Modifications of the Plan of the New Croton Dam
The great increase in the cost of the work is due principally to the four above de- scribed additions and modifications namely : the extra depth excavated under the main stone dam , the first ex- tension of 110 feet of the main stone dam , the extension of the main stone dam necessitating the removal of the embankment and core wall and lastly the additional ex- cavation necessary for the foundation of the last exten- sion . Some idea of what these changes have necessitated may be gained from the consideration of but two items , that of the amount of earth excavation which will be trebled and that of the amount of masonry which will be increased from 550,000 to about 800,000 cubic yards . The value of the work done to March 1 , 1904 is $ 5,363,000 . This most important of all structures to this great city , upon which its welfare would be almost wholly depend- ent , had to be mantled with all possible safeguards against its destruction . Thus the writer being brought face to face with the one paramount necessity that of the safety of this structure , was left no alternative but to modify the plan . Gaylord GAYLAMOUNT PAMPHLET BINDER Syracuse , N.Y. Stockton , Calif .
=== seq 17 ===
feet , would not have sufficient strength to resist the water pressure that would come against them , and their de- struction might result in a great losss of water from the reservoir and the demolition of the embankment , by the rush of water in falling a height of 150 feet to reach the valley below . On Dec. 18 , 1902 , on the writer's recom- mendation the Aqueduct Commissioners approved a plan providing for the reinforcement of these walls .