you. I think these are all really, really good questions because it sounds like a great thing to move forward on, but these are contingencies that, again, I appreciate Ana and Omar, your expertise in both of these areas to just highlight, the things …
The solar canopies at the train station are going through their final performance testing before being, excuse me, before being officially determined to be commercially operational. The project owner expects that to occur later this month or in early…
On the solar front, the long-awaited commissioning of the train station solar canopies and Battery Energy Storage System (BESS) is slated for completion by the end of December. However, plans for a second, larger BESS behind the Municipal Place facil…
You know, they're also, as part of that process, they've agreed to replace the generator that powers this building in need you know, when it's needed. So that is going to be a significant cost savings for the village because that generator was nearin…
Village Manager Healy advised that we continue to look at ways to try to slow
down traffic on Glengary Road, one is the installation of 15 mile per hour speed
signs, speed monitoring devices as well as reaching out to the community
reminding them of …
- Funding and Budgeting Issues
No new financial issues. The present focus is to push projects toward installation
before their incentives (e.g., NY-SUN, DirectPay) are lost due to bureaucratic delays.
We reviewed a possible new revenue source for fut…
Resolution #222-2025
On motion of TRUSTEE SIMON, seconded by TRUSTEE NICHOLSON, the following
resolution was adopted by the Board of Trustees of the Village of Croton-on-Hudson,
New York with a 5-0 vote.
WHEREAS, the Village of Croton-on-Hudson has…
Meanwhile, major infrastructure projects at the train station are moving forward. Excavation for 18 new EV charge ports—handled by contractor PISO—is slated to begin in early March, requiring a new 100-300 kVA pole-mounted transformer. Additionally, …
Pete Harckham and Assemblywoman Dana Levenberg to press DEC for an answer.
In the meantime, work with the contractor PISO is proceeding slowly. An issue has surfaced over the interconnection point to an adjacent 13.2 kV overhead power line: to minim…
No decision has been made. ## Solar Canopies and DPW Project
The train station solar canopies are close to commissioning. After a dead Canadian goose was removed from the site earlier in April, Con Ed discovered an outdated nameplate on one of the b…
Pugh also participated in a Business Council of Westchester clean energy panel on April 14 in Ossining, where he and Leo Wiegman of Sustainable Westchester later led about 20 attendees on a tour of Croton's solar canopies and BESS installation.
## F…
## Solar Projects Hit Snags
The train station solar canopies need minor repairs this summer, including replacing panels cracked by large birds dropping seashells onto them — a behavior the birds previously performed on the blacktop before the canopi…
On the solar front, the long-awaited commissioning of the train station solar canopies and Battery Energy Storage System (BESS) is slated for completion by the end of December. However, plans for a second, larger BESS behind the Municipal Place facil…