurant Drvwy.
Croton Point Avenue & Route
9/9A SB Ramps
Croton Point Avenue &
Veterans Plaza
South Riverside Avenue &
Croton Point Avenue
South Riverside Avenue &
Benedict Blvd.
South Riverside Avenue &
Clinton St.
AM PEAK HOUR
PM PEAK HOUR
Village of Croton-on-Hudson Board of Trustees
May 27, 2022
Table 2
Preliminary Level of Service Analysis
S. Riverside Avenue & Clinton Street
Peak Hour
Approach
Lane
Group
2022 Existing
2042 No Build
2042 Build
v/c
Delay
LOS
v/c
Delay
LOS
v/c
Delay
LOS
Ratio
(sec)
Ratio
(sec)
Ratio
(sec)
Weekday AM
Peak Hour
EB (Clinton)
LR
0.05
16.0
C
0.08
19.5
C
0.18
20.2
C
NB (S. Riverside)
L
0.01
8.9
A
0.01
9.3
A
0.02
9.5
A
Weekday PM
Peak Hour
EB (Clinton)
LR
0.05
17.3
C
0.09
21.8
C
0.15
21.8
C
NB (S. Riverside)
L
0.01
8.3
A
0.01
8.5
A
0.03
8.8
A
Notes:
v/c = Volume to Capacity; LOS = Level of Service
EB = Eastbound, NB = Northbound; L = Left, R=Right
The capacity analysis was performed using methodologies based on the Highway Capacity Manual, 6th
Edition (HCM 6) methodology (Synchro 11 software) to calculate existing and future traffic operating
conditions (Level of Service (“LOS”) and total delay) at each of the Study Area intersections. LOS is based
on a grading scale of “A” through “F” with “A” representing optimum traffic conditions and “F”
representing poor traffic conditions (LOS D or better is typically considered acceptable operating
conditions).
A comparison of the No Build and Build analysis results indicates that all intersection movements would
continue to operate at acceptable Level of Service (LOS) ‘C’ or better during the peak hours analyzed and
there would be no degradation to unacceptable LOS E or F under 2042 Build conditions with the proposed
rezoning. Therefore, due to the unlikely potential for this intersection to experience impacts with the
proposed rezoning, it is proposed that the intersection of S. Riverside Avenue and Clinton Street not be
included as part of the TIS study area for a quantified analysis.
B. CONCLUSION
Based on the screening outlined above, one intersection has been screened-out of quantified analysis, and
the following five intersections are proposed for quantified analysis in the TIS:
1.
Croton Point Ave. and Veterans Plaza
2.
Croton Point Ave. and Rt. 9/9A Southbound Ramps
3.
Croton Point Ave. and Rt. 9/9A Northbound Ramps
4.
Croton Point Ave. and S. Riverside Ave.
5.
S. Riverside Ave. and Benedict Blvd.
May 27, 2022
ATTACHMENT A
-Trip Generation Table from AKRF’s February 25, 2022
memorandum to the Village
- Cumulative trip assignment volumes for the HSRG
Overlay and LI District
Code #
Land Use
In
Out
Total
In
Out
Total
In
Out
Total
HSRG
Multifamily Housing
(3 story max.)
Multifamily Housing (Low-Rise) - Not
Close to Rail Transit (1)
383 Units
LI TOD
Multifamily Housing
(5 story max.)
Multifamily Housing (Mid-Rise) - Not
Close to Rail Transit(2)
87 Units
470 Units
-4
-13
-17
-14
-8
-22
-10
-9
-19
-4
-11
-15
-12
-8
-20
-9
-8
-17
470 Units
7.423 kSF (8)
-1
-1
-1
-1
-2
-1
-1
-1
-1
7.859 kSF (8)
-1
-1
-2
-3
-2
-5
-3
-2
-5
-1
-1
-2
-2
-3
-5
-2
-3
-5
Pass-by Trips (9)
-2
-1
-7
-7
-14
-6
-5
-11
6.549 kSF (6)
-1
-1
-3
-2
-5
-4
-3
-7
-3
-2
-5
-4
-2
-6
Pass-by Trips (10)
-1
-1
-12
-6
-18
-19
-14
-32
21.831 kSF
Notes:
(1) ITE equation T = 0.31(X) + 22.85 (24% entering, 76% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.43(X) + 20.55 (63% entering, 37% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.41 trips/dwelling unit (50% entering, 50% exiting) was used for the Saturday Midday Peak Hour.
(2) ITE equation T = 0.44(X) - 11.61 (23% entering, 77% exiting) was used for the Weekday AM Peak Hour
ITE equation T = 0.39(X) + 0.34 (61% entering, 39% exiting) was used for the Weekday PM Peak Hour
ITE Equation Ln(T) = 1.00 Ln(x) - 0.91 (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour.
(3) ITE rate of 1.67 trips/1,000 SF (82% entering, 18% exiting) was used for the Weekday AM Peak Hour
ITE rate of 2.16 trips/1,000 SF (34% entering, 66% exiting) was used for the Weekday PM Peak Hour
ITE rate of 0.53 trips/1,000 SF (54% entering, 46% exiting) was used for the Saturday Midday Peak Hour. ITE Rates unavailable for the "Small Office Building" land use for the
Saturday Midday Peak Hour, therefore, "General Office Building" land use rates were utilized instead.
(4) ITE rate of 2.36 trips/1,000 SF (60% entering, 40% exiting) was used for the Weekday AM Peak Hour
ITE rate of 6.59 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday PM Peak Hour
ITE rate of 6.57 trips/1,000 SF (51% entering, 49% exiting) was used for the Saturday Midday Peak Hour
(5) ITE rate of 0.73 trips/1,000 SF (50% entering, 50% exiting) was used for the Weekday AM Peak Hour
ITE rate of 7.80 trips/1,000 SF (67% entering, 33% exiting) was used for the Weekday PM Peak Hour
ITE rate of 10.68 trips/1,000 SF (59% entering, 41% exiting) was used for the Saturday Midday Peak Hour
(6) Internal trips calculated utilizing an internal trip credit of 10%.
(7) Mass Transit credit calculated utilizing a 10% mass transit credit.
(8) The commercial square footage was assumed to be 34% office, 36% retail, and 30% restaurant.
(9) Pass-by trip percentage of 34% utilized for the Weekday PM peak hour and 26% utilized for the Saturday Midday peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 820 "Shopping Center". ITE Pass-by trip percentage unavailable for Land Use 820 for the
Weekday AM peak hour and was developed from the ratio of Weekday AM to Weekday PM peak hour trips yielding a pass-by trip percentage of 20%.
(10) Pass-by trip percentage of 44% utilized for the Weekday PM peak hour, based on average of pass-by trip percentages presented in the Institute of
Transportation Engineers (ITE) Trip Generation Handbook, 3rd Edition for ITE Land Use Code 931 "Quality Restaurant". ITE Pass-by trip percentages unavailable for Land Use 931 for the
Weekday AM and Saturday Midday peak hours and were developed from the ratio of Weekday AM and Saturday Midday to Weekday PM peak hour trips yielding pass-by trip percentages of
24% and 57% for the Weekday AM and Saturday Midday peak hours, respectively.
*Source: ITE Trip Generation Manual, 11th Edition
Total Commercial
TOTAL TRIP GENERATION
Strip Retail Plaza (<40k)(4)
Internal Trips (6)
Mass Transit Credit (7)
Total Retail
Restaurant
Fine Dining Restaurant(5)
Internal Trips (6)
Mass Transit Credit (7)
Total Restaurant
Commercial
LI TOD
Office
712 / 710
Small Office Building (AM, PM) /
General Office Building (Sat.)(3)
Internal Trips (6)
Mass Transit Credit (7)
Total Office
Retail
Weekday PM Peak Hour
Saturday Midday Peak Hour
Residential
Subtotal Residential
Internal Trips (6)
Mass Transit Credit (7)
Total Residential
Table 1
Trip Generation*
Croton Zoning Study
Building
Component
Zoning
Component
Land Use
Description
ITE Land Use
Size
Weekday AM Peak Hour
Table A-1
Croton Zoning Cumulative Trip Assignment Summary
INTERSECTIONS
AM
PM
AM
PM
AM
PM
1. Croton Point Avenue & Veterans Plaza
EB L
T
R
WB L
T
R
NB L
T
R
SB L
T
R
2. Croton Point Avenue & Route 9/9A SB Ramps
EB T
R
WB L
T
SB L
T
R
3. Croton Point Av & Route 9/9A NB Ramps/Restaurant Drvwy.
EB L
T
R
WB L
T
R
NB L
T
R
SB L
T
R
4. South Riverside Avenue/Croton Point Avenue
EB L
R
NB L
T
SB T
R
5. South Riverside Avenue/Benedict Blvd.
EB L
T
R
WB L
T
R
NB L
T
R
SB L
T
R
6. South Riverside Avenue/Clinton St.
EB L
R
NB L
T
SB T
R
COMMERCIAL PROJECT TRAFFIC
EB = Eastbound, WB = Westbound, NB = Northbound, SB = Southbound; L = Left, T = Through, R = Right
Notes:
LI TOD TRIPS
HSRG TRIPS
RESIDENTIAL PROJECT TRAFFIC
RESIDENTIAL PROJECT TRAFFIC
ATTACHMENT B
Capacity Analysis Methodology
Synchro Output Reports
Capacity Analysis Methodology
CAPACITY ANALYSIS METHODOLOGY
SIGNALIZED INTERSECTIONS
AKRF analyzed the operation of Study Area signalized intersections by applying the Percentile
Delay Methodology included in the Synchro 10 traffic signal software. The Percentile Delay
Methodology differs from the Highway Capacity Manual (HCM) Methodology by calculating
vehicle delays for five different percentile scenarios (10th, 30th, 50th, 70th and 90th) and taking
the volume weighted average of the scenarios as compared to HCM, which calculates delay for a
single average scenario. The Percentile Delay Methodology includes an additional queue delay
component to account for the effects of queues and blocking on short links and turning bays. The
methodology evaluates signalized intersections for average delay per vehicle and level of service
(LOS).
LOS is characterized for the entire intersection, each intersection approach, and/or each lane
group. LOS is the only measure of effectiveness provided for the entire intersection operation.
Total delay and volume-to-capacity (v/c) ratio are used to characterize LOS for a lane group. The
volume-to-capacity ratio quantifies the degree to which a phase’s capacity is utilized by a lane
group.
LOS A describes operation with a delay of 10 seconds per vehicle or less and a volume-to-capacity
ratio no greater than 1.0. This level is typically assigned when the volume-to-capacity ratio is low
and either progression is exceptionally favorable or the cycle length is very short. If it is due to
favorable progression, most vehicles arrive during the green indication and travel through the
intersection without stopping.
LOS B describes operation with delay between 10 and 20 seconds per vehicle and a volume-to-
capacity ratio no greater than 1.0. This level is typically assigned when the volume-to-capacity
ratio is low and either progression is highly favorable or the cycle length is short. More vehicles
stop than with LOS A.
LOS C describes operation with delay between 20 and 35 seconds per vehicle and a volume-to-
capacity ratio no greater than 1.0. This level is typically assigned when the volume-to-capacity
ratio is favorable or the cycle length is moderate. Individual cycle failures (i.e., one or more queued
vehicles are not able to depart as a result of insufficient capacity during the cycle) may appear at
this level. The number of vehicles stopping is significant, although many vehicles still pass
through the intersection without stopping.
LOS D describes operation with delay between 35 and 55 seconds per vehicle and a volume-to-
capacity ratio no greater than 1.0. This level is typically assigned when the volume-to-capacity
ratio is high and either progression is ineffective or the cycle length is long. Many vehicles stop
and individual cycle failures are noticeable.
LOS E describes operation with delay between 55 and 80 seconds per vehicle and a volume-to-
capacity ratio no greater than 1.0. This level is typically assigned when the volume-to-capacity
ratio is high, progression is unfavorable, and the cycle length is long. Individual cycle failures are
frequent.
LOS F describes operation with delay exceeding 80 seconds per vehicle or a volume-to-capacity
ratio greater than 1.0. This level is typically assigned when the volume-to-capacity ratio is very
high, progression is very poor, and the cycle length is long. Most cycles fail to clear the queue.
A lane group can incur a delay less than 80 seconds per vehicle when the volume-to-capacity ratio
exceeds 1.0. This condition typically occurs when the cycle length is short, the signal progression
is favorable, or both. As a result, both the delay and volume-to-capacity ratio are considered when
lane group LOS is established. A ratio of 1.0 or more indicates that cycle capacity is fully utilized
and represents failure from a capacity perspective (just as delay in excess of 80 seconds per vehicle
represents failure from a delay perspective).
HCM’s standard delay criteria for the range of service levels at signalized intersections are shown
in Table A.1-1.
Table A.1-1
LOS Criteria for Signalized Intersections
Total Delay Per Vehicle
Level-of-Service (LOS)(1)
v/c ratio ≤1.0
v/c ratio > 1.0
≤ 10.0 seconds
A
F
>10.0 and ≤ 20.0 seconds
B
F
>20.0 and ≤ 35.0 seconds
C
F
>35.0 and ≤ 55.0 seconds
D
F
>55.0 and ≤ 80.0 seconds
E
F
>80.0 seconds
F
F
Note: (1) For approach-based and intersection-wide assessments, LOS is defined solely by delay.
Source: Transportation Research Board. Highway Capacity Manual, 6th Edition.
Synchro Output Reports
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
1: Veterans Plaza/Parking Lot Driveway & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Storage Length (ft)
Storage Lanes
Taper Length (ft)
Lane Util. Factor
1.00
1.00
1.00
0.95
0.95
1.00
1.00
0.95
0.95
1.00
1.00
1.00
Frt
0.989
0.984
0.871
0.850
Flt Protected
0.950
0.973
0.993
0.950
Satd. Flow (prot)
Flt Permitted
0.662
0.757
0.949
0.717
Satd. Flow (perm)
Right Turn on Red
No
Yes
Yes
Yes
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
7.9
3.9
3.9
6.6
Peak Hour Factor
0.81
0.81
0.81
0.91
0.91
0.91
0.78
0.78
0.78
0.63
0.63
0.63
Heavy Vehicles (%)
2%
10%
2%
3%
10%
2%
3%
3%
3%
2%
2%
2%
Adj. Flow (vph)
Shared Lane Traffic (%)
37%
47%
Lane Group Flow (vph)
Enter Blocked Intersection
No
No
No
No
No
No
No
No
No
No
No
No
Lane Alignment
Left
Left
Right
Left
Left
Right
Left
Left
Right
Left
Left
Right
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
1.00
0.96
1.00
1.04
1.04
1.00
1.00
1.09
1.09
1.00
0.88
1.00
Turning Speed (mph)
Number of Detectors
Detector Template
Left
Thru
Left
Thru
Left
Thru
Right
Left
Thru
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 1 Channel
Detector 1 Extend (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Queue (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Delay (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 2 Channel
Detector 2 Extend (s)
0.0
0.0
0.0
0.0
Turn Type
NA
pm+pt
NA
pm+pt
NA
pm+ov
pm+pt
NA
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
1: Veterans Plaza/Parking Lot Driveway & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Protected Phases
Permitted Phases
Detector Phase
Switch Phase
Minimum Initial (s)
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
Minimum Split (s)
11.0
11.0
11.0
11.0
11.0
11.0
11.0
11.0
11.0
Total Split (s)
41.0
41.0
41.0
41.0
41.0
41.0
41.0
41.0
41.0
Total Split (%)
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
Maximum Green (s)
35.0
35.0
35.0
35.0
35.0
35.0
35.0
35.0
35.0
Yellow Time (s)
4.0
4.0
4.0
4.0
4.0
4.0
4.0
4.0
4.0
All-Red Time (s)
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
Lost Time Adjust (s)
0.0
0.0
0.0
0.0
0.0
0.0
Total Lost Time (s)
6.0
6.0
6.0
6.0
6.0
6.0
Lead/Lag
Lag
Lag
Lead
Lag
Lag
Lead
Lead
Lag
Lead
Lead-Lag Optimize?
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Vehicle Extension (s)
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
Recall Mode
C-Max
C-Max
None
C-Max
None
None
None
None
None
Walk Time (s)
7.0
7.0
7.0
7.0
7.0
7.0
7.0
Flash Dont Walk (s)
18.0
18.0
18.0
18.0
18.0
18.0
18.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
132.1
141.1
141.1
7.2
19.9
7.2
Actuated g/C Ratio
0.81
0.86
0.86
0.04
0.12
0.04
v/c Ratio
0.10
0.20
0.20
0.50
0.25
0.16
Control Delay
4.4
1.9
1.8
30.2
14.0
79.5
Queue Delay
0.0
1.0
2.7
0.0
0.0
0.0
Total Delay
4.4
2.8
4.5
30.2
14.0
79.5
LOS
A
A
A
C
B
E
Approach Delay
4.4
3.7
22.2
79.5
Approach LOS
A
A
C
E
Intersection Summary
Area Type:
Other
Cycle Length: 164
Actuated Cycle Length: 164
Offset: 0 (0%), Referenced to phase 6:EBWB, Start of Yellow
Natural Cycle: 45
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.50
Intersection Signal Delay: 8.0
Intersection LOS: A
Intersection Capacity Utilization 36.8%
ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 1: Veterans Plaza/Parking Lot Driveway & Croton Point Ave.
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Storage Length (ft)
Storage Lanes
Taper Length (ft)
Lane Util. Factor
1.00
0.95
0.95
0.95
0.95
1.00
1.00
1.00
1.00
1.00
0.95
0.95
Frt
0.949
0.912
0.850
Flt Protected
0.969
0.980
Satd. Flow (prot)
Flt Permitted
0.656
0.980
Satd. Flow (perm)
Right Turn on Red
No
Yes
Yes
No
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
3.9
9.4
9.8
11.2
Peak Hour Factor
0.82
0.82
0.82
0.89
0.89
0.89
0.92
0.92
0.92
0.85
0.85
0.85
Heavy Vehicles (%)
2%
10%
10%
5%
5%
2%
2%
2%
2%
5%
5%
5%
Adj. Flow (vph)
Shared Lane Traffic (%)
38%
Lane Group Flow (vph)
Enter Blocked Intersection
No
No
No
No
No
No
No
No
No
No
No
No
Lane Alignment
Left
Left
Right
Left
Left
Right
Left
Left
Right
Left
Left
Right
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
1.00
1.04
1.00
1.00
1.04
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Turning Speed (mph)
Number of Detectors
Detector Template
Thru
Left
Thru
Left
Thru
Right
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 1 Channel
Detector 1 Extend (s)
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Queue (s)
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Delay (s)
0.0
0.0
0.0
0.0
0.0
0.0
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Cl+Ex
Cl+Ex
Cl+Ex
Detector 2 Channel
Detector 2 Extend (s)
0.0
0.0
0.0
Turn Type
NA
custom
NA
Perm
NA
Perm
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
Ø2
Ø3
Ø4
Ø6
Ø8
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Storage Length (ft)
Storage Lanes
Taper Length (ft)
Lane Util. Factor
Frt
Flt Protected
Satd. Flow (prot)
Flt Permitted
Satd. Flow (perm)
Right Turn on Red
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
Peak Hour Factor
Heavy Vehicles (%)
Adj. Flow (vph)
Shared Lane Traffic (%)
Lane Group Flow (vph)
Enter Blocked Intersection
Lane Alignment
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
Turning Speed (mph)
Number of Detectors
Detector Template
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Detector 1 Channel
Detector 1 Extend (s)
Detector 1 Queue (s)
Detector 1 Delay (s)
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Detector 2 Channel
Detector 2 Extend (s)
Turn Type
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Protected Phases
2 8
6 8
Permitted Phases
Detector Phase
2 8
6 8
Switch Phase
Minimum Initial (s)
5.0
5.0
5.0
5.0
Minimum Split (s)
22.0
31.0
31.0
31.0
Total Split (s)
26.0
36.0
36.0
36.0
Total Split (%)
17.6%
24.3%
24.3%
24.3%
Maximum Green (s)
20.0
30.0
30.0
30.0
Yellow Time (s)
4.0
4.0
4.0
4.0
All-Red Time (s)
2.0
2.0
2.0
2.0
Lost Time Adjust (s)
0.0
0.0
Total Lost Time (s)
6.0
6.0
Lead/Lag
Lag
Lead
Lead
Lead
Lead-Lag Optimize?
Yes
Yes
Yes
Yes
Vehicle Extension (s)
1.0
2.0
2.0
2.0
Recall Mode
None
Min
Min
Min
Walk Time (s)
7.0
7.0
7.0
Flash Dont Walk (s)
18.0
18.0
18.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
40.1
116.1
19.9
19.9
Actuated g/C Ratio
0.27
0.78
0.13
0.13
v/c Ratio
0.30
0.23
0.77
0.78
Control Delay
45.4
4.9
85.1
87.1
Queue Delay
0.1
0.3
0.0
0.0
Total Delay
45.4
5.2
85.1
87.1
LOS
D
A
F
F
Approach Delay
45.4
5.2
86.1
Approach LOS
D
A
F
Intersection Summary
Area Type:
Other
Cycle Length: 148
Actuated Cycle Length: 148
Offset: 95 (64%), Referenced to phase 6:WBTL, Start of Yellow
Natural Cycle: 115
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.97
Intersection Signal Delay: 38.0
Intersection LOS: D
Intersection Capacity Utilization 46.7%
ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
Ø2
Ø3
Ø4
Ø6
Ø8
Protected Phases
Permitted Phases
Detector Phase
Switch Phase
Minimum Initial (s)
10.0
5.0
4.0
10.0
4.0
Minimum Split (s)
39.0
22.0
20.0
29.0
20.0
Total Split (s)
66.0
36.0
20.0
66.0
20.0
Total Split (%)
45%
24%
14%
45%
14%
Maximum Green (s)
60.0
30.0
15.0
60.0
15.0
Yellow Time (s)
4.0
4.0
3.5
4.0
3.5
All-Red Time (s)
2.0
2.0
1.5
2.0
1.5
Lost Time Adjust (s)
Total Lost Time (s)
Lead/Lag
Lead
Lead
Lag
Lag
Lead-Lag Optimize?
Yes
Yes
Yes
Yes
Vehicle Extension (s)
3.0
2.0
3.0
2.0
3.0
Recall Mode
Min
None
None
C-Max
None
Walk Time (s)
7.0
7.0
Flash Dont Walk (s)
26.0
16.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
Actuated g/C Ratio
v/c Ratio
Control Delay
Queue Delay
Total Delay
LOS
Approach Delay
Approach LOS
Intersection Summary
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
3: Rt. 9/9A NB Ramps/Driveway & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Lane Util. Factor
0.95
0.95
0.95
0.95
0.95
0.95
1.00
1.00
1.00
1.00
1.00
1.00
Frt
0.952
0.930
Flt Protected
0.994
0.976
Satd. Flow (prot)
Flt Permitted
0.878
0.846
Satd. Flow (perm)
Right Turn on Red
Yes
Yes
No
Yes
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
9.4
10.8
13.4
1.9
Peak Hour Factor
0.89
0.89
0.89
0.90
0.90
0.90
0.95
0.95
0.95
0.92
0.92
0.92
Heavy Vehicles (%)
2%
5%
5%
5%
5%
2%
5%
2%
5%
2%
2%
2%
Adj. Flow (vph)
Shared Lane Traffic (%)
Lane Group Flow (vph)
Enter Blocked Intersection
No
No
No
No
No
No
No
No
No
No
No
No
Lane Alignment
Left
Left
Right
Left
Left
Right
Left
Left
Right
Left
Left
Right
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
1.00
1.04
1.00
1.00
1.04
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Turning Speed (mph)
Number of Detectors
Detector Template
Left
Thru
Left
Thru
Left
Thru
Left
Thru
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 1 Channel
Detector 1 Extend (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Queue (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Delay (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 2 Channel
Detector 2 Extend (s)
0.0
0.0
0.0
0.0
Turn Type
NA
Perm
NA
Perm
NA
Protected Phases
1 2 4
4 6
Permitted Phases
1 2 4
4 6
Detector Phase
1 2 4
1 2 4
4 6
4 6
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
3: Rt. 9/9A NB Ramps/Driveway & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
Ø1
Ø2
Ø4
Ø6
Ø7
Ø8
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Lane Util. Factor
Frt
Flt Protected
Satd. Flow (prot)
Flt Permitted
Satd. Flow (perm)
Right Turn on Red
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
Peak Hour Factor
Heavy Vehicles (%)
Adj. Flow (vph)
Shared Lane Traffic (%)
Lane Group Flow (vph)
Enter Blocked Intersection
Lane Alignment
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
Turning Speed (mph)
Number of Detectors
Detector Template
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Detector 1 Channel
Detector 1 Extend (s)
Detector 1 Queue (s)
Detector 1 Delay (s)
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Detector 2 Channel
Detector 2 Extend (s)
Turn Type
Protected Phases
Permitted Phases
Detector Phase
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
3: Rt. 9/9A NB Ramps/Driveway & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Switch Phase
Minimum Initial (s)
5.0
5.0
5.0
5.0
Minimum Split (s)
22.0
22.0
22.0
22.0
Total Split (s)
36.0
36.0
36.0
36.0
Total Split (%)
24.3%
24.3%
24.3%
24.3%
Maximum Green (s)
30.0
30.0
30.0
30.0
Yellow Time (s)
4.0
4.0
4.0
4.0
All-Red Time (s)
2.0
2.0
2.0
2.0
Lost Time Adjust (s)
0.0
0.0
Total Lost Time (s)
6.0
6.0
Lead/Lag
Lead
Lead
Lead
Lead
Lead-Lag Optimize?
Yes
Yes
Yes
Yes
Vehicle Extension (s)
2.0
2.0
2.0
2.0
Recall Mode
None
None
None
None
Walk Time (s)
Flash Dont Walk (s)
Pedestrian Calls (#/hr)
Act Effct Green (s)
106.3
107.3
29.7
Actuated g/C Ratio
0.72
0.72
0.20
v/c Ratio
0.09
0.20
0.97
Control Delay
5.8
6.8
104.4
Queue Delay
0.0
0.0
0.0
Total Delay
5.8
6.8
104.4
LOS
A
A
F
Approach Delay
5.8
6.8
104.4
Approach LOS
A
A
F
Intersection Summary
Area Type:
Other
Cycle Length: 148
Actuated Cycle Length: 148
Offset: 95 (64%), Referenced to phase 6:WBTL, Start of Yellow
Natural Cycle: 115
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.97
Intersection Signal Delay: 36.3
Intersection LOS: D
Intersection Capacity Utilization 45.6%
ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 3: Rt. 9/9A NB Ramps/Driveway & Croton Point Ave.
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
3: Rt. 9/9A NB Ramps/Driveway & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
Ø1
Ø2
Ø4
Ø6
Ø7
Ø8
Switch Phase
Minimum Initial (s)
5.0
10.0
4.0
10.0
5.0
4.0
Minimum Split (s)
22.0
39.0
20.0
29.0
31.0
20.0
Total Split (s)
26.0
66.0
20.0
66.0
36.0
20.0
Total Split (%)
18%
45%
14%
45%
24%
14%
Maximum Green (s)
20.0
60.0
15.0
60.0
30.0
15.0
Yellow Time (s)
4.0
4.0
3.5
4.0
4.0
3.5
All-Red Time (s)
2.0
2.0
1.5
2.0
2.0
1.5
Lost Time Adjust (s)
Total Lost Time (s)
Lead/Lag
Lag
Lead
Lag
Lead
Lag
Lead-Lag Optimize?
Yes
Yes
Yes
Yes
Yes
Vehicle Extension (s)
1.0
3.0
3.0
2.0
2.0
3.0
Recall Mode
None
Min
None
C-Max
Min
None
Walk Time (s)
7.0
7.0
7.0
Flash Dont Walk (s)
26.0
16.0
18.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
Actuated g/C Ratio
v/c Ratio
Control Delay
Queue Delay
Total Delay
LOS
Approach Delay
Approach LOS
Intersection Summary
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
4: S. Riverside Ave. & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBR
NBL
NBT
SBT
SBR
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Lane Util. Factor
0.97
0.95
0.95
0.95
1.00
1.00
Frt
0.938
0.850
Flt Protected
0.971
0.974
Satd. Flow (prot)
Flt Permitted
0.971
0.826
Satd. Flow (perm)
Right Turn on Red
Yes
Yes
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
10.8
8.3
11.8
Peak Hour Factor
0.88
0.88
0.97
0.97
0.90
0.90
Heavy Vehicles (%)
5%
5%
5%
5%
5%
5%
Adj. Flow (vph)
Shared Lane Traffic (%)
Lane Group Flow (vph)
Enter Blocked Intersection
No
No
No
No
No
No
Lane Alignment
Left
Right
Left
Left
Left
Right
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
1.04
1.04
1.09
1.09
1.09
1.09
Turning Speed (mph)
Turn Type
Prot
Perm
NA
NA
pm+ov
Protected Phases
Permitted Phases
Minimum Split (s)
31.0
36.0
36.0
36.0
31.0
Total Split (s)
31.0
36.0
36.0
36.0
31.0
Total Split (%)
46.3%
53.7%
53.7%
53.7%
46.3%
Maximum Green (s)
25.0
30.0
30.0
30.0
25.0
Yellow Time (s)
4.0
4.0
4.0
4.0
4.0
All-Red Time (s)
2.0
2.0
2.0
2.0
2.0
Lost Time Adjust (s)
0.0
0.0
0.0
0.0
Total Lost Time (s)
6.0
6.0
6.0
6.0
Lead/Lag
Lead-Lag Optimize?
Walk Time (s)
7.0
7.0
7.0
7.0
7.0
Flash Dont Walk (s)
18.0
23.0
23.0
23.0
18.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
25.0
30.0
30.0
67.0
Actuated g/C Ratio
0.37
0.45
0.45
1.00
v/c Ratio
0.24
0.08
0.06
0.26
Control Delay
8.9
10.9
10.9
0.4
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
4: S. Riverside Ave. & Croton Point Ave.
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBR
NBL
NBT
SBT
SBR
Queue Delay
0.0
0.0
0.0
0.0
Total Delay
8.9
10.9
10.9
0.4
LOS
A
B
B
A
Approach Delay
8.9
10.9
1.7
Approach LOS
A
B
A
Intersection Summary
Area Type:
Other
Cycle Length: 67
Actuated Cycle Length: 67
Offset: 0 (0%), Referenced to phase 2:NBTL and 6:SBT, Start of Green
Natural Cycle: 70
Control Type: Pretimed
Maximum v/c Ratio: 0.26
Intersection Signal Delay: 5.4
Intersection LOS: A
Intersection Capacity Utilization 33.9%
ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 4: S. Riverside Ave. & Croton Point Ave.
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
5: S. Riverside Ave. & Benedict Blvd
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Lane Util. Factor
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Frt
0.989
0.967
0.850
0.990
Flt Protected
0.995
0.998
0.997
0.988
Satd. Flow (prot)
Flt Permitted
0.957
0.984
0.954
0.851
Satd. Flow (perm)
Right Turn on Red
Yes
Yes
Yes
Yes
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
6.2
7.8
11.8
8.3
Peak Hour Factor
0.95
0.95
0.95
0.82
0.82
0.82
0.83
0.83
0.83
0.86
0.86
0.86
Bus Blockages (#/hr)
Adj. Flow (vph)
Shared Lane Traffic (%)
Lane Group Flow (vph)
Enter Blocked Intersection
No
No
No
No
No
No
No
No
No
No
No
No
Lane Alignment
Left
Left
Right
Left
Left
Right
Left
Left
Right
Left
Left
Right
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
1.00
0.85
1.00
1.00
0.85
1.00
1.00
1.09
1.14
1.00
1.00
1.00
Turning Speed (mph)
Turn Type
Perm
NA
Perm
NA
Perm
NA
Perm
Perm
NA
Protected Phases
Permitted Phases
Minimum Split (s)
31.0
31.0
31.0
31.0
40.0
40.0
40.0
40.0
40.0
Total Split (s)
31.0
31.0
31.0
31.0
40.0
40.0
40.0
40.0
40.0
Total Split (%)
43.7%
43.7%
43.7%
43.7%
56.3%
56.3%
56.3%
56.3%
56.3%
Maximum Green (s)
25.0
25.0
25.0
25.0
34.0
34.0
34.0
34.0
34.0
Yellow Time (s)
4.0
4.0
4.0
4.0
4.0
4.0
4.0
4.0
4.0
All-Red Time (s)
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
Lost Time Adjust (s)
0.0
0.0
0.0
0.0
0.0
Total Lost Time (s)
6.0
6.0
6.0
6.0
6.0
Lead/Lag
Lead-Lag Optimize?
Walk Time (s)
7.0
7.0
7.0
7.0
7.0
7.0
7.0
7.0
7.0
Flash Dont Walk (s)
18.0
18.0
18.0
18.0
27.0
27.0
27.0
27.0
27.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
25.0
25.0
34.0
34.0
34.0
Actuated g/C Ratio
0.35
0.35
0.48
0.48
0.48
v/c Ratio
0.29
0.37
0.26
0.04
0.79
Control Delay
17.4
17.3
12.2
2.1
25.1
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
5: S. Riverside Ave. & Benedict Blvd
Weekday AM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Queue Delay
0.0
0.0
0.0
0.0
0.0
Total Delay
17.4
17.3
12.2
2.1
25.1
LOS
B
B
B
A
C
Approach Delay
17.4
17.3
11.0
25.1
Approach LOS
B
B
B
C
Intersection Summary
Area Type:
Other
Cycle Length: 71
Actuated Cycle Length: 71
Offset: 0 (0%), Referenced to phase 2:NBTL and 6:SBTL, Start of Green
Natural Cycle: 75
Control Type: Pretimed
Maximum v/c Ratio: 0.79
Intersection Signal Delay: 19.7
Intersection LOS: B
Intersection Capacity Utilization 68.0%
ICU Level of Service C
Analysis Period (min) 15
Splits and Phases: 5: S. Riverside Ave. & Benedict Blvd
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
1: Veterans Plaza/Parking Lot Driveway & Croton Point Ave.
Weekday PM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Storage Length (ft)
Storage Lanes
Taper Length (ft)
Lane Util. Factor
1.00
1.00
1.00
0.95
0.95
1.00
1.00
0.95
0.95
1.00
1.00
1.00
Frt
0.993
0.994
0.852
0.850
Flt Protected
0.950
0.995
0.999
0.950
Satd. Flow (prot)
Flt Permitted
0.649
0.975
0.996
0.449
Satd. Flow (perm)
Right Turn on Red
No
Yes
Yes
Yes
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
7.9
3.9
3.9
6.6
Peak Hour Factor
0.77
0.77
0.77
0.92
0.92
0.92
0.82
0.82
0.82
0.31
0.31
0.31
Heavy Vehicles (%)
2%
10%
2%
3%
10%
2%
3%
3%
3%
2%
2%
2%
Adj. Flow (vph)
Shared Lane Traffic (%)
10%
50%
Lane Group Flow (vph)
Enter Blocked Intersection
No
No
No
No
No
No
No
No
No
No
No
No
Lane Alignment
Left
Left
Right
Left
Left
Right
Left
Left
Right
Left
Left
Right
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
1.00
0.96
1.00
1.04
1.04
1.00
1.00
1.09
1.09
1.00
0.88
1.00
Turning Speed (mph)
Number of Detectors
Detector Template
Left
Thru
Left
Thru
Left
Thru
Right
Left
Thru
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 1 Channel
Detector 1 Extend (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Queue (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Delay (s)
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 2 Channel
Detector 2 Extend (s)
0.0
0.0
0.0
0.0
Turn Type
NA
pm+pt
NA
pm+pt
NA
pm+ov
pm+pt
NA
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
1: Veterans Plaza/Parking Lot Driveway & Croton Point Ave.
Weekday PM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Protected Phases
Permitted Phases
Detector Phase
Switch Phase
Minimum Initial (s)
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
Minimum Split (s)
11.0
11.0
11.0
11.0
11.0
11.0
11.0
11.0
11.0
Total Split (s)
41.0
41.0
41.0
41.0
41.0
41.0
41.0
41.0
41.0
Total Split (%)
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
25.0%
Maximum Green (s)
35.0
35.0
35.0
35.0
35.0
35.0
35.0
35.0
35.0
Yellow Time (s)
4.0
4.0
4.0
4.0
4.0
4.0
4.0
4.0
4.0
All-Red Time (s)
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
Lost Time Adjust (s)
0.0
0.0
0.0
0.0
0.0
0.0
Total Lost Time (s)
6.0
6.0
6.0
6.0
6.0
6.0
Lead/Lag
Lag
Lag
Lead
Lag
Lag
Lead
Lead
Lag
Lead
Lead-Lag Optimize?
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Vehicle Extension (s)
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
Recall Mode
C-Max
C-Max
None
C-Max
None
None
None
None
None
Walk Time (s)
7.0
7.0
7.0
7.0
7.0
7.0
7.0
Flash Dont Walk (s)
18.0
18.0
18.0
18.0
18.0
18.0
18.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
130.1
137.1
137.1
8.9
21.9
8.9
Actuated g/C Ratio
0.79
0.84
0.84
0.05
0.13
0.05
v/c Ratio
0.12
0.11
0.09
0.70
0.47
0.33
Control Delay
4.5
2.0
1.9
27.9
13.3
90.0
Queue Delay
0.0
0.6
1.9
0.0
0.0
0.0
Total Delay
4.5
2.6
3.8
27.9
13.3
90.0
LOS
A
A
A
C
B
F
Approach Delay
4.5
3.3
20.7
90.0
Approach LOS
A
A
C
F
Intersection Summary
Area Type:
Other
Cycle Length: 164
Actuated Cycle Length: 164
Offset: 0 (0%), Referenced to phase 6:EBWB, Start of Yellow
Natural Cycle: 45
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.70
Intersection Signal Delay: 12.9
Intersection LOS: B
Intersection Capacity Utilization 36.2%
ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 1: Veterans Plaza/Parking Lot Driveway & Croton Point Ave.
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
Weekday PM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Storage Length (ft)
Storage Lanes
Taper Length (ft)
Lane Util. Factor
1.00
0.95
0.95
0.95
0.95
1.00
1.00
1.00
1.00
1.00
0.95
0.95
Frt
0.957
0.987
0.850
Flt Protected
0.970
0.956
Satd. Flow (prot)
Flt Permitted
0.580
0.956
Satd. Flow (perm)
Right Turn on Red
No
Yes
Yes
No
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
3.9
9.4
9.8
11.2
Peak Hour Factor
0.88
0.88
0.88
0.87
0.87
0.87
0.92
0.92
0.92
0.90
0.90
0.90
Heavy Vehicles (%)
2%
10%
10%
5%
5%
2%
2%
2%
2%
5%
5%
5%
Adj. Flow (vph)
Shared Lane Traffic (%)
10%
Lane Group Flow (vph)
Enter Blocked Intersection
No
No
No
No
No
No
No
No
No
No
No
No
Lane Alignment
Left
Left
Right
Left
Left
Right
Left
Left
Right
Left
Left
Right
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
1.00
1.04
1.00
1.00
1.04
1.00
1.00
1.00
1.00
1.00
1.00
1.00
Turning Speed (mph)
Number of Detectors
Detector Template
Thru
Left
Thru
Left
Thru
Right
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Cl+Ex
Detector 1 Channel
Detector 1 Extend (s)
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Queue (s)
0.0
0.0
0.0
0.0
0.0
0.0
Detector 1 Delay (s)
0.0
0.0
0.0
0.0
0.0
0.0
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Cl+Ex
Cl+Ex
Cl+Ex
Detector 2 Channel
Detector 2 Extend (s)
0.0
0.0
0.0
Turn Type
NA
custom
NA
Perm
NA
Perm
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
Weekday PM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
Ø2
Ø3
Ø4
Ø6
Ø8
Lane Configurations
Traffic Volume (vph)
Future Volume (vph)
Ideal Flow (vphpl)
Lane Width (ft)
Storage Length (ft)
Storage Lanes
Taper Length (ft)
Lane Util. Factor
Frt
Flt Protected
Satd. Flow (prot)
Flt Permitted
Satd. Flow (perm)
Right Turn on Red
Satd. Flow (RTOR)
Link Speed (mph)
Link Distance (ft)
Travel Time (s)
Peak Hour Factor
Heavy Vehicles (%)
Adj. Flow (vph)
Shared Lane Traffic (%)
Lane Group Flow (vph)
Enter Blocked Intersection
Lane Alignment
Median Width(ft)
Link Offset(ft)
Crosswalk Width(ft)
Two way Left Turn Lane
Headway Factor
Turning Speed (mph)
Number of Detectors
Detector Template
Leading Detector (ft)
Trailing Detector (ft)
Detector 1 Position(ft)
Detector 1 Size(ft)
Detector 1 Type
Detector 1 Channel
Detector 1 Extend (s)
Detector 1 Queue (s)
Detector 1 Delay (s)
Detector 2 Position(ft)
Detector 2 Size(ft)
Detector 2 Type
Detector 2 Channel
Detector 2 Extend (s)
Turn Type
HSRG Overlay and LI District Zoning Amendments
2022 Existing Conditions
2: Rt. 9/9A SB On-Ramp/Rt. 9/9A SB Off-Ramp & Croton Point Ave.
Weekday PM Peak Hour
AKRF, Inc.
Synchro 11 Report
Lane Group
EBL
EBT
EBR
WBL
WBT
WBR
NBL
NBT
NBR
SBL
SBT
SBR
Protected Phases
2 8
6 8
Permitted Phases
Detector Phase
2 8
6 8
Switch Phase
Minimum Initial (s)
5.0
5.0
5.0
5.0
Minimum Split (s)
22.0
31.0
31.0
31.0
Total Split (s)
26.0
36.0
36.0
36.0
Total Split (%)
17.6%
24.3%
24.3%
24.3%
Maximum Green (s)
20.0
30.0
30.0
30.0
Yellow Time (s)
4.0
4.0
4.0
4.0
All-Red Time (s)
2.0
2.0
2.0
2.0
Lost Time Adjust (s)
0.0
0.0
Total Lost Time (s)
6.0
6.0
Lead/Lag
Lag
Lead
Lead
Lead
Lead-Lag Optimize?
Yes
Yes
Yes
Yes
Vehicle Extension (s)
1.0
2.0
2.0
2.0
Recall Mode
None
Min
Min
Min
Walk Time (s)
7.0
7.0
7.0
Flash Dont Walk (s)
18.0
18.0
18.0
Pedestrian Calls (#/hr)
Act Effct Green (s)
49.7
125.3
10.7
10.7
Actuated g/C Ratio
0.34
0.85
0.07
0.07
v/c Ratio
0.42
0.20
0.59
0.51
Control Delay
40.1
2.1
85.7
81.9
Queue Delay
0.1
0.3
0.0
0.0
Total Delay
40.2
2.4
85.7
81.9
LOS
D
A
F
F
Approach Delay
40.2
2.4
84.0
Approach LOS
D
A
F
Intersection S
[...truncated...]