Agenda item: Public Hearing — Public hearing on the special permit application for the installation of an integrated energy system at Croton Auto Park, 1 Municipal Place.
Application, 5 pages. Attached to agenda item: “Public Hearing — Public hearing on the special permit application for the installation of an integrated energy system at Croton Auto Park, 1 Municipal Place.”
Retrieved 2026-04-15 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
06-23-2024-13551-Croton Auto Mall Electrical Set
1 Municipal Place Croton Auto Park -survey
August 21st Resolution 168-2024 Schedule Public...
Auto Park Solar Special Permit Application
CRO 24-005 Croton Auto Park Battery Energy Storage...
Cover Letter for Croton Board of Trustees
Cover letter for Croton Board of Trustees meeting 8.21.24
Croton Auto Mall Site Plan 6-21-24
Crton Auto Mall Site Power Plan rev 8-16-24
LOA from Lou Giordano
Memo from PB to VB
September 11th Resolution 174-2024 1 Municipal Pl...
Extracted text
Presentation on Croton Auto Park Integrated
Energy Project: September 11, 2024
Sprocket Power
2 Depot Plaza
Bedford Hills, NY 10507
Peter Fazio, Project Manager
Ben Kriegler, VP Sales
Croton Auto Park Project Background
•
The project proposed is an integrated energy system to be installed at Croton Auto
Park at 1 Municipal Place in Croton-on-Hudson.
•
The system, called a Managed Microgrid, encompasses several components including
the following:
➢Electrical Vehicle charging – one DC Fast Charger (DCFC) with 180 kW capacity,
two L2 wall-mount chargers. 19.2 kW capacity
➢New utility transformer – one 480V 500 kVA, plus one 208 V 150 kVA step
down transformer
➢Solar canopy: 20 x 24ft, 20 kW DC output
➢Battery Energy Storage System (BESS) – 125 kW capacity, 280 kWh energy
output
➢Associated Electrical Combiner Panel
Croton Auto Park Project Background
•
The capacity of the battery - 280 kWh, above the 200 kWh threshold – necessitates a
Special Use Permit and Board of Trustees review.
•
The EV charger installation is required by the auto manufacturer, Stellantis, for the
business to be authorized to sell electric vehicles.
•
The balance of the system components are being pursued to reduce utility costs and
decrease the facilities carbon emissions.
•
This installation includes one powerful DCFC capable of charging a car from empty in
under 30 minutes. The power requirements of this charger necessitate an upgrade to
the current Con Edison utility service feeding the building from 208V to 480V. The
total cost of this required upgrade and associated electrical work is roughly $400,000.
Croton Auto Park Project Review Process
•
Following a Planning Board meeting on August 6, 2024, where we received negative
feedback on the placement of the electrical equipment along the road frontage, we
revised the site plan as follows:
•
Relocated the BESS, and other non-utility equipment to a location near the
proposed solar canopy car port and EV charging.
•
We also approach Con Edison regarding flexibility on the location of the utility
transformer. We worked with the Con Ed engineering team to also locate the
transformer adjacent to the canopy towards the back of the lot with reduced
visibility from the road.
•
We and the business owner are pleased with this outcome and with the collaboration
between town goals, system requirements and Con Edison constraints.
Croton Auto Park Project Benefits:
•
As NY State works to install charging infrastructure statewide, the power
requirements of DCFCs are an issue as they strain the capacity of the local grid.
•
Unmanaged additions of DCFC could create large capacity upgrade requirements for
Con Edison, which cause delays in transportation electrification due to the buildout of
this infrastructure, are costly for rate payers and work against NYS climate goals.
•
NY State is looking to create smarter approaches to these EV infrastructure issues. The
proposed project at Croton Auto Park is a model for such an approach.
•
This system generates solar energy to 1) offset building energy uses and 2) store
energy in a BESS. This stored energy is used to supply the EV chargers and to offset
peak usage. The result is a project that reduces grid strain, serves as a resource of the
local grid, and reduces GHG emissions at the site. The site will be a case study for Con
Edison of smart approaches to EV infrastructure additions.
•
The project will contribute significantly to Croton on Hudson sustainability goals and
also represents a significant investment by Croton Auto Park in the community.