CoH Train Station Parking Lot Shoreline Resiliency and Flood Mitigation 20250904
report
9 pages
From the meeting:
Board of Trustees Work Session — 2025-11-12
· our coverage →
Agenda item: Update on shoreline resiliency study at the Croton-Harmon Train Station parking lot.
Report / study, 9 pages. Attached to agenda item: “Update on shoreline resiliency study at the Croton-Harmon Train Station parking lot.”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Extracted text
34 South Broadway, Suite 300
White Plains, NY 10601
tel: 914.949.7336
www.akrf.com
Memorandum
To: Bryan T. Healy [Village of Croton-on-Hudson]
From: David Stahl [AKRF]
Date: 07/03/2025
Re: Croton-Harmon Train Station Parking Lot – Shoreline Resiliency and Flood Mitigation
cc: Dan O’Connor, Frank Balbi [Village of Croton-on-Hudson]; Patrick Parault, Justin Seeney, Nora
Schmidt [AKRF]
The Metro-North Railroad (MTA) Croton Harmon Train Station in the Village of Croton on Hudson (Village)
has experienced significant flooding conditions at Parking Lot I (site). The flooding is caused by high tides
that enter the site from the adjacent Hudson River. These flooding conditions reduce parking capacity and
increase the risk of vehicular and property damage.
The Village contracted AKRF to evaluate existing flooding and future flooding conditions from projected sea
level rise, to identify alternatives to mitigate this risk, and propose a recommendation to advance to potential
design and funding procurement. AKRF performed a desktop analysis of current and projected future flood
conditions, visited the site during a flood condition, identified possible design flood elevations (DFE) to
protect the site with varying levels of risk mitigation, selected a singular DFE to design to that would protect
the site through 2080, developed three alternatives in consultation with the Village, and developed a
recommendation to construct a 1,200-foot-long, 2-to-3-foot-high knee wall to provide flood protection up to
elevation 6.0, along with a new stormwater collection system and pump.
Due Diligence
To understand the site's characteristics, historical information, including site surveys, as-built plans, and
historical flooding event photos provided by the Village were reviewed. Westchester County GIS and LiDAR
data were obtained to supplement the files provided by the Village. Based on a review of historical imagery,
the parking lot was constructed between 1953 and 1974 over assumed marshland. The parking lot was
retrofitted in 2009/2010 to raise its elevation to 4.9 feet based on the rim elevations of the inlets.
To determine the elevations that cause the parking lot to flood, AKRF established a relationship between
the tide gauges and elevations within the site. AKRF analyzed the tide gauges located closest to the site:
(i) The NOAA gauge at the Battery is approximately 30 miles south of the site, and (ii) USGS has a gauge
at Piermont, NY approximately 5 miles south of the site. The USGS gauge has a smaller record period, so
a correlation between the two sites' water surface elevation levels (WSEL) was calculated. It was
determined that the max WSEL difference between the two sites was 0.25 feet, meaning that the elevation
at the Battery was on average 0.25 feet higher than the elevation at the Piermont station. Using this, AKRF
calculated the approximate water elevations for historical storms shared by the Village. See Table 1 for a
summary of historical flooding events. Summary photos from these historical events were shared by the
Village and are included in Figure 1. It was found that the primary cause of flooding was due to high tidal
water levels that occur because of lunar tides. Sometimes, rain coincides with high water levels and
Croton-Harmon Train Station Parking Lot – Shoreline Resiliency and Flood Mitigation 05/23/25
compounds onsite flooding. Storms that coincide with higher tide can increase the predicted tides because
of the storm surge caused by the storm system.
Table 1. Historical Flood Events at Project Site
Date
Est. Flood
Depth
(based on
photos)
Hudson
Water Level
(Piermont
Station) – FT
NAVD88
Max Flood
Time
(Piermont
Station)
Last Rain
Amount
(in)
Days
from Last
Rain
Event
Days
to/from
Full/New
Moon
12/23/20221
24-30"
5.68
9:12
0.84
9/30/20231
6"
4.01
10:42
1.77
12/28/20231
6-10"
4.10
11:00
1.80
1/13/20241
30-40"
5.58
11:42
2.38
9/20/20242
4-8"
3.73
11:30
0.35
1) Photos from these events were provided by the Village and included in Figure 1.
2) Photos from this event were taken by AKRF as part of this project and are included in Figure 2.
12.23.22 9:23 AM
9.30.23 12:36 PM
12.28.23 11:17 AM
1.13.24 11:55 AM
Figure 1. Photos taken during historical flooding events.
AKRF performed a site visit on 9/20/2024. The peak high tide was observed around 12:30 pm which
coincides with the photo time stamps. Only 4-8 inches of flooding was observed. This flooding is described
as “nuisance flooding” and would not cause damage to personal property and vehicles. Based on
observations, the water entered the site from the marsh on the eastern side of the parking lot. It was
observed that water entered the parking lot through the existing drainage system as seen in Photo D, in
Croton-Harmon Train Station Parking Lot – Shoreline Resiliency and Flood Mitigation 05/23/25
Figure 2. The original site plans for the 2009 upgrade included duck bill tide gates; however, based on
discussions with the Village, it was understood that these tide gates were not installed. The missing tide
gates allow tidal water to back up through the storm sewer system causing the surcharging inlets as
observed. The amount of flooding during this event was higher than expected based on site elevations, and
AKRF calculated that settling had occurred which is described in the next section.
Photo A
Photo B
Photo C
Photo D
Figure 2. Photos taken during site visit on 9/20/2024 by AKRF.
Site Settling Analysis
Based on the elevations provided in the as-builts and Westchester County LiDAR, the site was experiencing
more flooding than expected. AKRF predicted that settling at the site was the cause of the increased
flooding and calculated this by using 1 foot contour data from 2019 (NYS Contour Download App) for the
Town of Cortland and the as-built contours from the 2009 parking lot retrofit. AKRF calculated the site was
about 0.8 feet lower than the design elevations from 2009. This was further verified by Value.Space, a third-
party contractor, who performed an aerial movement analysis using imagery from 2016-2024. They also
determined that the site is subsiding. Value Space’s report indicates that the rate of subsistence in Lot I
has decreased over time: up to 37 mm/yr from 2016-2018, up to 34 mm/y from 2018-2021, and up to 24
mm/yr from 2021-2024. There is not enough information to predict if or when the site will stop settling. Using
the lowest setting rate from 2021-2024 (24 mm/yr), AKRF projected that approximately 1.2 feet of settling
has occurred in Lot I from 2009-2024.
Exposure Screening and Vulnerability Analysis
AKRF analyzed the known flood events to determine the cause of flooding within the parking lot. The tides,
lunar cycles, and past precipitation were analyzed to determine if overland (stormwater runoff) or tidal
fluctuations were the main cause of flooding in the parking lot. Based on the analysis the primary cause of
Croton-Harmon Train Station Parking Lot – Shoreline Resiliency and Flood Mitigation 05/23/25
flooding was the tidal and lunar cycle, with more flooding occurring during a high tide that was closer to a
new or full moon, when tides are highest. Water levels may be higher during events where both rain and a
high tide impact the site.
To evaluate the effects of various tidal conditions on the site, AKRF mapped out various water level datums
such as the current FEMA Limit of Moderate Wave Action (LiMWA), Mean Higher High Water (MHHW),
100-year, and 500-year floodplains. The site is fully within the 500-year and 100-year floodplains and ARKF
recommended to not size an intervention to these levels due to the significant disturbance and anticipated.
The Village acknowledged that any intervention was not going to elevate or eliminate the site above the
100- or 500-year floodplains.
To determine the impact of projected sea level rise on flooding of the parking lot, AKRF applied sea level
rise adjustment factors from the New York City Panel on Climate Change to the LiMWA and MHHW
elevations. Table 2 shows the elevations and impacts to the site on parking and structures for MHHW and
LiMWA for existing, projected 2020, 2050, and 2080 Sea Level Rise (SLR) conditions. Figure 3 graphically
shows these existing and projected elevations on the site map with present day elevations (no further
settlement). The observed flooding event on 9/20/24 and historical flood elevations were all above the
existing MHHW and MHHW with SLR. The LiMWA elevations consider wave action due to storms. AKRF
utilized the historical flood information with the predicted amount of parking spaces lost, and discussions
with the Village to set the DFE at the projected 2080 LiMWA elevation of 5.9 ft (NAVD88).
Table 2. Parking and Structures Impacted Based on Flood Elevations
Elev
(ft - NAVD88)
Parking Spaces
Impacted
Structures / Buildings
Impacted
9/20/2024 Event
3.73
MHHW
Existing
2.07
2020 SLR
2.57
2050 SLR
3.40
2080 SLR
4.40
LiMWA
Existing
3.57
2020 SLR
4.07
2050 SLR
4.90
2080 SLR1
5.90
1) Selected DFE for Flood Mitigation Alternatives
Croton-Harmon Train Station Parking Lot – Shoreline Resiliency and Flood Mitigation 05/23/25
Figure 3: MHHW and LiMWA for existing conditions and 2020, 2050, & 2080 SLR
Flood Mitigation Alternatives
After determining a DFE, AKRF developed three alternatives to mitigate the flooding: 1) non-construction
measures focusing on operational strategies, 2) raise the parking lot elevation to reduce flood risk, and 3)
knee wall installation for structural flood protection. These options are described below and in Table 3.
Option 1- Non-Construction Measures Focused on Operational Strategies (“Do-Nothing”)
The do-nothing approach represents no significant capital improvements to mitigate flooding at the
site in the short term before an option with significant capital investment is needed. AKRF
recommends this approach only in the short term while the recommended solution is designed and
constructed. Signs and barriers would be deployed to restrict access to areas of the parking lot
temporarily, prior to anticipated flooding events, or permanently. By the end of the 2020’s,
approximately 70 parking spaces would be impacted by LiMWA elevations. The do-nothing/non-
construction option includes deploying signage and barriers before high tide events and
permanently abandoning 32 parking spaces that are currently in the existing LiMWA area. Sites
closer to the marsh at lower elevations should be the priority in closing prior to projected flooding.
This option is easy to implement, with low costs, but requires active monitoring of water levels in
the Hudson. The Battery has a predictive tide gauge, so the Village would use that as a prediction
tool.
Croton-Harmon Train Station Parking Lot – Shoreline Resiliency and Flood Mitigation 05/23/25
Option 2 - Raise Parking lot with Fill
Option 2 would raise the elevation of the entire parking lot to the prosed DFE. Option 2 would raise
the elevation of the parking lot using traditional fill, like what was completed in 2009. The drainage
system would need to be evaluated and potentially elevated to ensure that the site can properly
drain during high tide events. While this option is comparatively simpler than other options, it does
not address the settling issue that resulted from the 2009 improvements. The site will be designed
for a 2080 DFE, settling would likely continue to occur and reduce the effectiveness of the design
and increase the risk of nuisance flooding over time.
Another alternative that addresses the site setting is to replace some of the existing soil with
lightweight fill to raise the elevation of the parking lot to the proposed DFE. Light weight fill is more
expensive than standard fill. Because the lightweight fill is less dense than the existing soil, it would
impart a reduced load from the current conditions. This will require testing of excavated soils for
contamination before being. Settling at the site would likely still occur, but not at the rate expected
with standard fill. Using light weight fill would be more complicated as lightweight fill will need to be
designed to counteract buoyancy and wrapped in a geotextile to prevent siltation overtime.
Both options would require wetland permitting. Permitting is needed due to the physical disturbance
of land within the 100’ buffer of a freshwater wetland. The impervious area within the wetland buffer
will be reduced for both options by adding a stabilized embankment at the edge (currently gabion
baskets). This would reduce parking by approximately 100 spaces. Since the parking lot and the
stormwater system are being elevated, the revised stormwater design will be retrofitted with water
quality treatment devices to improve the water quality leaving the site. These improvements to the
design would help facilitate an easier permitting approval process.
For construction, both options would require a thoughtful construction phasing approach to
minimize the disruption and access to parking spaces at a given time. This can be done by breaking
the project limits into 3 to 4 stages where only portions of the 10 acres are excavated at a time.
However, there would still be major disturbances to parking during construction. To help with the
permitting process, the 100’ wetland buffer could be staged separately to mitigate potential issues.
Option 3 – Knee Wall
Option 3 presents a proactive and resilient flood mitigation strategy that includes the construction
of a knee wall along the parking lot's perimeter. On average, the knee wall would be 2 ft high (based
on the existing pavement elevation) and have a total length of approximately 1,200 ft. The knee
wall would terminate at points along the shoreline that are equal to the DFE, such that there is a
contiguous barrier to prevent flooding of the parking lot. To ensure long-term stability, the wall would
be supported by deep foundations (e.g. piles, steel sheeting, etc.) to minimize potential settling.
The drainage system would mostly stay the same; however, the outfalls below the knee wall would
require protection or resetting during construction. For rain events that occur in the future, flooding
could still occur on the site if the storm event coincides with a high tide event. To further enhance
the site’s resilience, a new pumping system will be required to manage stormwater during high tide
events.
While more complex than Options 1 and 2, the construction and design of knee wall offers a robust
and long-term flood protection solution. This approach includes structural design support for the
deep foundations and knee wall as well as the inclusion of multiple pumping stations with additional
piping and structures. Construction of this option involves limited closures of portions of Lot I along
the lot perimeter to excavate the edge of the parking lot, install deep foundations to support the
knee wall, install the structural concrete knee wall, install the pumping stations, and install
associated piping to connect the existing drainage network to the stormwater pumps. Although
some parking spaces will be temporarily unavailable during construction, the number of spots
impacted is expected to be significantly lower than in Option 2 and will ultimately depend on final
design details and staging requirements.
Croton-Harmon Train Station Parking Lot – Shoreline Resiliency and Flood Mitigation 05/23/25
This option will require wetland permits due to the knee wall’s location within the freshwater wetland
buffer. However, by driving the piles from the parking lot side, additional permitting for in-wetland
work can be avoided, helping to streamline the approval process.
Table 3. Comparison of Flood Mitigation Options
Criteria
Option 1-
“Do
Nothing”
Option 2-
Normal Fill
Option 3-
Knee Wall
Loss of Permanent
Parking
High
None
None
Risk Reduction
Low
Medium
Medium
Impact to Operations
During Construction
None
High
Medium
Environmental/
Permitting
Requirements
None
Medium
Medium
Maintenance
Low
Medium
Medium
Capital Costs
Low
High
Medium
Preferred Alternative
Based on the previously described options and discussions with the Village, Option 3 was selected as the
preferred alternative (Appendix A). It provides effective protection against future tidal flooding while
minimizing disturbance to the existing parking lot. An additional concept—construction of a five-story
parking garage with elevated entrances above the 100-year floodplain—was also discussed but not
advanced for further analysis. This concept is included for reference in Appendix B.
A rough order of magnitude estimate of the Option 3 alternative is provided below.
Item
Quantity Unit
Unit Price
Total
Notes
Knee Wall
Steel Sheeting
60,000 SF
$
3,600,000
$
50' Deep for 1,200 LF
Concrete Wall
300 CY
$
240,000
$
7'H x 1'D x 1,200' L
Drainage Improvments
Manholes
8 EA
7,000
$
56,000
$
Overflow Piping
800 LF
$
240,000
$
Tideflex Valves
5 EA
7,000
$
35,000
$
Pump Stations
3 EA
100,000
$
300,000
$
4,471,000
$
670,650
$
1,788,400.0
$
6,930,050
$
Subtotal
Design & Permitting (15%)
Contingency (40%)
Order of Magnitude Total
Croton P
th Hudson Line
ne
Metro North Hudson Line
Croton Point Ave
Metro North Hudson Line
Metro North Hudson Line
Croton P
oint
Ave
Metro North Hudson Line
Wayne St
Briarcliff Peekskill Pkwy N
Briarcliff Peekski
ll Pkwy S
Croton Point Ave
Gateway Plz
Briarcliff P
eekskill Pkwy N
Briarcliff Pe
ekskill Pkwy S
Gateway Plz
Metro North Hudson Line
Gateway Plz
Metro North Hudson Line
Metro North Hudson Line
Croton Harmon
Station
Metro North Hudson Line
Metro North Hudson Line
Wayne St
Briarcliff Peekskill Pkwy N
Briarcliff Peekskill Pkwy
S
Briarcliff Peekskill Pkwy N
Briarcliff Peekskill Pkwy S
Gateway Plz
Gat
eway Plz
Metro North Hudson Line
Metro North Hudson Line
Gateway Plz
Metro North Hudson L
Metro North Hud
G
atewa
Gateway Plz
Bria
Briarcliff P
eekskill Pkwy
55 55
Esri Community Maps Contributors, County of Westchester, © OpenStreetMap, Microsoft, Esri, TomTom, Garmin, SafeGraph, GeoTechnologies, Inc, METI/NASA, USGS, EPA, NPS, US Census Bureau, USDA, USFWS
34 South Broadway, Suite 300, White Plains, NY 10601
1 Van Wyck Street, Croton-On-Hudson, NY, 10520
CROTON-HARMON TRAIN STATION PARKING LOT
SHORELINE RESILIENCY AND FLOOD MITIGATION STUDY
VILLAGE OF CROTON-ON-HARMON
DATE
PROJECT NO.
FIGURE
3/27/2025
SK-2
Document Path: W:\Projects\240624 - SHORELINE RESILIENCY (CROTON-ON-HUDSON)\Drawings\GIS\Croton.aprx Date Saved: 3/26/2025 4:51 PM Author:
LEGEND
Storm Pipe
Discharge Point
Catch Basin
FEMA 100-yr Floodplain
2019 Contours
AKRF, Inc. Environmental Consultants
c
o
37.5
Feet
FLOOD WALL OPTION
1,200 FT FLOOD
PROTECTION KNEE WALL
TOP OF WALL: 6.0'
PROVIDE TIDEFLEX VALVES
AT ALL EXISTING AND
PROPOSED OUTFALLS
PROVIDE OVERFLOW
CONNECTIONS FROM
EXISTING PARKING
LOT DRAINAGE TO
NEW PUMP STATIONS
TIE WALL INTO EXISTING
GRADE AT EL. 6.0'
TIE WALL INTO EXISTING
GRADE AT EL. 6.0'
APPENDIX A
APPENDIX B
Machine-extracted for search and reference — the original PDF is the authoritative version.