Prior to installation of the canopies, the birds did so using the surface of the blacktop. 2 DPW solar canopy: Because the adjacent rooftop already has a rooftop solar
installation (from 2020), Con Ed is requiring the canopy project to file a CESIR…
The DPW solar canopy project faces a more significant delay. Con Edison is requiring a Coordinated Electric System interconnect Review (CESIR) because an adjacent rooftop solar installation from 2020 already exists on the property. Rivertown Solar ch…
On solar, Con Edison gave the train station canopy project permission to operate on May 10, and the project was featured in a SUNY Binghamton graduate student's thesis on that school's solar options. For the planned solar canopy at the Department of …
Bryan Healy OKed that solution. 2 E-bikes: Len said that in the 24 days since the
program re-started on 4/6/26, 210 e-bike rides were
logged. On 5/2/26, the Senasqua Park bike station
opened (see pic). Another site (at the base of the
overpass on…
Commissioning of the entire system (canopies and batteries) was almost done when Con
Ed found an outdated nameplate on one of the BESS inverters, requiring replacement. Once done, Con Ed will issue its formal Permission To Operate (PTO), hopefully v…
No decision has been made. ## Solar Canopies and DPW Project
The train station solar canopies are close to commissioning. After a dead Canadian goose was removed from the site earlier in April, Con Ed discovered an outdated nameplate on one of the b…
Con Ed’s formal Permission To Operate (PTO) should follow in early April. A dead
Canadian goose was found atop canopy #3, facing the 2nd floor east window in the train
station. Due to concerns over possible bird flu, removal has been scheduled with…
- Solar Projects/Issues
Train station canopies: Third-party commissioning is underway. It should be finished by
our March meeting, with full operation of the system thereafter.
DPW solar canopy: Rivertown Solar’s bid (already accepted by the Villa…
WHEREAS this project is to be funded through grants awarded to the Village by the
New York State Energy Development and Research Authority (NYSERDA), and
WHEREAS two bids were submitted by the deadline of December 8, 2025, and
WHEREAS the lowest re…
Whereas the village issued an invitation to bid on 11/20/2025 for the installation and commissioning of a solar canopy at the DPW garage, and whereas this project is to be funded through grants awarded to the village by the New York State Energy Deve…
The separate DPW solar canopy project is also moving forward. Rivertown Solar is securing a ~$39K NY-SUN incentive, has performed test borings for foundation work, filed for interconnection with Con Ed, and will soon order the canopy kit. The goal is…
The DPW solar canopy project faces a more significant delay. Con Edison is requiring a Coordinated Electric System interconnect Review (CESIR) because an adjacent rooftop solar installation from 2020 already exists on the property. Rivertown Solar ch…