EAF for Stretch Code
resolution
3 pages
From the meeting:
Board Of Trustees — 2022-06-21
Agenda item: Proposed Resolutions — Consider adopting EAF Parts 2 and 3 Determination of Significance attached hereto, adopting a Negative Declaration under SEQRA and a statement of consistency with the Village's LWRP in connection with adopting Local Law Introductory No. 7 of 2022 as drafted for such purposes.
Resolution, 3 pages. Attached to agenda item: “Proposed Resolutions — Consider adopting EAF Parts 2 and 3 Determination of Significance attached hereto, adopting a Negative Declaration under SEQRA and a statement of consistency with the Village's LWRP in connection w”
Retrieved 2026-07-31 from the village's meeting portal.
View the original PDF ↗
Also attached to this agenda item:
CAF for Stretch Code
EAF Part II and Part III
Energy Code Memo
LWRP LL Intro 7
Local Law Intro 7 of 2022 NYStretch
NY State Stretch Code Planning Board Memo
NYS Stretch for Residences-Summary and FAQ -...
NYStretch-Energy-Code-2020 3
NYStretch-Energy-Code-2020 Comparison
Res 100-2022 LL Intro 7 Adoption
Res 62-2022 LL Intro 7 PH
WAC Memo on NYStretch Code 2022
Extracted text
Part 1 – Project Information. The applicant or project sponsor is responsible for the completion of Part 1. Responses become part of the
application for approval or funding, are subject to public review, and may be subject to further verification. Complete Part 1 based on
information currently available. If additional research or investigation would be needed to fully respond to any item, please answer as
thoroughly as possible based on current information.
Complete all items in Part 1. You may also provide any additional information which you believe will be needed by or useful to the
lead agency; attach additional pages as necessary to supplement any item.
Project Location (describe, and attach a location map):
E-Mail:
State:
1.
Does the proposed action only involve the legislative adoption of a plan, local law, ordinance,
administrative rule, or regulation?
If Yes, attach a narrative description of the intent of the proposed action and the environmental resources that
may be affected in the municipality and proceed to Part 2. If no, continue to question 2.
NO
YES
2.
Does the proposed action require a permit, approval or funding from any other government Agency?
If Yes, list agency(s) name and permit or approval:
NO
YES
3.
a. Total acreage of the site of the proposed action?
c. Total acreage (project site and any contiguous properties) owned
or controlled by the applicant or project sponsor?
4.
Check all land uses that occur on, are adjoining or near the proposed action:
Aquatic
Other(Specify):
□ Urban
□ Forest
SEAF 2019
Parkland
Adoption of Local Law Introductory No. 7 of 2022
Village-wide
The Village of Croton-on-Hudson would like to amend Chapter 86 of the Village Code, Building Construction, to adopt the NYStretch Energy Code.
5.
a.
b.
NO
YES
N/A
6.
Is the proposed action consistent with the predominant character of the existing built or natural landscape?
NO
YES
7.
Is the site of the proposed action located in, or does it adjoin, a state listed Critical Environmental Area?
NO
YES
8.
a. Will the proposed action result in a substantial increase in traffic above present levels?
b.
Are public transportation services available at or near the site of the proposed action?
c.
Are any pedestrian accommodations or bicycle routes available on or near the site of the proposed
action?
NO
YES
9.
Does the proposed action meet or exceed the state energy code requirements?
If the proposed action will exceed requirements, describe design features and technologies:
NO
YES
10. Will the proposed action connect to an existing public/private water supply?
If No, describe method for providing potable water: _________________________________________
_____________________________________________________________________________________________
NO
YES
11. Will the proposed action connect to existing wastewater utilities?
If No, describe method for providing wastewater treatment: ______________________________________
_____________________________________________________________________________________________
NO
YES
archaeological sites on the NY State Historic Preservation Office (SHPO) archaeological site inventory?
NO
YES
13. a. Does any portion of the site of the proposed action, or lands adjoining the proposed action, contain
wetlands or other waterbodies regulated by a federal, state or local agency?
b. Would the proposed action physically alter, or encroach into, any existing wetland or waterbody?
If Yes, identify the wetland or waterbody and extent of alterations in square feet or acres: _____________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
NO
YES
12. a. Does the project site contain, or is it substantially contiguous to, a building, archaeological site, or district
which is listed on the National or State Register of Historic Places, or that has been determined by the
Commissioner of the NYS Office of Parks, Recreation and Historic Preservation to be eligible for listing on the
State Register of Historic Places?
b. Is the project site, or any portion of it, located in or adjacent to an area designated as sensitive for
14. Identify the typical habitat types that occur on, or are likely to be found on the project site. Check all that apply:
15. Does the site of the proposed action contain any species of animal, or associated habitats, listed by the State or
Federal government as threatened or endangered?
NO
YES
16. Is the project site located in the 100-year flood plan?
NO
YES
17. Will the proposed action create storm water discharge, either from point or non-point sources?
If Yes,
a.
Will storm water discharges flow to adjacent properties?
b.
Will storm water discharges be directed to established conveyance systems (runoff and storm drains)?
NO
YES
18. Does the proposed action include construction or other activities that would result in the impoundment of water
or other liquids (e.g., retention pond, waste lagoon, dam)?
If Yes, explain the purpose and size of the impoundment:______________________________________________
____________________________________________________________________________________________
_
NO
YES
19. Has the site of the proposed action or an adjoining property been the location of an active or closed solid waste
management facility?
NO
YES
20.Has the site of the proposed action or an adjoining property been the subject of remediation (ongoing or
completed)
NO
YES
I CERTIFY THAT THE INFORMATION PROVIDED ABOVE IS TRUE AND ACCURATE TO THE BEST OF
MY KNOWLEDGE
Date: _____________________
Applicant/sponsor/name: ____________________________________________________ __________________________
Signature: _____________________________________________________Title:__________________________________
Bryan Healy
5/13/2022
Village Manager
PRINT FORM