DPW Garage
Location
5 mentions
· 2026-02-04
Related
Appearances (6)
Croton's Board of Trustees took a major step toward renewable energy on February 4, awarding a $302,940 contract to Rivertown Solar of Dobbs Ferry for the installation of a solar canopy at the DPW Garage. The project, funded entirely through NYSERDA …
Whereas the village issued an invitation to bid on 11/20/2025 for the installation and commissioning of a solar canopy at the DPW garage, and whereas this project is to be funded through grants awarded to the village by the New York State Energy Deve…
The comment came after trustees heaped praise on Balby and his crew following a tour of the DPW garage, with one trustee calling it "the friendliest DPW crew I've ever seen in my life" and another marveling at the organization, including the cots lin…
Alright. Good evening, and welcome to our January 14 work session. Our first item of business is a discussion with, Frank Balby, regarding the DPW Garage and DPW operations.
Mayor Brian Pugh had a rare definitive answer: the industrial tenant's lease was renewed for more than five years, so "there will not be a change in use for the remainder of this decade."
On the sustainability front, the village is switching all die…
Thank you, mayor. To start with the question that was raised during the public comment period, as I detailed a little bit in my memo, we are switching over all of our diesel vehicles to the renewable diesel, fuel that, we have been piloting for the p…